2023 Supreme(Online)(Del) 18872

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
S. M. Kantikar, J
Ramesh Thangarajan v. Dr. Santhosshi Narayanan
Consumer Complaints Nos. CC / 2036/2017, CC / 2037/2017, CC / 2112/2017, CC / 2117/2017, CC / 2118/2017, CC / 2119/2017, CC / 2120/2017, CC / 2121/2017, CC / 2122/2017, CC / 2153/2017, CC / 2154/2017, CC / 2155/2017, CC / 3747/2017, CC / 1682/2018, CC / 234/2019



Advocates:
For the Appellants/Petitioners: Sushil Kaushik
For the Respondents: Gopal Jain

Court held that one-sided contractual terms favoring builders amount to unfair trade practices under consumer laws, entitling buyers to refunds and compensation for delays.

Headnote:(A) Consumer Protection Act, 1986 - Section 21 - Consumer Complaints for deficiency in service related to delayed possession of residential villas - Complainants sought refund and compensation due to failure to deliver villas as per agreed terms - Agreement terms declared unfair as they disproportionately favor the builder. (Paras 1, 2, 8, 24)

(B) Delay in possession - Builder’s reliance on force majeure events rejected due to lack of evidence related to impact on construction timelines - Complainants entitled to seek refund with interest due to unreasonable delay. (Paras 18, 19)

(C) Consumer status - Builders’ claim that Complainants were investors rejected as it was found they were consumers under the Act. (Para 12)

Facts of the case:
Complainants entered into agreements for villas with the builder but possession was delayed beyond the stipulated time without adequate justification. Builder's claims of natural calamities as reasons for delay were also dismissed.

Findings of Court:
The builders were ordered to refund amounts with interest and delay compensation to affected Complainants.

Issues: The main issues were unjust contractual terms, delay in possession, and the status of Complainants as consumers.

Ratio Decidendi: The court held that one-sided agreements with unfair terms were unenforceable, emphasizing the consumer's right to timely possession and compensation for delays.

Result: Complaints partly allowed, with directives for refunds and interest.

Table of Content
1. consumer complaints filed regarding possession delays. (Para 1 , 2)
2. allegations against builder include unfair contract terms. (Para 3 , 4 , 5)
3. court analysis on unreasonable delays in possession. (Para 18 , 19 , 20)
4. court directives for refunds and compensation awarded. (Para 22 , 23 , 24 , 25)

1. The bunch of present Consumer Complaints has been filed under S.21 of the Consumer Protection Act, 1986 (for short "the Act) by the Complainants / Purchasers of the Villas under the name and style "Pacifica Aurm" proposed to be developed at Pacific Aurum Pandur, OMR Road, Chennai, Tamil Nadu (hereinafter to be referred as the Villa), by Sylvanus Builders and Developers Ltd., (hereinafter referred to as the Opposite Party Builder), inter alia, alleging deficiency in service in not handing over the possession of the Villa within stipulated period and seeking either possession with delayed compensation or refund of amount deposited by them along with reasonable interest and compensation.

2. Since all the Complainants have entered into identical Undivided Share of land and Construction Agreements (hereinafter referred to as the "Agreement") with the Opposite Parties; the facts and question of law involved in all the cases are similar except minor variation in the dates, and almost similar reliefs have been prayed for, these Complaints are being disposed off by this Common Order. However, for the sake of convenience, CC No. 2118 of 2017 is treated as the lead case and the facts enumerated hereinafter are taken from CC No. 2118 of 2017.

3. It has been averred in the Complaint that in the year 2011, Opposite Party No. 1, Sylvanus Builders & Developer Limited and Opposite Party No. 2 Pacifica (Chennai) Infrastructure Company Private Ltd. (hereinafter referred to as the OP Builder) launched a Group Housing Colony under the name and style of "Pacifica Aurum" (hereinafter referred to as the Project) in Padur, OMR Road, Chennai, Tamil Nadu. Allured by the exaggerated advertisement and the assurances given by the authorised representatives of the OP Builder that there would be club, shopping complex, sports complex, amphitheater, hospital and every modern facilities in the Project and the physical Possession would be handed over within two years of the booking, the Complainant booked a Villa for residential purpose in the said Project for a total sale consideration of Rs.1,03,59,118.73ps. (Rupees One Crore Three Lacs Fifty Nine Thousand One Hundred Eighteen and paisa seventy three only) by paying a sum of Rs.1,00,000 towards booking amount on 13.5.2013. The total sale consideration of the Villa was inclusive of (i) basic sale price, (ii) total sale consideration of UDS of land (iii) infrastructure charges, (iv) club membership charges, (v) TNEB / CMWSSB charges and (vi) maintenance charges in advance for two years. It was assured that the possession of the Villa would be delivered by 3.12.2015. Undivided Share of land Agreement / Agreement to sell and Construction Agreement (hereinafter referred to as the Agreements) were executed between the Parties on 10.09.2013. It was alleged that the terms and conditions of the Agreements were unfair, one - sided and only in favour of the OP Builder. Clause 22 of the Agreement reads as under:
"22. In Case, the undivided share of the land in the Schedule "C" Property had already been conveyed to the customer(s) at such point in time, the customer(s) shall, at the Customer(s) cost and expense re - convey the same to the developer and / or to any person nominated by the Developer for a sale consideration equivalent to the amount for which the same was originally purchased by the Customer(s) or for the amount that is held by the Developer in the account of the Customer(s) in excess of the said liquidated damages, whichever is less. The Customer(s) agrees that in any event the first charge over the Property in schedule "D and E" shall be in favor of the Developer only. And the customer(s)




































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top