2025 Supreme(Online)(CERC) 225

CENTRAL ELECTRICITY REGULATORY COMMISSION
Shri Jishnu Barua, CJ, Shri Ramesh Babu V., Member
Approval under Regulation 86 of the Central Electricity Regulatory Commission (Conduct of Business) Regulations 1999 and the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations 2019 for the determination of transmission tariff from the COD to 31.3.2024 for Asset-I: 1x500 MVA 400/220 kV ICT (3rd) along with the associated bays and 2 Nos. 220 kV Bus Sectionalizer Bay (Hybrid/MTS) at Indore (POWERGRID) Sub-station and Asset-II: 1 No. 220 kV Hybrid/MTS Line Bay at Indore Sub-station under “Connectivity and LTA for 325 MW Wind Project of M/s SBESS Services Projects Private Limited” in Western Region. Power Grid Corporation of India Limited
Petition No. 33/TT/2023



Advocates:
For the Appellants/Petitioners: Ms. Swapna Seshadari, Shri Utkarsh Singh, Ms. Sneha, Shri Mohd. Mohsin, Shri Zafrul Hassan, Shri Divyanshu Mishra
For the Respondents: Shri Ravi Sharma, Shri Anup Jain, Shri Hemant Singh, Shri Sanjeev S. Thakur, Shri Gandharv Garg, Shri Pawan Singh, Shri Lakshyajit Singh Bagdwal, Shri Mohd. Mohsin

The determination of transmission tariff requires strict adherence to regulatory frameworks, with liabilities for mismatch periods attributed to the generator. Exemptions for delays due to force majeure are narrowly defined and do not absolve financial responsibilities.

Headnote:(A) Central Electricity Regulatory Commission (Conduct of Business) Regulations, 1999; Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 - Determination of transmission tariff - Petition filed for approval of transmission tariff from commercial operation date (COD) of Assets I and II to 31.3.2024 - COD of Asset-I approved as 29.4.2022; COD of Asset-II approved as 30.4.2022 - Petitioner established that plans for Assets were discussed in regulatory meetings, with necessary approvals obtained - Claims of delay in commissioning attributed to external factors including pandemic - Key legal principles determined relate to operational readiness of transmission assets, eligibility for tariff recovery and liability for mismatch period - Transmission charges to be borne by the generator during the mismatch period and shared among beneficiaries thereafter as per applicable regulations. (Paras 10, 34, 97, 132, 136)

(B) Regulations on Transmission Charges - Compliance with regulatory frameworks governing the recovery and calculation of transmission charges critical to avoid disputes among stakeholders. (Paras 104, 128)

(C) Appeals and Submissions - Petitioner’s claims challenged by different respondents regarding beneficiary definitions and responsibilities under long-term access agreements, clarifying roles and liabilities in the tariff determination process. (Paras 89-90, 96)

(D) Emergency provisions and force majeure - Petitioner unable to claim exemption from charges due to delays attributed to unrelated force majeure events - Regulatory clarity upheld. (Paras 104, 120)

ORDER

The Petitioner, Power Grid Corporation of India Limited, has filed the instant Petition for the determination of transmission tariff under the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 (hereinafter referred to as “the 2019 Tariff Regulations”) from the commercial operation date (COD) to 31.3.2024 for Asset-I: 1x500 MVA, 400/220 kV ICT (3rd) along with the associated bays and 2 Nos. 220 kV Bus Sectionalizer Bay (Hybrid/MTS) at Indore (POWERGRID) Sub-station, and Asset-II: 1 No. 220 kV Hybrid/MTS Line Bay at Indore Sub-station (hereinafter referred to as “the transmission assets”) under the “Connectivity and LTA for 325 MW Wind Project of M/s SBESS Services Projects Private Limited” (hereinafter referred to as “the transmission project”) in the Western Region.

2. The Petitioner has made the following prayers:

“1) Condone the delay in the commissioning of assets covered under this petition.

2) Approve DOCO of Asset-2 as 30.04.2022 and allow to recover the tariff of the mismatch period from SBESSSPTPL.

3) Approve the Transmission Tariff for the tariff block 2019-24 block for the assets covered under this petition, as per para8.0 above.

4) Admit the capital cost as claimed in the Petition and approve the Additional Capitalization incurred / projected to be incurred.

5) Allow the petitioner to recover the shortfall or refund the excess Annual Fixed Charges, on account of Return on Equity due to change in applicable Minimum Alternate/Corporate Income Tax rate as per the Income Tax Act, 1961 (as amended from time to time) of the respective financial year directly without making any application before the Commission as provided in Tariff Regulation 2019 as per para 8 above for respective block.

6) Approve the reimbursement of expenditure by the beneficiaries towards petition filing fee, and expenditure on publishing of notices in newspapers in terms of Regulation 70 (1) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019, and other expenditure (if any) in relation to the filing of petition.

7) Allow the petitioner to bill and recover Licensee fee and RLDC fees and charges, separately from the respondents in terms of Regulation 70 (3) and (4) Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019.

8) Allow the petitioner to bill and adjust impact on Interest on Loan due to change in Interest rate on account of floating rate of interest applicable during 2019-24 period, if any, from the beneficiaries.

9) Allow the Petitioner to bill and recover GST on Transmission Charges separately from the respondents, if GST on transmission is levied at any rate in future. Further, any taxes including GST and duties including cess etc. imposed by any statutory/Govt./municipal authorities shall be allowed to be recovered from the beneficiaries.

10) Allow interim tariff in accordance with Regulation 10(3) of Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019 for purpose of inclusion in the PoC charges.

and pass such other relief as Hon’ble Commission deems fit and appropriate under the circumstances of the case and in the interest of justice.”

Background

3. The brief facts of the case are as follows:

a. The Investment Approval (IA) of the project was accorded by the competent authority of the Petitioner on 10.7.2021, vide Memorandum No. C/CP/PA2122-04-0I- IA008 dated 12.7.2021, with an estimated cost of ₹4465 lakh, including Interest During Construction (IDC) of ₹99 lakh based on the December 2020 price level.

b. The transmission project was approved in the 2nd meeting of the Western Regional Power Committee on Transmission Planning (WRPCTP) held on 4.9.2020, and the 4th meeting of the National Committee on Transmission (NCT) held on 20.1.2020 and 28.1.2020.

c. The Long Term Access (LTA) was granted to Respondent No. 9, M/s SBESS Services Project Two Private Limited (hereinafter referred to as

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top