IN THE HIGH COURT OF DELHI AT NEW DELHI
Jasmeet Singh, Vibhu Bakhru, JJ
Supreme Infrastructure India Ltd – Appellant
Versus
Engineer-In-Chief, Army Headquarter – Respondent
O.M.P. (COMM) 15/2021 | I.A. 335/2021 | I.A. 336/2021 | I.A. 5882/2024
| Table of Content |
|---|
| 1. overview of the contractual dispute and history of the arbitral proceedings. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10) |
| 2. petitioner's assertion of procedural unfairness regarding the unnotified amendment of counter-claims. (Para 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18) |
| 3. respondent's contention that the amendments were procedural and the petitioner had adequate notice. (Para 19 , 20 , 21 , 22 , 23 , 24 , 25) |
| 4. judicial restraint under section 34 of the arbitration and conciliation act. (Para 26 , 27 , 28 , 29) |
| 5. assessment of arbitral record confirming knowledge and opportunity to contest specific amendments. (Para 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43) |
| 6. final determination that adherence to natural justice principles validates the arbitral decision. (Para 44 , 45 , 46 , 47 , 48 , 49) |
J U D G M E N T
1. The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (“the Act”) has been filed by the petitioner, assailing the arbitral award dated 13.08.2020 passed by the Sole Arbitrator in the matter of “Supreme Infrastructure v. Engineer-in-chief, Army Headquarter”.
FACTUAL BACKGROUND
2. On 02.06.2010 the respondent (respondent in the Arbitral Proceedings) issued a tender for construction of dwelling units including allied services for Officers, JCOs and ORs at Babina. The petitioner (claimant in the arbitral proceedings) participated in the tender process and was awarded the contract for a total value of approximately Rs. 50.7 crores. Pursuant thereto, a Contract Agreement was executed between the parties on 01.11.2010, incorporating the General Conditions of Contract governing military engineering works.
3. As per the contractual stipulations, the work was to be executed in three phases, with completion schedules extending between the years 2011 and 2013. The petitioner commenced execution of the work after mobilisation of men, machinery, tools, plant and materials at site.
4. According to the petitioner, from the inception of the project, execution of the work was impeded on account of factors attributable to the respondent, including delayed handing over of clear and obstruction-free site, frequent changes in drawings and specifications, additional and extra items of work, delayed approvals, and interruptions in execution owing to administrative reasons. Further running account bills were not processed and released in a timely manner, resulting in financial constraints and disruption of work.
5. On 19.12.2014, the respondent cancelled the Contract, citing slow progress and failure to adhere to milestones.
6. Since there were disputes between the parties in relation to termination of the Contract and financial claims, the petitioner invoked the arbitration clause. Upon the respondent’s failure to appoint an arbitrator, the petitioner approached this Court under Section 11 of the Act and the Sole Arbitrator was appointed.
7. The arbitral proceedings continued over several years. Pleadings were completed, evidence was led, and detailed oral arguments were addressed by both sides. Upon conclusion of arguments, the matter was reserved for award in January 2019.
8. After a lapse of more than one year from reserving of the award, the Sole Arbitrator reopened the proceedings and permitted the respondent to amend its counter-claims. The amendment resulted in enhancement of the quantum of counter-claims, which was stated to be on account of correction of calculations. The petitioner objected to the amendment on the ground that it caused serious prejudice and was permitted at an advanced stage of the proceedings.
9. The Sole Arbitrator thereafter passed the impugned arbitral Award dated 13.08.2020. By the said Award, the Sole Arbitrator held that the petitioner had abandoned the project, rejected the majority of the petitioner’s claims including claims for prolongation costs, and allowed substantial portions of the respondent’s counter-claims.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.