SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Online)(Del) 18870

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
Not mentioned, Not mentioned
builder co. – Appellant
Versus
complainants – Respondent
Consumer Protection Act, 1986 | Complaint No. 491 of 2017



Advocates:
For the Appellants/Petitioners: Mr. Arjun Jain
For the Respondents: Mr. Raktim Gogoi

The builder's delay in possession constituted deficiency of service, requiring compensation with interest under consumer protection law.

Headnote:(A) Consumer Protection Act, 1986 - Section 19 - Builder-buyer dispute - Delay in possession - Builder fails to deliver possession within the committed period, resulting in deficiency of service - Compensation awarded at 9% interest for the delay - Interest rate adjusted to 10% as per consumer's request concerning pecuniary jurisdiction - Statutory provisions allow compensation for consumer losses and injuries. (Paras 3, 15, 16)

(B) Jurisdiction - Pecuniary jurisdiction challenged - The submission of the builder regarding the pecuniary jurisdiction is dismissed as it was not substantiated with adequate evidence. (Para 6)

Facts of the case:
A builder failed to deliver possession of a flat within the stipulated time, leading the complainants to seek remedy through the State Commission. They were awarded compensation for the delay based on the interest rate.

Findings of Court:
There was clear deficiency in the builder's service, and the delay in possession was deemed abnormal. The builder's preliminary objections regarding consumer classification and jurisdiction were unsupported and dismissed.

Issues: Key issues addressed include the abnormal delay of possession, the nature of the consumer's purchase, and the builder's jurisdiction challenge.

Ratio Decidendi: The court emphasized that the builder's responsibility encompasses timely possession and service delivery. Consumer law prioritizes protecting consumers against service provider unfairness.

Result: The appeal was disposed of with the award of interest at 9% and costs imposed on the builder.

Table of Content
1. overview of the builder-buyer dispute. (Para 1 , 2 , 3)
2. arguments relating to pecuniary jurisdiction and compliance. (Para 4 , 6 , 12)
3. court's emphasis on builder's responsibility for timely possession. (Para 5 , 10 , 11 , 14)
4. assessment of compensation standards and consumer protection. (Para 13)
5. final ruling and modifications to the state commission's order. (Para 15 , 16)

1. This appeal under S.19 of The Consumer Protection Act, 1986 is in challenge to the Order dated 5.11.2018 of the State Commission in complaint No. 491 of 2017.

2. Mr. Arjun Jain, learned Counsel appears for the appellant (the 'builder co.'). Mr. Raktim Gogoi, learned Counsel appears for the respondents No. 1 and No. 2 (the 'complainants'). The respondent No. 1 (the 'complainant No. 1') present in person also makes his submissions.
The record including inter alia the State Commission's impugned Order dated 5.11.2018 and memorandum of appeal has been perused.

3. The matter pertains to a builder - buyer dispute. Briefly, the builder co. entered into an agreement with the complainants in respect of the subject flat on 14.9.2010. The total consideration of the unit was Rs.56,36,404.06. The complainants paid an amount of Rs.54,98,003 plus some taxes to the builder co. in the period from 14.9.2010 to 26.11.2014. As per clause 14(a) of the agreement, the possession of the flat was to be handed over within 24 months from the date of start of construction with a grace period of 06 months. It is the builder co.'s assertion that the construction of the project was started on 21.8.2010. The complainants do not object to this date in the arguments today. Counting from the said date the 30 month commitment period inclusive of the grace period for handing over possession elapsed on 20.2.2013. Despite having received almost the entire consideration, possession of the flat was not handed over to the complainants in the assured period or even within a reasonable period beyond (reasonable period here would connote a period which appears reasonable per se and which a reasonable man of ordinary prudence would not normally agitate). The complainants went before the State Commission on 11.8.2017, i.e. 4 years 5 months 21 days after the expiry of the commitment period. During the pendency of the proceedings before the State Commission, possession was offered on 14.3.2018. According to the complainants the actual physical possession of the flat was made on 27.9.2018. The builder co. does not dispute the said date in the arguments today. Holding the abnormal unreasonable delay in handing over possession of the flat to be 'deficiency in service' on the part of the builder co. the State Commission has ordered for compensation by way of interest at the rate of 9% per annum on the amount deposited by the complainants for the period of delay ("xx xx It is a case where the reasonable interest @ 09% could be allowed. Hence with these observations the complaint stands allowed and the interest @ 9% be allowed or calculated on the amount paid by the complainants in different phases. xx xx"). It has also stipulated that the rate of interest shall stand enhanced to 12% if the payment is not made within two months ("xx xx In case, there is a breach in making payment within the stipulated period of two months, in that eventuality, the complainants would further be entitled to get the interest @ 12% per annum, for the defaulting period xx xx "). It has awarded Rs.21,000 as cost of litigation.

4. Learned Counsel for the builder co. submits that the complainants obtained this flat for "speculative purpose" and "undue enrichment" and therefore they are not 'consumer' within the meaning of S.2(1)(d)(ii) of the Act 1986.
Learned Counsel for the complainants submits that the complainants No. 1 and No. 2 are father and son and they have no other own flat except the subject flat. After taking the belated possession, they are residing in the same.
The complainant No. 1 in person cat












































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top