SUPREME COURT OF INDIA
R.F. NARIMAN, ANIRUDDHA BOSE, V. RAMASUBRAMANIAN, JJ.
BGS SGS Soma JV – Petitioner
Versus
NHPC Ltd. – Respondent
Civil Appeal No. 9307, 9308, 9309 of 2019 (Arising Out of SLP (Civil) No.25618, 25848, 28062 of 2018)
Decided On : 10-12-2019
(a) Arbitration and Conciliation Act, 1996 - Section 37 r/w section 13, Commercial Courts Act, 2015 - Section 13(1) merely provides the forum of filing appeals, there is no independent right of appeal u/s 13(1) - Appeal u/s 37 lies against orders setting aside, or refusing to set aside awards under Section 34 - Instantly the Commercial Court held that it had no jurisdiction to decide application u/s 34 and directed the petition to be filed before competent court - There is no adjudication u/s 34 - Application u/s 34 has not been refused - Application u/s 37 not maintainable. (Para 16)
(b) Arbitration and Conciliation Act, 1996 - Section 9 - A step towards an interim order would not amount to granting, or refusing to grant, any measure. (Para 22)
(c) Arbitration and Conciliation Act, 1996 - Section 2(1)(e) and Section 2(2) r/w Sections 20, 31(4) and 42 - Arbitral award should not only to state its date, but also the place of arbitration as determined in accordance with Section 20 - “Court” means only principal civil court and the High Court in exercise of their original ordinary civil jurisdiction - Concept of juridical seat of the arbitral proceedings and its relationship to the jurisdiction of competent courts - Unclear - Developed in accordance with international practice on a case by case basis by Supreme Court. (Para 31, 34)
(d) Interpretation of judgment - Judgments of Courts should not be construed as statutes - Also, not to be read as Euclid’s theorems - All observations made must be read in the context in which they appear - Judgment must be read as a whole so that conflicting parts may be harmonised to reveal the true ratio of the judgment - Failing which it should be seen whether a ratio decidendi can be culled out without the conflicting portion - If not, the point of conflict loses its binding nature. (Para 43, 45)
(e) Arbitration and Conciliation Act, 1996 - Section 2(1)(e) and Section 2(2) r/w Sections 20, 31(4) and 42 - Seat and venue of arbitration - The Act gives recognition to party autonomy. (Para 46)
(e) Arbitration and Conciliation Act, 1996 - Section 2(1)(e) r/w Section 20 - Section 20(1) and (2) refer to “seat” of the arbitration, and Section 20(3) refers only to the “venue” of the arbitration - when a seat is agreed upon by the parties or in absence of an agreement the Arbitral tribunal determined the seat, Courts at the seat alone would be competent for the purpose of interim orders and challenges to the award. (Para 47, 50)
(f) Arbitration and Conciliation Act, 1996 - Section 2(1)(e) r/w Section 20 - Choosing the seat of arbitration amounts to an exclusive jurisdiction clause, insofar as the Courts at that seat are concerned. (Para 52, 55)
(g) Arbitration and Conciliation Act, 1996 - Section 42 - Meant to avoid conflicts in jurisdiction of Courts by placing the supervisory jurisdiction over all arbitral proceedings in connection with the arbitration in one Court exclusively. (Para 61)
(h) Arbitration and Conciliation Act, 1996 - Section 2(1)(e) r/w Section 20 - Seat and venue - Expression “venue” of the arbitration proceedings - Not including just one or more individual or particular hearing, but the arbitration proceedings as a whole, including making of an award at that place - That place would be the seat - On the other hand use of expressions like “tribunals are to meet or have witnesses, experts or the parties” where only hearings are to take place in arbitration clause - That place will not be the seat but only a convenient place of meeting, venue. (Para 63, 84)
(i) Arbitration and Conciliation Act, 1996 - Section 20(1) - Dispute with a foreign contractor - Arbitral proceedings agreed to be held at New Delhi/Faridabad - Parties choosing to apply a supranational body of law, namely, UNCITRAL Arbitration Rules, in conjunction with Act, 1996 - Arbitration would be an international commercial arbitration to be decided in India under Act, 1996 - New Delhi or Faridabad would be seat of arbitral proceedings - Instantly proceedings held at New Delhi, and awards were signed in New Delhi - Apparently New Delhi was chosen as the seat of arbitral proceedings - Courts at New Delhi alone would have exclusive jurisdiction over the arbitral proceedings - Part of the cause of action having arisen at Faridabad irrelevant. (Para 98, 99, 100)
Facts of the case:
The Petitioner was awarded a contract for construction of Diversion Tunnels, Coffer Dams, Concrete Gravity Dams, Plunge Pools and Cutoff Walls of Subansiri Lower Hydroelectric Project on river Subansiri. Clause 67.3 of the agreement between the parties provides for dispute resolution through arbitration.
A Notice of Arbitration was issued by the Petitioner to the Respondent, in regard to payment of compensation for losses suffered due to abnormal delays and additional costs as a result of hindrances caused by the Respondent. A three-member Arbitral Tribunal was constituted as per clause 67.3 of the agreement under the Arbitration Act, 1996. The Tribunal delivered its unanimous award at New Delhi on 26.08.2016, by which the claims of the Petitioner aggregating to INR 424,70,52,126.66 (rectified) was allowed. The Respondent filed an application under Section 34 of the Arbitration Act, 1996 seeking to set aside these awards before the Court of the District and Sessions Judge, Faridabad, Haryana. The Petitioner filed an application under Section 151 read with Order VII Rule 10 of the Code of Civil Procedure, 1908 and Section 2(1)(e)(i) of the Arbitration Act, 1996, seeking a return of the petition filed under Section 34 for presentation before the appropriate Court at New Delhi and/or the District Judge at Dhemaji, Assam. After the constitution of a Special Commercial Court at Gurugram, the Section 34 petition filed at Faridabad was transferred to the said Gurugram Commercial Court.
The Special Commercial Court, Gurugram allowed the application of the Petitioner, and returned the Section 34 petition for presentation to the proper court having jurisdiction in New Delhi. The Respondent filed an appeal under Section 37 of the Arbitration Act, 1996 read with Section 13(1) of the Commercial Courts Act, 2015 before the High Court. The High Court held that the appeal filed under Section 37 of the Arbitration Act, 1996 was maintainable, and that Delhi being only a convenient venue where arbitral proceedings were held and not the seat of the arbitration proceedings, Faridabad would have jurisdiction on the basis of the cause of action having arisen in part in Faridabad. Thus the appeal was allowed and the judgment of the Special Commercial Court, Guru-gram was set aside.
Finding of the Court:
Appeals filed in the present case do not fall within Section 37 of the Arbitration Act,1996 and are not maintainable.
New Delhi was seat of arbitration and hence courts at New Delhi alone would have exclusive jurisdiction over the arbitral proceedings.
Result: Appeals allowed.
The provided legal document references several judgments that cite or discuss the case in question, particularly in the context of arbitration law, jurisdiction, and the concept of the "seat" of arbitration. Some judgments have explicitly acknowledged or relied upon this case to interpret provisions related to the jurisdiction of courts, the nature of arbitration clauses, and the interpretation of arbitration agreements.
For example, certain judgments have referred to this case when elaborating on the principles that the courts should read judgments as a whole and interpret them in their proper context, rather than as statutes or Euclidean theorems. Others have cited it to emphasize the importance of understanding the arbitration clause as an exclusive jurisdiction or seat designation, and the legal implications thereof.
Additionally, some judgments have discussed the case in the context of international arbitration law, particularly regarding the determination of the "seat" of arbitration and the importance of party autonomy. They have used this case to clarify that once a seat is designated, it typically functions as an exclusive jurisdiction, and courts should interpret arbitration clauses accordingly.
In summary, various judgments have cited or referenced this case to support principles related to the interpretation of arbitration agreements, the significance of the arbitration "seat," and the jurisdictional boundaries of courts in arbitration proceedings.
JUDGMENT :
R.F. NARIMAN, J.
1. Leave granted.
2. Three appeals before us raise questions as to maintainability of appeals under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Arbitration Act, 1996”), and, given the arbitration clause in these proceedings, whether the “seat” of the arbitration proceedings is New Delhi or Faridabad, consequent upon which a petition under Section 34 of the Arbitration Act, 1996 may be filed dependent on where the seat of arbitration is located.
3. At the outset, the facts in SLP (Civil) No.25618 of 2018 are set out as follows. On 16.01.2004, the Petitioner was awarded a contract for construction of Diversion Tunnels, Coffer Dams, Concrete Gravity Dams, Plunge Pools and Cutoff Walls of Subansri Lower Hydroelectric Project on river Subansri, with an installed capacity of 2000 MW, stated to be the largest Hydropower project yet in India. The project site is located in the lower Subansri districts in the States of Assam and Arunachal Pradesh. Clause 67.3 of the agreement between the parties provides for dispute resolution through arbitration. Clause 67.3 reads as follows:
“Any dispute in respect of which the Employer and the Contractor have failed to reach at an amicable settlement pursuant to Sub-Clause 67.1, shall be finally settled by arbitration as set forth below. The Arbitral Tribunal shall have full power to open up, review and revise any decision, opinion, instruction, determination, certificate or valuation of the Engineer.
(i) A dispute with an Indian Contractor shall be finally settled in accordance with the Indian Arbitration and Conciliation Act, 1996, or any statutory amendment thereof. The arbitral tribunal shall consist of 3 arbitrators, one each to be appointed by the Employer and the Contractor. The third Arbitrator shall be chosen by the two Arbitrators so appointed by the Parties and shall act as Presiding arbitrator. In case of failure of the two arbitrators, appointed by the parties to reach upon a consensus within a period of 30 days from the appointment of the arbitrator appointed subsequently, the Presiding arbitrator shall be appointed by the President of the Institution of Engineers (India). For the purposes of this Sub-Clause, the term “Indian Contractor” means a contractor who is registered in India and is a juridic person created under Indian law as well as a joint venture between such a contractor and a Foreign Contractor.
(ii) In the case of a dispute with a Foreign Contractor, the dispute shall be finally settled in accordance with the provisions of the Indian Arbitration and Conciliation Act, 1996 and read with UNCITRAL Arbitration Rules. The arbitral tribunal shall consist of three Arbitrators, one each to be appointed by the Employer and the Contractor. The third Arbitrator shall be chosen by the two Arbitrators so appointed by the Parties and shall act as Presiding arbitrator. In case of failure of the two arbitrators appointed by the parties to reach a consensus within a period of 30 days from their appointment on the Presiding Arbitrator to be appointed subsequently, the Presiding arbitrator shall be appointed by the President of the Institution of Engineers (India). For the purposes of this Clause 67, the term “Foreign Contractor” means a contractor who is not registered in India and is not a juridic person created under Indian Law. In case of any contradiction between Indian Arbitration and Conciliation Act, 1996 and UNCITRAL Arbitration Rules, the provisions in the Indian Arbitration and Conciliation Act, 1996 shall prevail.
(iii) Arbitration may be commenced prior to or after completion of the Works, provided that the obligations of the Employers, the Engineer, and the Contractor shall not be altered by reason of the arbitration being conducted during the progress of the Works.
xxx xxx xxx
(v) If one of the parties fail to appoint its arbitrator in pursuance of sub-clause (i) and (ii) above, within 30 days after receipt of
Kandla Export Corporation v. M/s OCI Corporation
Hakam Singh v. M/s. Gammon (India) Ltd.
Bharat Aluminium Co. (BALCO) v. Kaiser Aluminium Technical Service, Inc.
Indus Mobile Distribution Private Limited v. Datawind Innovations Private Limited
Union of India v. Hardy Exploration and Production (India) Inc. 2018 SCC Online SC 1640 [Para 6]
Reliance Industries Ltd. v. Union of India
Antrix Corporation Ltd. v. Devas Multimedia Pvt. Ltd.
Municipal Corporation of Delhi v. International Security & Intelligence Agency Ltd.
Arcot Textile Mills Ltd. v. Regional Provident Fund Commissioner
Hamanprit Singh Sidhu v. Arcadia Shares & Stock Brokers Pvt. Ltd.
Amar Nath Om Prakash v. State of Punjab
Union of India v. Amrit Lal Manchanda
Brahmani River Pellets Ltd. v. Kamachi Industries Ltd.
Enercon (India) Ltd. v. Enercon GmbH
Dozco India (P) Ltd. v. Doosan Infracore Co. Ltd.
Videocon Industries Ltd. v. Union of India
Harmony Innovation Shipping Ltd. v. Gupta Coal India Ltd.
Roger Shashoua v. Mukesh Sharma
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.