SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Online)(DEL) 11213

HIGH COURT OF DELHI
Dharmesh Sharma, J
DELHI TECHNOLOGICAL UNIVERSITY – Appellant
Versus
MR CHANDER SHEKHAR – Respondent
C.R.P.-155/2023



Advocates:
Ms. Avnish Ahlawat, SC with Ms. Tania Ahlawat, Mr. Nitesh Kumar Singh, Ms. Laavanya Kaushik, Ms. Aliza Alam & Mr. Monish Sehrawat, Advs.; Mr. Jatin Arora, Adv.

The court held that a suit for recovery filed after the limitation period is barred, emphasizing that reminders or RTI requests do not extend the limitation period.

Headnote:(A) Code of Civil Procedure, 1908 - Section 115 - Limitation Act, 1963 - Section 3 - Civil revision petition challenging dismissal of application under Order VII Rule 11(d) - Suit for recovery of Rs. 11,48,324/- filed after limitation period - Court found that the suit was barred by limitation as the cause of action arose in 2013 and suit was filed in 2020 - The trial court erred in not framing an issue on limitation and in holding that there was a continuous cause of action. (Paras 1, 10, 26)

(B) Limitation - The period of limitation for recovery suits is three years from the date the right to sue accrues - Mere issuance of reminders or RTI requests does not extend the limitation period. (Paras 11, 22)

Facts of the case:
The petitioner, Delhi Technological University, challenged the dismissal of its application claiming that the respondent's suit for recovery was barred by limitation as it was filed well after the three-year period following the alleged cause of action arising from work orders issued in 2013. (Paras 1, 10)

Findings of Court:
The court found that the trial court had committed a grave error by not recognizing the suit as barred by limitation and failing to frame an issue on this aspect. (Paras 26)

Issues: The main issues were whether the suit was barred by limitation and whether the trial court erred in its findings regarding the cause of action. (Paras 10, 26)

Ratio Decidendi: The court ruled that the trial court's failure to address the limitation issue was a significant error, and that the respondent's claims did not constitute a continuous cause of action. (Paras 25, 26)

Result: The revision petition was allowed, and the impugned orders were set aside, declaring the suit barred by limitation.

JUDGEMENT

1. This judgment shall decide the instant civil revision petition filed by the petitioner under Section 115 of the Code of Civil Procedure, 1908 1 assailing the impugned order dated 27.08.2022 and consequential order dated 15.11.2022 passed by the learned District Judge (Commercial), Rohini Courts2, New Delhi, in CS(Comm) No. 380/2020 titled as “Mr. Chander Shekhar v. Delhi Technological University” wherein the petitioner’s application under Order VII Rule 11(d) of the CPC read with Section 3 of the Limitation Act, 1963 was dismissed.

1 CPC 2 Trial Court

2. The petitioner herein is the Delhi Technological University3, constituted under the Delhi Technological University Act4, 2009. The financial powers of the University are exercised by the Finance Committee, which is regulated by the Board of Management under Section 23 of the DTU Act and also the financial rules framed by the Government of India are followed by the University from time to time whilst dealing with contracts and other financial matters.

FACTUAL BACKGROUND:

3. The respondent/plaintiff in the present lis filed a Civil Suit (Comm) bearing No. 380/2020 titled as “Mr. Chander Shekhar v. Delhi Technological University” for the recovery of Rs. 11,48,324/- before the Rohini Court, New Delhi on 15.10.2020 in respect of five work orders from 2012-2013, which were purportedly issued by the Project and Estate Officer.

It was contended by the petitioner/defendant that each of the work orders were to be completed in a stipulated period of 15 days, however, the work orders were not completed satisfactorily. The claim by the respondent/plaintiff before the learned Trial Court was that the work orders were completed but the alleged amount sanctioned to them on 21.02.2013 was not released by the petitioner/defendant. The details of the five work orders are reproduced below: -

  • S.
  • No.
  • Name of work Work Order No. & Date Amount of Work Order

1. Replacement & repairing of existing lighting fixtures, fans, DTU/Engg.

Cell/Civil/2012-13/89 Rs. 1,49,460/- 3 University 4 DTU Act switches and providing additional as per requirements etc. in E&C Dept. in DTU dated 07.12.2012

2. Renovation In Deptt.

Of Physics in room SB TF-13 in DTU DTU/Engg.

Cell/Comp/2012- 13/186(2) dated 18.01.2013 Rs.1,51,948/-

3. Floor Tiles and False Ceiling work in Deptt. Of Physics in room SB TF-13 DTU/Engg.

Cell/Comp./2012- 13/186(7) dated 18.01.2013 Rs.1,83,193/-

4. Supplying & fixing collar mic system in Expo Hall & Room No.307 in Admin. Block in DTU DTU/Engg.

Cell/Gen/2012- 13/137/564 dated 31.01.2013 Rs.1,40,060/-

5. Repair and dry cleaning of fixed chairs in Convocation Hall in DTU DTU/Engg.

Cell/Gen/2012-13/127 dated 19.02.2013 Rs.1,67,170/-

4. It was the case of the respondent/plaintiff that he submitted the bills dated 11.02.2013, 24.05.2013 and 14.08.2013 but no monies for the same were released by the petitioner/defendant as they contended that the five work orders were obtained by fraud. It was stated that the petitioner/defendant discovered that Sh. Ratan Singh, Assistant Engineer (Electrical) who was assigned with the task of awarding the work order to the respondent, was the father of the respondent. The respondent in collusion with the Assistant Engineer (Electrical) secured the work orders by falsifying details of M/s Cherub Webs and played fraud upon the petitioner/defendant; and when such facts came to light, the services of Sh. Ratan Singh were terminated w.e.f. 13.11.2013.

5. It appears that the respondent/plaintiff sent demand letters dated 15.06.2018 and 21.07.2018, which were never replied by the petitioner/defendant. It is the case of the respondent/plaintiff that he filed an RTI application dated 21.07.2018 seeking the status of the action taken on the letter dated 15.06.2018, which was replied on 22.10.2018 wherein they stated that “the payment will be made only after scrutiny of bills”.

PROCEEDINGS BEFORE THE LEARNED TRIAL COURT AND THE IMPUGNED ORDERS:

6. On ins

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top