SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(SC) 721

SUPREME COURT OF INDIA
Abhay S. Oka, Ujjal Bhuyan, JJ.
Consolidated Construction Consortium Limited – Appellant
Versus
Software Technology Parks of India – Respondent
Civil Appeal No. 5383 of 2024
Decided On : 28-04-2025

Advocates appeared:
For the Appellant(s) : Mr. S. S. Rajesh, Adv. Mr. K.S. Mahadevan, Adv. Ms. Swati Bansal, Adv. Mr. R. Rangarajan, Adv. Mr. Aravind Gopinathan, Adv. Mr. Rajesh Kumar, AOR
For the Respondent(s): Mr. Vinay Mohan Sharma, Adv. Mr. Ravinder Kumar Yadav, AOR Mrs. Arti Anupriya, Adv. Mr. Kartikey, Adv. Mr. Paras Juneja, Adv. Ms. Kritika Yadav, Adv. Mr. Arnav Singh, Adv. Mr. Vineet Yadav, Adv. Ms. Manisha, Adv.

The court affirmed that the scope of interference under Section 34 of the Arbitration and Conciliation Act is limited, and an arbitral award can only be set aside on specific grounds, not on broader interpretations.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 and Section 37 - Appeal against arbitral award - High Court set aside Single Judge's order which had annulled the arbitral award on grounds beyond Section 34 - The Division Bench found the Single Judge's reasoning to be based on assumptions and not within the scope of the Act. (Paras 2, 6, 28)

(B) Contract Law - Liquidated damages - The court upheld the validity of liquidated damages as per contract terms, emphasizing that extension of time does not negate the right to claim such damages if the delay was within the contractor's control. (Paras 11.2, 18)

Facts of the case:
The appellant was awarded a contract for construction but delayed completion, leading to deductions for liquidated damages by the respondent. The appellant contested these deductions through arbitration, which upheld the respondent's claims.

Findings of Court:
The Division Bench reinstated the arbitral award, stating the Single Judge exceeded jurisdiction under Section 34 by setting aside the award without valid grounds.

Issues: The main issues were whether the Single Judge had the authority to set aside the arbitral award and the validity of liquidated damages despite the extension of time.

Ratio Decidendi: The court ruled that the Single Judge's decision was not justified as it exceeded the limited grounds for interference under Section 34, and the arbitral tribunal's findings were plausible and within its jurisdiction.

Result: Appeal dismissed.

Judgement Key Points

Key Points: - The scope and grounds of interference under Section 34 of the Arbitration and Conciliation Act, 1996; the Division Bench held the Single Judge exceeded jurisdiction by intervening beyond Section 34 grounds. (!) (!) - Section 34 is a restrictive, summary remedy; an arbitral award can be set aside only on grounds in Section 34(2) and (2A), including patent illegality for non-international arbitration. (!) (!) (!) - Liquidated damages are valid where delay occurred, with extension of time not automatically negating LD if delay was within contractor’s control; conduct of extensions and notices affecting LD rights. (!) (!) (!) (!) (!) (!) - The contract clauses 26, 27, and 28 govern liquidated damages, extensions of time, and failure to comply with instructions, and must be interpreted conjointly; earlier extension does not automatically nullify LD if time was extended with reservation of rights. (!) (!) (!) (!) (!) (!) (!) - The High Court Division Bench’s reversal of the Single Judge’s Section 34 order and restoration of the award was upheld; the Single Judge’s reasoning was found to be beyond the scope of Section 34. (!) (!) - Time is of the essence or not; Sections 55, 73, 74 of the Indian Contract Act govern compensation; extension of time and LD implications discussed. (!) (!) (!) (!) - The judgment clarifies that Section 34's scope is limited and an award is not subject to re-evaluation on merits; the field for setting aside is narrow. (!) (!)

Question 1?

Question 2?

Question 3?


JUDGMENT :

UJJAL BHUYAN, J.

This appeal by special leave is directed against the judgment and order dated 08.08.2019 passed by the High Court of Judicature at Madras in O.S.A. No. 157 of 2019.

2. Be it stated that by the judgment and order dated 08.08.2019 (‘impugned judgment’ hereinafter), Division Bench of the High Court of Judicature at Madras (briefly ‘the High Court’ hereinafter) allowed the appeal of the respondent filed under Section 37 of the Arbitration and Conciliation Act, 1996 (briefly ‘the 1996 Act’ hereinafter) by setting aside the judgment and order dated 02.01.2019 passed by the learned Single Judge of the High Court in O.P. No. 433 of 2010 which was filed by the appellant under Section 34 of the 1996 Act setting aside the arbitral award dated 05.01.2010.

3. Relevant facts may be briefly noted.

4. Software Technology Parks of India i.e. the respondent following a tender process had awarded a contract to M/s Consolidated Construction Consortium Ltd. i.e. the appellant for construction of office building, incubation centre etc. of the respondent. As per the Letter of Intent dated 09.03.2006 issued by the respondent, the total cost of the project was Rs. 16,48,69,970.00. The scheduled date for completion of construction was 15.01.2007. Appellant could complete the construction only by 30.11.2007. There was thus a delay of about 10 months.

4.1. Appellant after handing over the project site to the respondent claimed a sum of Rs. 1,40,12,786.00 including retention money and interest thereon. However, because of the delay in completion, respondent levied and deducted liquidated damages to the tune of Rs. 82,43,499.00 by invoking clause 26 of the contract agreement entered into between the parties. Respondent also made other deductions. After such deductions, balance amount of Rs. 3,70,992.00 was paid to the appellant by the respondent.

4.2. Aggrieved appellant invoked the arbitration clause of the contract agreement and initiated arbitral proceedings challenging deduction of liquidated damages by the respondent and also lodged other claims. Respondent also lodged counter claims.

4.3. Learned arbitrator vide the award dated 10.05.2010 upheld the deduction of liquidated damages by the respondent. That apart, learned arbitrator dismissed the claims and counter claims of the parties. Learned arbitrator held that he did not find any of the claims or counter claims to have been established and, therefore, declared the award as nil against all the claims and counter claims.

5. Appellant filed a petition before the High Court under Section 34 of the 1996 Act to set aside the award which was registered as Original Petition (O.P.) No. 433 of 2010. A learned Single Judge of the High Court vide the judgment and order dated 02.01.2019 held that there was extension of the work period. Appellant had completed the work during the extended period of time. Therefore, deduction of liquidated damages was not justified. Consequently, the arbitral award dated 10.05.2010 was set aside.

6. Aggrieved by the aforesaid judgment and order dated 02.01.2019, respondent preferred an appeal before the High Court under Section 37 of the 1996 Act which was registered as O.S.A. No. 157 of 2019. A Division Bench of the High Court vide the impugned judgment and order dated 08.08.2019 opined that learned Single Judge was not justified in setting aside the award. The award was set aside purely on assumptions and surmises. Grounds on which the award was set aside were beyond the scope of Section 34 of the 1996 Act. Accordingly, the judgment and order of the learned Single Judge dated 02.01.2019 was set aside, thereby allowing the appeal of the respondent.

7. Aggrieved thereby appellant had filed the related special leave petition on which notice was issued on 05.02.2021. When the matter was heard on 23.04.2024, leave was granted.

8. Learned counsel for the appellant submits that Division Bench of the High Court was not at all justified in exercising power under Section

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top