IN THE HIGH COURT OF DELHI AT NEW DELHI
Jasmeet Singh, J
SJVN Ltd – Appellant
Versus
Patel Gammon Joint Venture – Respondent
O.M.P. (COMM) 9/2017
| Table of Content |
|---|
| 1. nature of the contractual dispute between sjvn ltd and the respondent regarding claim no. 4. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12) |
| 2. petitioner challenges the arbitral award based on jurisdiction and specific contractual prohibitions against paying for overbreak haulage. (Para 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24) |
| 3. respondent argues for the validity of the award and maintains that delhi lacks the seat of arbitration due to an exclusive jurisdiction clause. (Para 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33) |
| 4. court reiterates limited scope of interference under sec 34 and affirms the arbitral tribunal's findings on the merits of claim no. 4. (Para 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53) |
| 5. determination that multiple venues in an arbitration agreement do not establish a seat, and an express exclusive jurisdiction clause overrides venue choices. (Para 54 , 55 , 56 , 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64 , 65 , 66 , 67 , 68) |
| 6. dismissal of the petition on grounds of lack of jurisdiction and absence of patent illegality. (Para 69 , 70) |
J U D G M E N T
1. This is a petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (“1996 Act”) seeking to partially set aside the Arbitral Award dated 01.09.2016 passed in the arbitration proceedings titled as “Patel Gammon Joint Venture (PGJV) vs. SJVN Limited (SJVN)”, only to the extent of Claim No. 4, which was allowed in favour of the respondent.
FACTUAL BACKGROUND
2. The petitioner i.e., M/s SJVN Ltd., a Central Public Sector Enterprise, is a joint venture of Government of India and Government of Himachal Pradesh. It is engaged in the business of electricity generation and owns and operates hydroelectric power stations in the country.
3. The respondent i.e., M/s Patel Gammon Joint Venture, is a joint venture consortium of Patel Engineering Ltd. and Gammon India Ltd.
4. The petitioner awarded the respondent a Contract dated 15.03.2007 (“Contract”), wherein the respondent had to undertake civil construction works at petitioner’s 412 MW hydroelectric power project at Rampur, Himachal Pradesh, on river Satluj (“project”).
5. The General Conditions of Contract (“GCC”) forms part of the Contract and contains an arbitration clause being Clause No. 20.6, which reads as under:-
“20.6 Arbitration
Unless settled amicably, any dispute in respect of which the DB's decision/ recommendations (if any) has not been accepted by either party and notice giving intention to commence Arbitration has been served under sub-clause 20.4, shall be finally settled (subject to further rights conferred upon under the law) by Arbitration as per Indian Arbitration and Conciliation Act 1996 in case of disputes between the Employer and a domestic Contractor, and under the rules of arbitration of the International Chamber of Commerce in case of disputes between the Employer and a foreign Contractor, subject to following :
(a) Dispute shall be settled by three arbitrators, one each to nominated by the parties and third one to be appointed by the Secretary (Power), Ministry of Power, Government of India in case of disputes between the Employer and a domestic Contractor, whereas, in case of dispute between the employer and a foreign contractor, the third arbitrator shall be appointed by the International Chamber of Commerce. The definition of domestic bidders and foreign bidders shall be as defined in the World Bank guidelines (latest addition)
(b) The venue of arbitration shall be either Shimla or Delhi or Project site only.”
6. The work was an item rate contract and was awarded at BOQ rates. Technical Specifications formed part of the Contract, and laid down all the technical details of the works i.e., how and what work is to be executed and how work done will be measured and paid.
7. The work under the Contract was divided into two components i.e., package 1.0 and package 2.0. The present petit
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.