SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(SC) 259

SUPREME COURT OF INDIA
Abhay S. Oka, Ujjal Bhuyan, JJ.
M/s. C & C Constructions Ltd. – Appellant
Versus
IRCON International Ltd. – Respondent
Civil Appeal No. 6657 of 2023
Decided On : 31-01-2025

Advocates appeared:
For the Appellant(s) : Mr. Vikas Goel, Adv. Mr. Tarun Dua, Adv. Mr. Ritesh Sharma, Adv. Mr. Vivek Gupta, Adv. Mr. Harmanbir Singh Sandhu, Adv. Mr. Pragun Dua, Adv. Mr. Rahul Shyam Bhandari, AOR Ms. G Priyadharshni, Adv. Mr. Satyam Pathak, Adv. Mr. Prabhakar Pahepuri, Adv. Mr. Harsh Vardhan, Adv.
For the Respondent(s): Mr. Gaurav Pachnanda, Sr. Adv. Mr. Sidhant Goel, Adv. Mr. Mohit Goel, Adv. Mr. Shubham S Saxena, Adv. Mr. Karmanya D Sharma, Adv. Ms. Nikita Jaitly, Adv. Ms. Avni Sharma, Adv. Mr. Sahil Tagotra, AOR

Limitation of liability clauses in contracts are enforceable, and acceptance of contract terms precludes subsequent claims for damages.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37 - Appeal against arbitral award - Validity of clause 49.5 of General Conditions of Contract - Clause prohibiting claims for damages upheld - Appellant's claims for damages rejected as barred by contract terms - Extension of time granted without penalty does not entitle additional claims. (Paras 7, 8, 12, 19, 27)

(B) Public Policy - Enforcement of limitation of liability clauses - Parties cannot contract against the provisions of the Indian Contract Act, 1872 - Clause 49.5 valid and enforceable. (Paras 10, 11, 22)

Facts of the case:
The appellant entered into a contract for constructing Road Over Bridges in Rajasthan. Delays were attributed to the respondent, leading to claims for damages which were rejected based on clause 49.5 of the General Conditions of Contract. The appellant invoked arbitration after the claims were dismissed.

Findings of Court:
The court upheld the validity of clause 49.5, ruling that the appellant was estopped from claiming damages after accepting extensions without penalty.

Issues: The main issues were whether clause 49.5 could be enforced and if the appellant could claim damages despite accepting the contract terms.

Ratio Decidendi: The court reasoned that the appellant's acceptance of the contract terms and extensions without penalty barred any subsequent claims for damages, reinforcing the principle that limitation of liability clauses are enforceable.

Result: Appeal dismissed.

Table of Content
1. contract for road over bridges (Para 1 , 2)
2. claims for damages rejected (Para 5 , 6 , 7 , 8 , 9)
3. appellant's claims for damages (Para 10)
4. respondent's defense on clause 49.5 (Para 11)
5. validity of clause 49.5 (Para 12 , 13 , 14 , 15 , 16 , 17 , 18 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28)
6. estoppel from claiming damages (Para 19)
7. appeal dismissed (Para 29)

JUDGMENT

ABHAY S. OKA, J.

FACTUAL ASPECTS

1. This appeal arises out of the impugned judgment and order of the Division Bench of the High Court of Delhi dated 1st March, 2021, which is passed in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, ‘the Arbitration Act’).

2. We refer to a few factual aspects of the case. An agreement dated 28th June, 2012 was entered into between the appellant and the respondent for constructing five Road Over Bridges (for short, ‘ROBs’) and their approaches at different locations in the State of Rajasthan. The schedule of completion in respect of each ROB was different. The locations where ROBs were to be constructed have been described as LC-200, LC-89, LC-228, LC-233 and LC-108. According to the appellant's case, the work at the sites was delayed for the reasons attributable to the respondent. According to the appellant's case, the respondent withdrew the work relating to the construction of two ROBs (LC-200 and LC-233) from the scope of work and certified the completion of the remaining work. There is no dispute that we are not concerned with LC-200 and LC-233 in this appeal. In the case of LC89 and LC-228, the scheduled completion date was 15th September, 2013. For LC-108, it was 16th July, 2013. As per the completion certificate dated 22nd March 2016, the work of LC-89 was completed on 8th October 2014, and the work of LC-228 was completed on 21st March 2015. According to the appellant's case, work at LC-108 was completed on 31st March 2017.

3. On 19th June 2013, the appellant addressed a letter to the respondent's General Manager stating that the construction delay of ROBs at LC-108 was due to various hindrances at the site. By the said letter, the appellant requested the respondent to grant an extension of 264 days. The appellant contended that the delay in construction work has resulted in an additional financial burden on account of the establishment and overheads, etc., for a longer period than planned, for which the appellant would be claiming separately. By the reply dated 14th October 2013, the respondent informed the appellant that the statement of the appellant that it would be claiming separately for financial burden was not acceptable. The respondent stated that the claim would have to be considered along with the prayer for extension. Therefore, the respondent requested the appellant to submit a detailed claim immediately so that the prayer for an extension of time could be considered. Separate letters dated 30th August, 2013 were addressed by the appellant to the respondent regarding LC-89 and LC-228 for grant of extension by 430 and 437 days, respectively. By a letter dated 29th November, 2013, the respondent granted an extension of time as follows:

LC No.

Extension Upto

Penalty

228

20th March, 2014

With Penalty

89

28th February, 2014

With Penalty

108

31st March, 2014

Without Penalty

4. On 28th February, 2014, 09th April, 2014 and 19th April, 2014, the appellant again applied for a grant extension of time regarding LC Nos. 89, 228 and 108, respectively. By a letter dated 24th May, 2014, the respondent granted an extension of time as follows:

LC No.

Extension Upto

Penalty

228

31st January, 2015

Without Penalty

89

30th November, 2014

Without Penalty

108

15th December, 2014

Without Penalty

5. By letters dated 03rd September, 2014, the appellant submitted separate claims concerning

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top