SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

HIGH COURT OF CHHATTISGARH AT BILASPUR


2026:CGHC:14187-DB


ARBA No.40 of 2020, ARBA No.36 of 2020, ARBA No.39 of 2020, ARBA No.42 of 2020, ARBA No. 37 of 2020, ARBA No.41 of 2020



State Of Chhattisgarh Through The Chief Executive Officer, Chhattisgarh Rural Road Development Agency, Vikas Bhawan, Civil Lines, Raipur, Chhattisgarh


versus


Gilcon Project Service Ltd. J.V. Scapes Associates, Thacker Tower, Plot No. 86, Sector 17, 1, Vashi Navi Mumbai, Maharashtra



For State: Mr. Avinash Singh, GA


For Gilcon Project Service Ltd: Mr. Ankit Pandey, Advocate



Hon’ble Smt. Justice Rajani Dubey


Hon’ble Shri Justice Radhakishan Agrawal

Advocates:
For the Appellants/Petitioners: Avinash Singh, Ankit Pandey
For the Respondents: Avinash Singh, Ankit Pandey

The scope of judicial interference under Section 34 of the Arbitration and Conciliation Act is extremely limited; courts should not sit in appeal on facts or re-appreciate evidence unless the award suffers from specific legal infirmities or patent illegality appearing on the face of the record.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34, 37 - Scope of interference - Appellate court should not re-appreciate evidence or act as a court of appeal on facts but should restrict review to grounds enumerated in Section 34 (Paras 10, 13, 14)

(B) Arbitration Award - Interest - Award for admitted amount being withheld by the State requires grant of interest - Court granted interest at 6% per annum from date of completion of contract until realization (Para 21)

Facts of the case:
Multiple arbitration appeals arose from common orders passed by the Commercial Court and the Sole Arbitrator regarding two contract agreements executed on 23.10.2007. The State sought to set aside the arbitral award, while the contractor sought interest on claims allowed by the Commercial Court.

Findings of Court:
The Court dismissed the appeals filed by the State, finding no illegality or perversity in the Commercial Court's order. It allowed the contractor's appeals specifically to award interest on the admitted amounts withheld by the State.

Issues: The main issues were whether the arbitral award was against public policy or perverse, whether the court could re-appreciate evidence under Section 34, and whether the respondent was entitled to interest on withheld admitted amounts.

Ratio Decidendi: An arbitral award can only be set aside on limited grounds specified under Section 34. Appellate courts under Section 37 cannot act as a court of first appeal or undertake independent assessment of evidence. If an award is silent on interest for admitted amounts, the Court may grant reasonable interest in the interest of justice.

Result: State's appeals dismissed, Contractor's appeals allowed with award of interest.

The date when the judgment is reserved The date when the judgment is pronounced The date when the judgment is uploaded on the website
20.02.2026 25.03.2026 Operative: -- | Full: 25.03.2026

CAV Judgment

Per Rajani Dubey. J.

1. The present batch of arbitration appeals arise out of common order passed by the learned Commercial Court as well as the learned Arbitrator, as such the same have been clubbed together, heard together and are being disposed of by a common order.

2. The arbitration appeals i.e. ARBA Nos.36, 37, 39 & 40 of 2020 have been preferred by the State seeking setting aside the common order dated 29.02.2020 passed by the learned Commercial Court as well as the common arbitral award dated 31.08.2018 passed by the learned sole Arbitrator, whereas ARBA Nos.41 & 42 of 2020 have been preferred by the Gilcon Project Service Ltd against the common order dated 29.02.2020 passed by the learned Commercial Court seeking interest on the amount claimed before it.

3. Brief facts of the case are that two contract agreements, firstly contact agreement bearing No.24/RC-4/CGRRDA dated 23.10.2007 and secondly contract agreement bearing No.25-RC/4/CGRRDA dated 23.10.2007 were executed between the parties. The dispute arose between the parties in relation to both these agreements. Both the matters were referred for adjudication to learned sole Arbitrator pursuant to order of this Court. The dispute arising out of agreement No.24/RC-4/CGRRDA was registered as Arbitration Application No.7/2014 and the dispute arising out of agreement No.25/RC-4/CGRRDA was registered as Arbitration Application No.6/2014 before the learned sole Arbitrator. The learned sole Arbitrator adjudicated both the matters and passed the common arbitral award dated 31.08.2018. The learned sole Arbitrator treated the Arbitration Application No.6/2014 as the leading case and referred to the pleadings and documents filed in Arbitration Application No.6/14 in the common award. Against the award dated 31.08.2018, both the parties filed petitions under Section 34 of the Arbitration and Conciliation Act before the learned Commercial Court and the learned Commercial Court registered MJC No.40/2018 and MJC No.43/2018 with regard to award related to contract agreement No.25-R-C/4/CGRRDA which is registered as Arbitration Application No.6/14 before the learned sole Arbitrator and MJC No.41/18 and 42/2018 were registered before the learned Commercial Court pertaining to the contract agreement No.24-RC-4/CGRRDA, which is registered as Arbitration Application No.7/14 in MJC No.40/2018. The learned Commercial Court passed a separate order on 29.02.2020, against which 4 appeals have been filed by the State, whereas 2 appeals have been filed by Gilcon Project. For ready reference, the details are described as under:-

Sr. No. Arbitration Appeal No. MJC No. Arbitration Application
1. ARBA No.39/2020 40 & 43 of 2018 6/14
2. ARBA No.40/2020 40 & 43 of 2018 6/14
3. ARBA No.36/2020 41 & 42 of 2018 7/14
4. ARBA No.37/2020 41 & 42 of 2018 7/14
5. ARBA No.41/2020 41 & 42 of 2018 7/14
6. ARBA No.42/2020 40 & 43 of 2018 6/14

4. Learned counsel for the appellant/State submits that there is error apparent on the face of the award and therefore the same is against the public policy because learned Sole Arbitrator as well as the learned Commercial Court travelling beyond the pleadings as well as the documents had recorded a perverse finding in the entire arbitral award. The learned Sole Arbitrator as well as the learned Commercial Court have failed to appreciate and consider the presence of a clear cut provision of Clause 6.5 of General Conditions of Contract. The contract was never foreclosed between the parties and the same was still alive the claimant Gilcon was required to full the conditions of the contract. The Arbitrator, being a creature of contract and has a duty to act within the four corners of the terms and conditions specifically agreed between the p

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top