2022 Supreme(Online)(Del) 7424
NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION, NEW DELHI
F. M. Ibrahim Kalifulla, J
Delhi Urban Shelter Improvement Board v. Desh Raj
Review Petition No. 123 of 2016
For the Appellants/Petitioners: None specified
For the Respondents: None specified
Inordinate delays in service can amount to deficiency under the Consumer Protection Act, but excessive compensation beyond claims is not warranted.
Headnote:The review petition challenges the order of the State Consumer Dispute Redressal Commission under the Consumer Protection Act, 1986, relating to a delay in allotting residential flats under a 1985 Scheme. The District Forum initially dismissed the complaint, citing no deficiency of service. However, the State Commission reversed this, recognizing substantial delay as a service deficiency. The court emphasized that compensation awarded was disproportionate to the original claim. Consequently, the petition is partly allowed, modifying the compensation and interest rates.
| Table of Content |
|---|
| 1. review petition under consumer protection act regarding service deficiencies. (Para 1 , 2 , 3) |
| 2. discussion on delay in allotment and its implications. (Para 4 , 7 , 8) |
| 3. arguments presented regarding jurisdiction and compensation. (Para 5 , 6 , 10) |
| 4. modification of compensation due to excessive claims. (Para 11) |
1. This review petition filed under S.21(b) of the Consumer Protection Act, 1986 (in short, the ˜Act) assails the order of the State Consumer Dispute Redressal Commission, Delhi (in short, ˜State Commission) in First Appeal No. 352 of 2010 dated 21.4.2016 setting aside the order of the District Forum (Central), Delhi (in short, ˜District Forum) dated 12.4.2010 directing the petitioner to refund the amount of Rs 3,000 with 18% interest per annum from 27.12.1985 along with compensation of Rs. 20,00,000 to the respondent for harassment and mental agony, to deposit Rs. 50,00,000 in the Consumer Welfare Fund and pay Rs. 1,00,000 towards litigation costs to the respondent.
2. The brief facts of the case are that the Delhi Urban Shelter Improvement Board (DUSIB), a statutory body of the State government under the Delhi Urban Shelter Improvement Board Act, 2010 launched a Residential Flats Registration Scheme for slum dwellers and others in 1985 through the Delhi Development Authority (DDA). The period of registration was from 21.11.1985 to 30.12.1985 and was intended for residents with a food card of areas notified as slums under the Slum Areas (Improvement and Clearance) Act, 1985, jhuggi jhopries, slum rehabilitation colonies, JJ resettlement colonies and unauthorized colonies in urban villages in Delhi. The initial deposit fixed was Rs. 3,000 and 27,693 applications were received by DDA.
3. As the respondent was not allotted a flat, he filed a complaint before the District Consumer Forum, Kashmere Gate, Delhi (Complaint No. 541 of 2008) stating that he had applied under the said scheme on 27.12.1985 but had subsequently withdrawn the amount on 14.9.1987 and was refunded Rs. 3,385 with interest @ 7%. However, he was asked by the authorities to re - apply and accordingly he had deposited Rs. 3,385 on 20.2.1988 again. As no flat had been allotted to him, the respondent prayed for allotment of a flat along with damages of Rs. 50,000 and costs of Rs. 10,000. This complaint was contested by the petitioner herein on grounds that the Priority No. of the respondent was 12,929 under General category and that only Priority No. 2650 had been reached under the scheme. The complaint was dismissed by the District Forum on the ground that there was no time frame fixed for the scheme and therefore no violation of the scheme was attributable to the petitioner. No deficiency was also alleged as Priority Number had not been violated.
4. The respondent challenged this order before the State Commission in First Appeal No. 352 of 2010. Vide order dated 21.4.2016, the State Commission set aside the order of the District Forum on the ground that as no flat had been allotted despite 30 years having passed since the scheme was launched, deficiency was well established. It also concluded insensitivity and negligence on part of the petitioner herein and ordered as under:
7. The only controversy before me is that as to whether the shelter board is ˜deficient in service in not allotting the flat to the complainant in a span of thirty years. Complainant admittedly deposited an amount of Rs. 3,000 on 27.12.1985. Perusal of the brochure of the scheme 1985 floated by the shelter board shows that it had promised to allot singly storyed houses which were fully ventilated and fitted with all the facilities. It was specifically mentioned that houses would be allotted without loss of much time (paragraph 2 of the Scheme 1985, Hindi version). Clearly a period thirty years has elapsed. In its written arguments, shelter board stated that it has so far allotted flats upto the priority number 2650 / G. Priority number of the complainant is 12,929 /