IN THE HIGH COURT OF DELHI AT NEW DELHI
Jasmeet Singh, J
National Highways Authority Of India – Appellant
Versus
Hindustan Construction Co Ltd – Respondent
O.M.P. 1556/2014
| Table of Content |
|---|
| 1. procedural history and factual background of the dispute. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 22) |
| 2. competing claims on contractual rates and measurement methods. (Para 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19) |
| 3. limited scope of judicial review under section 34. (Para 20 , 21) |
| 4. interpretation of composite work items for fly ash embankments. (Para 23 , 24 , 25 , 26 , 27 , 28) |
| 5. compliance with binding precedent regarding composite measurement. (Para 29 , 30 , 31) |
| 6. validity of tribunal jurisdiction and interest award methodology. (Para 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39) |
| 7. final adjudication dismissing the petition. (Para 40 , 41) |
JUDGMENT
1. This is a petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (“1996 Act”) seeking to challenge the Arbitral Award dated 22.07.2014 passed by the learned Arbitral Tribunal (“Tribunal”) in the matter of “Hindustan Construction Co. Ltd. v. M/s. National Highways Authority of India‖.
2. The petitioner (respondent before the Tribunal) is a statutory body constituted under Section 3 of the National Highways Authority of India Act, 1998 , for the purpose of developing, maintaining, and managing the National Highways entrusted to it by the Central Government. The respondent (claimant before the Tribunal) is an entity engaged in the business of providing various services on contractual basis.
3. The petitioner vide Agreement dated 21.10.2005, awarded the respondent the contract package titled “4-Laning from Km. 92.00 to Km. 135.00 of the Lucknow to Ayodhya Section of NH-28 in Uttar Pradesh Contract Package LMNHP EX-II (WB)-3” for a total contract value of Rs. 249,95,04,940/-. The Conditions of Particular Application (“CoPA”) has Arbitration clause being Clause No. 67.3.
4. Since there were disputes between the parties, disputes were referred to Dispute Resolution Board (“DRB”). The respondent was not satisfied with the resolution by the DRB therefore the disputes were referred to the Tribunal for the following claims:
―Claim No.1: Fixing of appropriate rates for the new/varied works of construction of embankment at Faizabad bypass with earth in place fly ash embankment as provided for in the contract.
Claim No.2: Payment for construction of embankment with fly ash as per additional Technical Specification Clause A-8.
Claim No. 3: Reimbursement of additional cost incurred by the Contractor on account of subsequent legislation in respect of imposition of levy of Cess in the State of UP w.e.f. 04.02.2009.
Claim No. 4: Withholding the part payment due to Price Adjustment on foreign currency portion from interim payment certificate.‖
5. The Tribunal vide Award dated 22.07.2014 allowed all the claims of the respondent. Aggrieved thereby, the petitioner filed a petition under Section 34 of the 1996 Act challenging the said Award.
6. This Court vide order dated 20.04.2017 in National Highway Authority of India v. Hindustan Construction Co. Ltd.1OMP Nos. 1165/2014; 1556/2014 & OMP (Comm.) No. 156/2016., rejected the objections raised by the petitioner and upheld the Award. Aggrieved by the said order, the petitioner preferred an Appeal under Section 37 of the 1996 Act before the Division Bench of this Court. The Division Bench, vide judgment dated 23.03.2018 in National Highway Authority of India v. Hindustan Construction Co. Ltd.2FAO (OS) 192/2017. upheld Claim Nos. 1, 3, and 4, and remanded the matter to the Single Bench for fresh consideration only with respect to Claim No. 2. The said finding of the Division bench is reproduced below:
―10.6 Accordingly, we are constrained to set aside the finding of the learned Single Judge Claim No.2 of the respondent and remand the matter to the learned Single Judge for reconsideration thereof.‖
7. Accordingly, the present petition survives only qua Claim No. 2, and the parties have addressed their submissions limited to the said claim.
SUBMISSIONS ON BEHALF OF PETITIONER
8. Mr. Singh, learned counsel fo
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.