SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Del) 81

IN THE HIGH COURT OF DELHI AT NEW DELHI
Jasmeet Singh, J
SJVN Ltd – Appellant
Versus
Patel Gammon Joint Venture – Respondent
O.M.P. (COMM) 9/2017



Advocates:
For the Appellants/Petitioners: Uttam Datt, Sonakshi Singh, Kumar Bhaskar
For the Respondents: SK Chandwani

An arbitral tribunal's interpretation of contractual provisions is binding if plausible. Furthermore, where an agreement specifies multiple venues for convenience, these do not equate to the juridical seat; an explicit exclusive jurisdiction clause in the contract constitutes a superior indication of the agreed supervisory forum.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34 - Challenge to Arbitral Award - Scope of judicial interference - Court exercising jurisdiction under this provision cannot sit in appeal over an arbitral award - Re-assessment of factual findings or evidence lies outside the scope of judicial review - Award can be set aside only on specific grounds including contravention of fundamental policy or patent illegality. (Paras 36, 37)

(B) Seat vs. Venue - Designation of a place as a venue does not establish the seat of arbitration when the contract simultaneously provides an exclusive jurisdiction clause, especially where multiple venues are mentioned - A contractual stipulation of multiple venues for convenience does not confer supervisory jurisdiction upon the courts at those locations - An exclusive jurisdiction clause in the contract operates as a contrary indicia, effectively designating the seat of arbitration. (Paras 57, 58, 62, 65, 66, 67)

(C) Contract Interpretation - Arbitral tribunal is the master of construction of the terms of the contract - A court must not interfere with an interpretation unless it is so perverse that it shocks the judicial conscience or is based on no evidence - Construction of ambiguous terms through the rule of contra proferentum is permissible where interpretation is needed. (Paras 43, 47, 53)

Facts of the case:
The petitioner awarded a contract for civil construction works. The contract contained an arbitration clause providing three potential venues for proceedings, alongside a separate clause in the particular conditions of the contract conferring exclusive jurisdiction to the courts of a specific state. A dispute arose regarding the payment for haulage of excavated material beyond a certain distance. The arbitral tribunal decided in favour of the respondent, allowing the claim. The petitioner challenged the award, contending that the tribunal misinterpreted the contract and that the award was patently illegal, while also challenging the territorial jurisdiction of the instant court.

Findings of Court:
The court upheld the merit of the arbitral award, finding that the tribunal’s interpretation of the contract was plausible, consistent with the evidence, and not patently illegal. However, the court concluded that it lacked the territorial jurisdiction to entertain the petition because the contract’s exclusive jurisdiction clause prevailed over the venue-driven arbitration clause. Despite the lack of jurisdiction, the court decided the matter on merits as there had been significant pendency.

Issues: Whether the court has territorial jurisdiction when the contract provides multiple venues for arbitration and a separate clause conferring exclusive jurisdiction to a different court; whether the arbitral award, in interpreting contract provisions regarding haulage, suffers from patent illegality or is contrary to the terms of the contract.

Ratio Decidendi: The arbitral tribunal’s interpretation of contractual terms is binding if it is a plausible view based on the material on record. Where a contract contains an exclusive jurisdiction clause that is meant to override general conditions, and where venue clauses are provided merely for convenience without designating a single seat, the exclusive jurisdiction clause prevails as the definitive intent of the parties.

Result: Petition dismissed for lack of territorial jurisdiction, reinforcing the validity of the arbitral award on merits.

Table of Content
1. nature of the contractual dispute between sjvn ltd and the respondent regarding claim no. 4. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12)
2. petitioner challenges the arbitral award based on jurisdiction and specific contractual prohibitions against paying for overbreak haulage. (Para 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24)
3. respondent argues for the validity of the award and maintains that delhi lacks the seat of arbitration due to an exclusive jurisdiction clause. (Para 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33)
4. court reiterates limited scope of interference under sec 34 and affirms the arbitral tribunal's findings on the merits of claim no. 4. (Para 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53)
5. determination that multiple venues in an arbitration agreement do not establish a seat, and an express exclusive jurisdiction clause overrides venue choices. (Para 54 , 55 , 56 , 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64 , 65 , 66 , 67 , 68)
6. dismissal of the petition on grounds of lack of jurisdiction and absence of patent illegality. (Para 69 , 70)

J U D G M E N T

1. This is a petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (“1996 Act”) seeking to partially set aside the Arbitral Award dated 01.09.2016 passed in the arbitration proceedings titled as “Patel Gammon Joint Venture (PGJV) vs. SJVN Limited (SJVN)”, only to the extent of Claim No. 4, which was allowed in favour of the respondent.

FACTUAL BACKGROUND

2. The petitioner i.e., M/s SJVN Ltd., a Central Public Sector Enterprise, is a joint venture of Government of India and Government of Himachal Pradesh. It is engaged in the business of electricity generation and owns and operates hydroelectric power stations in the country.

3. The respondent i.e., M/s Patel Gammon Joint Venture, is a joint venture consortium of Patel Engineering Ltd. and Gammon India Ltd.

4. The petitioner awarded the respondent a Contract dated 15.03.2007 (“Contract”), wherein the respondent had to undertake civil construction works at petitioner’s 412 MW hydroelectric power project at Rampur, Himachal Pradesh, on river Satluj (“project”).

5. The General Conditions of Contract (“GCC”) forms part of the Contract and contains an arbitration clause being Clause No. 20.6, which reads as under:-

“20.6 Arbitration

Unless settled amicably, any dispute in respect of which the DB's decision/ recommendations (if any) has not been accepted by either party and notice giving intention to commence Arbitration has been served under sub-clause 20.4, shall be finally settled (subject to further rights conferred upon under the law) by Arbitration as per Indian Arbitration and Conciliation Act 1996 in case of disputes between the Employer and a domestic Contractor, and under the rules of arbitration of the International Chamber of Commerce in case of disputes between the Employer and a foreign Contractor, subject to following :

(a) Dispute shall be settled by three arbitrators, one each to nominated by the parties and third one to be appointed by the Secretary (Power), Ministry of Power, Government of India in case of disputes between the Employer and a domestic Contractor, whereas, in case of dispute between the employer and a foreign contractor, the third arbitrator shall be appointed by the International Chamber of Commerce. The definition of domestic bidders and foreign bidders shall be as defined in the World Bank guidelines (latest addition)

(b) The venue of arbitration shall be either Shimla or Delhi or Project site only.”

6. The work was an item rate contract and was awarded at BOQ rates. Technical Specifications formed part of the Contract, and laid down all the technical details of the works i.e., how and what work is to be executed and how work done will be measured and paid.

7. The work under the Contract was divided into two components i.e., package 1.0 and package 2.0. The present petit

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top