SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Online)(Del) 7310

DELHI STATE CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
R. K. Agrawal, J
Sanjeev Agarwal v. Parsvnath Buildwell Pvt. Ltd.
Consumer Complaint No. 123 of 2019



Advocates:
For the Appellants/Petitioners:[Advocate Name]
For the Respondents:[Advocate Name]

Deficiency in services occurs when contractual obligations regarding timely delivery are not met, allowing for consumer redress.

Headnote:This case concerns a Consumer Complaint filed under S.17 of the Consumer Protection Act, 1986, seeking refunds and damages due to service deficiencies by the Opposite Parties in constructing a booked flat. The Court found the Opposite Parties deficient in service based on delayed completion and non-fulfillment of contractual obligations. The key legal issue was whether the Opposite Parties provided the contracted services efficiently. The Court concluded by ruling in favor of the Complainants, ordering refunds with interest and additional compensation.

Table of Content
1. seeking relief through consumer complaint under cp act. (Para 1)
2. contractual agreement details and service failure. (Para 2 , 3 , 7)
3. opposite party's objections and complaint maintainability. (Para 4 , 5)
4. determining deficiency of service by opposite party. (Para 8 , 9)
5. contractual obligations and acknowledgment of delays. (Para 10 , 11 , 12)
6. court's final determination and orders for compensation. (Para 13 , 14 , 15 , 16 , 17 , 18)

1. The The present Consumer Complaint has been filed before this Commission under S.17 of the Consumer Protection Act, 1986 , seeking the following reliefs:
(a) “Direct the Opposite Party to refund sum of Rs. 11,92,854 (Rupees Eleven Lakh Ninety Two Thousand Eight Hundred Fifty Four Only) being the amount deposited by the Complainants with the Opposite Party along with interest @ 24% per annum, with effect from the date of payment made towards the booking amount of the said flat till the date of the actual refund made by the opposite party.
(b) Restrain the Opposite Parties:
(i) from making further illegal demand of money and charging any interest on the illegal demand to the Complainant; AND / OR;
(ii) from illegally cancellation of the allotment of the booked apartment, AND / OR;
(iii) from forfeiture of the money paid by the Complainant, AND / OR;
(c) Direct the Opposite Party to pay Rs. 10,00,000(Rupees Ten lakh) towards mental trauma, harassment and hardships suffered by the Complainants;
(d) Direct the Opposite Party to pay a sum of Rs. 2,00,000 / (Rupees Two Lakh Only) to the Complainants towards the cost of litigation; and
(e) Pass any other or further relief in favour of the Complainants and against the Opposite Party which this Hon’ble Commission may deem fit, just and proper in the facts and circumstances of the case.”


2. Brief facts necessary for the adjudication of the present complaint are that the Complainants booked a flat bearing No. E8-305, 3rd Floor, Tower No. E8 admeasuring 1450 sq. ft. in the project of the Opposite Parties namely ‘Parsvnath Exotica’ at Ghaziabad, Uttar Pradesh. Thereafter, the Opposite Parties entered into a Flat Buyer Agreement dated 19.7.2013 with the Complainants and an advance amount of Rs. 6,12,235 was paid by the Complainants at the time of agreement. The Opposite Parties assured the Complainants that as per the clause 10 (a) of builder buyer agreement, the construction of the said flat shall be completed within 36 months from the date of commencement of construction of the particular tower in which the flat in question is situated with a grace period of six months. However, the Opposite Parties failed to complete the construction of the project till today. The Complainants over the time had paid a sum of Rs. 11,92,854 to the Opposite Parties.

3. The Complainants also requested the Opposite Parties to refund the amount deposited by them with interest but was of no avail. Thus, left with no other option, alleging deficiency of service and unfair trade practice on the part of the Opposite Parties, the Complainants approached this Commission.

4. The Opposite Parties have contested the present case and have raised some preliminary objections as to the maintainability of the complaint case. The Counsel for the Opposite Parties contended that the present complaint filed by the Complainants is devoid of any cause of action. The Counsel for Opposite Parties further contended that the present dispute pertains to the recovery of amount and therefore, the present complaint should be adjudicated by a Civil Court. Pressing the aforesaid preliminary objections, the Counsel appearing on behalf of the Opposite Parties prayed that the present complaint should be dismissed.

5. The Complainants have filed their Rejoinder rebutting the written statement filed by the Opposite Parties. Thereafter both the parties were directed to file their Evidence by way of Affidavit and written arguments vide the order dated 22.2.2021 and 25.1.2022 in order to pr
























Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top