SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Del) 36209

IN THE HIGH COURT OF DELHI AT NEW DELHI
Subramonium Prasad, Harish Vaidyanathan Shankar, JJ
Air Force Naval Housing Board – Appellant
Versus
Umaxe Projects Pvt Ltd – Respondent
FAO(OS) (COMM) 40/2024|FAO(OS) (COMM) 41/2024



Advocates:
For the Appellants/Petitioners: Yoginder Handoo, Ashwin Kataria, Garvit Solanki
For the Respondents: Anirudh Bakhru, Ayush Puri, Vasundhara Bakhru, Archita Mahlawat, Kanav Manmani, Mohd Umar, Vijay Laxmi Rathi, Umang Tyagi, Sultan Jafri

Unilateral appointment of a sole arbitrator is impermissible as it violates neutrality. Statutory ineligibility under the governing arbitration law can only be waived by an express agreement in writing executed after the dispute has arisen, rather than by mere conduct, participation in proceedings, or seeking extensions of the mandate.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 12(5), 14 - Constitution of India - Article 14 - Unilateral appointment of sole arbitrator - Independence and impartiality of tribunal - Express waiver of ineligibility.

(B) Arbitration - Unilateral appointment - An arbitration clause permitting one party to unilaterally appoint a sole arbitrator is violative of the requirement of equal treatment and the fundamental principle that no one should be a judge in their own cause (Paras 12, 13).

(C) Waiver - Requirement of express agreement in writing - The proviso to Section 12(5) requires an "express agreement in writing" after the dispute has arisen to waive the disqualification of an arbitrator. Participation in proceedings or seeking the extension of the mandate through an application does not constitute a valid express waiver for the purposes of statutory disqualification (Paras 17, 18, 19).

(D) Jurisdictional Challenge - Ineligibility as a matter of law - Because an ineligible entity cannot appoint an arbitrator, an award passed by such an arbitrator is a nullity, and the objection regarding jurisdiction can be raised for the first time during challenge proceedings or enforcement of the award (Para 20).

Facts of the case:
Disputes arose in two infrastructure projects between an entity and a contractor. A sole arbitrator was unilaterally appointed by the entity per the contract terms. The contractor initially participated in the proceedings and sought an extension of the arbitrator's mandate. However, the contractor later challenged the awards, contending that the unilateral appointment rendered the arbitrator de jure ineligible.

Findings of Court:
The court determined that participating in arbitration and filing for an extension of the mandate does not satisfy the criteria of an "express agreement in writing" required to waive statutory ineligibility.

Issues: Whether a unilateral appointment of a sole arbitrator is inherently invalid and whether the activities of the party in the arbitration forum constitute a valid waiver of the statutory disqualification of the arbitrator.

Ratio Decidendi: An arbitration clause allowing unilateral appointment violates principles of procedural equality and public policy. Statutory ineligibility under the law requires an express, unequivocal written waiver made subsequent to the emergence of the dispute; mere participation or conduct cannot replace this requirement.

Result: Appeals dismissed.

Table of Content
1. factual background and initiation of appeals regarding unilateral appointment of arbitrator. (Para 1 , 2 , 3)
2. arguments concerning existence of waiver for unilateral appointment of arbitrator. (Para 4 , 5 , 6 , 7 , 8)
3. unilateral appointment of sole arbitrator is inherently ineligible and violates principles of equality. (Para 9 , 10 , 11 , 12 , 13)
4. express waiver under section 12(5) requires explicit written agreement, not conduct or extension of mandate. (Para 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22)
5. validation of the lower court's decision setting aside awards as a nullity due to invalid arbitrator appointment. (Para 23 , 24 , 25)

JUDGMENT

SUBRAMONIUM PRASAD, J.

1. The Petitioner has filed FAO(OS)(COMM) No. 40 of 2024 and FAO(OS)(COMM) No. 41 of 2024 under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”), seeking to appeal against the common Judgment and Order dated 01.12.2023 (hereinafter referred to as “Impugned Judgment”) passed by this Court in OMP (COMM) No. 470 of 2023, and OMP (COMM) No. 469 of 2023 respectively, wherein this Court allowed these Petitions filed by the Respondent under Section 34 of the Act and set aside the final arbitral awards, both dated 28.06.2023 (hereinafter referred to as “Impugned Awards”).

2. Both the Impugned Awards were delivered by the same Sole Arbitrator between the parties, albeit with respect to different projects. As the parties were same and the contentions raised were common in both the petitions, the same were taken up for consideration together by the learned Single Judge of this Court vide the Impugned Judgment. This Court, in the same vein, will take up both the cases, together.

3. Shorn of unnecessary details, the facts leading to the filing of the present Appeals are as follows:-

i. The impugned award in FAO(OS)(COMM) No. 41 of 2024, was passed in the context of Letter of Acceptance (LOA) dated 04.05.2010 issued to the Respondent being the lowest bidder for the project to construct 430 flats in eight towers in a housing scheme near Jhajjar Village, Prem Nagar, Dehradun, for an estimated cost of Rs. 98.01 crores (hereinafter referred to as “Dehradun Project”). An agreement was executed on 10.06.2010.

ii. The impugned award in FAO(OS)(COMM) No. 40 of 2024, was passed in the context of LOA dated 30.11.2017 issued to the Respondent to complete the balance work at the project site comprising 545 flats in eight towers for an amount of Rs. 38.33 crores (hereinafter referred to as “Meerut Project”). Notably, the Petitioner in the year 2010 had launched a housing scheme at Shatabdi Nagar, Meerut, which it had awarded to one M/s Omaxe Infrastructure & Construction Limited. However, the contract was terminated on 27.10.2017 resulting in issuance of LOA in favour of the Respondent. An agreement was executed on 17.01.2018.

iii. Disputes arose between the parties regarding delayed construction and other ancillary issues connected therewith, in both, the Dehradun Project and the Meerut Project.

iv. On 13.07.2019, the Appellant terminated the contract with respect to the Dehradun Project by invoking Clause 7 of the Contract Agreement and the balance/unfinished work was undertaken at the risk and cost of the Respondent.

v. On 22.06.2019, the Appellant terminated the Contract with respect to the Meerut Project for non-performance.

vi. As per clause 18.2 of the Contract Agreement dated 04.05.2010/ Clause 18.2 of GCC forming part of the Agreement dated 10.06.2010, executed for the Dehradun Project, the Chairman of the Appellant vide appointment letter dated 24.07.2019 appointed Mr. Vinod Kumar Maheshwari as the Sole Arbitrator for adjudication of disputes.

vii. Similarly, as per clause 18.2 of the Contract Agreement dated 30.11.2017/Clause 22 of the Agreement dated 17.01.2018, executed for the Meerut Project, the Chairman of the Appellant vide appointment letter dated 15.07.2019 appointed Mr. Vinod Kumar Maheshwari the So

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top