2025 Supreme(Online)(Del) 4381
IN THE HIGH COURT OF DELHI AT NEW DELHI
Jasmeet Singh, J
ADITYA ENERGY HOLDINGS – Appellant
Versus
SUNSURE ENERGY PRIVATE LIMITED AND ANR – Respondent
O.M.P.(I) (COMM.) 305/2025
For the Appellants/Petitioners: Ms. Shalini Kaul
For the Respondents:
The court emphasizes the need to preserve the subject matter of arbitration and prevent parties from transferring rights that may undermine arbitral outcomes.
Headnote:This judgment concerns a petition under Section 9 of the Arbitration and Conciliation Act, 1996, wherein the petitioner seeks ex parte ad interim injunction against the respondents regarding a project transfer. The respondents have allegedly failed to pay approximately Rs. 2 crores stipulated in a Term Sheet, breaching the agreement. The court finds a strong prima facie case for the petitioner, noting potential irreparable damage. The respondents are thus ordered to maintain status quo until the next hearing.
| Table of Content |
|---|
| 1. petitioner seeks injunction to protect its rights in arbitration. (Para 1 , 2) |
| 2. petitioner argues breach of obligations by respondents regarding payment. (Para 3) |
| 3. court finds a strong case for interim protection to prevent irreparable harm. (Para 6 , 7) |
| 4. balance of convenience favors petitioner for granting relief. (Para 8) |
| 5. court orders status quo pending further hearing. (Para 9) |
O R D E R
% 04.08.2025
1. This is a petition filed under Section 9 of the Arbitration and Conciliation Act, 1996 seeking the following relief:-
“(a) Pass an order of exparte ad interim injunction restraining Respondent No. 1 and 2, their directors, officers, agents, servants, or any person claiming through or under them, from selling, transferring, assigning, alienating, recording or creating any third party rights or interest in the 25 MW power connectivity approval dated 16.03.2024 & 22.04.2024 granted by Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO/TNGECL) or effecting any name transfer of the said connectivity or causing noted for record approvals in respect of the said connectivity approvals to any third party, during the pendency of the arbitral proceedings.”
2. The brief facts of the case are that the respondents had engaged the services of the petitioner to set up the entire project on a turn-key basis for them. The same was based upon a Term Sheet executed on 04.03.2024. The term sheet stipulated reciprocal promises to be performed by both parties and also laid time frames within which the same were to be performed. However, the petitioner has not been paid for its services in entirety. The respondents are refusing to tender the amounts due even for the milestones completed.
3. Ms. Kaul, learned counsel for the petitioner, submits that it is the respondents who are in breach of their obligations under the Term Sheet and not the petitioner. She states that a substantial amount of approximately Rs. 2 crores is due and payable by the respondents to the petitioner, and despite this, the respondents are threatening to terminate the agreement and transfer the approval for the power project to a third party. She contends that such a transfer would defeat the very substratum of the arbitral dispute, even though the respondents remain in default of their obligations and have failed to discharge their admitted liabilities.
4. The issue needs consideration.
5. For the said reasons, issue notice to the respondent through all modes including electronic as well as dasti process on the petitioner taking steps within 1 week from today, returnable on 14.08.2025.
6. Under Section 9 , the object of the Court is to ensure protection of the property being the subject-matter of arbitration and/or otherwise ensure that the arbitration proceedings do not become infructuous and the arbitral award does not become an award on paper, of no real value as held in Arcelormittal Nippon Steel (India) Ltd. v. Essar Bulk Terminal Ltd., (2022) 1 SCC 712 .
7. Prima facie it seems that the petitioner has not been paid for its services and an approximate amount of Rs. 2 crores is due and payable by the respondents and despite this, the respondents are threatening to terminate the agreement and transfer the approval of the power project to a third party.
8. For the said reasons, I am satisfied that the petitioner has a strong prima facie case and the balance of convenience lies in favor of the petitioner and irreparable damage will be caused if an interim relief is not granted.
9. In view of the above, till the next date of hearing, the respondents shall maintain status quo as regards the transfer of the project to a third party.