SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(Del) 156

IN THE HIGH COURT OF DELHI AT NEW DELHI
Avneesh Jhingan, J
Shiva Engineering Company – Appellant
Versus
Reliance Communication Ltd. – Respondent
O.M.P.(MISC.)(COMM.) 761/2025



Advocates:
For the Appellants/Petitioners: Vijay Joshi, Kuldeep Singh
For the Respondents: Charu Bansal, Gaurav Arora, Aditya Ganju, Hasan Murtaza, Sameer Sharma, Samanyu Sethi, Ankit Sinha, Vatsal Agrwal, Sahil Safdar

The court may extend an arbitral tribunal's mandate post-expiry upon showing sufficient cause. A party’s diligent pursuit of remedies in alternative forums, even if incorrect, evidences good faith, negates intentional delay, and justifies an extension to ensure the timely and effective resolution of disputes.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 29A(4) and 29A(5) - Arbitral proceedings - Extension of mandate - Power of the court to extend time for the arbitral award - Sufficient cause as a requirement for extension - Extension permissible even after expiry of mandate. (Para 7)

(B) Arbitration - Efficient resolution of disputes - Requirement of "sufficient cause" - Evaluation based on facts and circumstances rather than fixed formulas - Pursuit of remedies in incorrect forums demonstrates good faith and lack of intentional delay. (Paras 11, 14, 17)

Facts of the case:
The petitioner, a small-scale entity, faced an expiry of the arbitral tribunal's mandate due to delays in communication and legal proceedings involving a co-party. After discovering the expiry, the petitioner sought remedies through alternative administrative and judicial channels before approaching the appropriate court. The respondents opposed the request for extension, citing a significant delay in filing the application.

Findings of Court:
The court observed that the duration consumed in initial service and the statement of defense, along with legal developments concerning insolvency and moratoriums, contributed to the delay. Since the petitioner consistently sought remedies, the court found no evidence of intentional delay or abuse of process.

Issues: Whether the court should exercise its discretion to extend the arbitral mandate post-expiry, and whether the time spent in incorrect forums constitutes "sufficient cause" for delay in filing the petition.

Ratio Decidendi: "Sufficient cause" for the extension of an arbitral mandate under the relevant Act must be evaluated based on the specific facts and circumstances of each case. Where a party pursues legal remedies diligently, even in inappropriate forums, the requirement of "sufficient cause" is satisfied, justifying the extension of time to prevent the frustration of the arbitration process.

Result: Petition allowed. Mandate extended by one year.

Table of Content
1. factual context of arbitration mandate extension under section 29a(5). (Para 1 , 2 , 3)
2. parties' contentions regarding timely filing and 'sufficient cause' for delay. (Para 4 , 5)
3. court discretion in extending arbitration mandate timelines. (Para 6 , 7 , 8 , 9 , 10)
4. determination of sufficient cause based on case-specific circumstances. (Para 11 , 12 , 13 , 14 , 15 , 16 , 17)
5. formal order granting one-year extension of the arbitral tribunal's mandate. (Para 18)

AVNEESH JHINGAN, J. (ORAL)

1. This petition is filed under Section 29A(5) of the Arbitration and Conciliation Act, 1996 (for short „the Act‟) seeking extension of the mandate of the Arbitral Tribunal for a period of one year.

2. The brief facts are that the petitioner is a unit registered under the Micro, Small and Medium Enterprises Development Act, 2006 (for short „MSMED Act‟). There was dispute amongst the parties and the petitioner in March 2020 approached the Micro and Small Enterprises Facilitation Council (for short ‘MSME Council’) and the matter was referred on 14.07.2021 to Delhi International Arbitration Centre (for short ‘DIAC’). The first date before the Arbitrator was 12.11.2021. Respondent no.1 put in first appearance on 09.09.2022 before the Arbitrator and respondent no.2 appeared on 01.12.2022 and sought time. On 23.03.2023, a statement of defence was filed by respondent no.2 alongwith an application under Section 16 of the Act. The order was reserved on 11.01.2024. On 29.06.2024, the petitioner was informed that the mandate of the Arbitral Tribunal had expired.

3. On 11.11.2024, the petitioner attempted to approach the MSME Council for getting the expiry of the mandate redressed but was not successful. On 29.01.2025, the petitioner approached the learned District Judge (Commercial Court), Patiala House Courts, New Delhi, for extension of the mandate but the petition was rejected on 07.08.2025 as not maintainable. Thereafter, on 26.08.2025, the present petition was filed.

4. Learned counsel for the petitioner submits that considerable time was consumed in securing appearance of the respondents. The application filed by respondent no.2 under Section 16 of the Act was argued, the order was reserved and in the meantime the mandate of the Arbitral Tribunal expired. The contention is that there was no delay on part of the petitioner. Decision of the Supreme Court in M/s Ajay Protech Pvt. Ltd. v. General Manager & Anr. 2024 INSC 889 is relied upon to fortify the contention that the mandate can be extended even after the expiry of the period.

5. Per contra, there was a delay of four hundred days in approaching this court and no sufficient cause is pleaded. It is argued that even the Commercial Court was approached after a period of two hundred thirty-nine days. The application is belated and should be rejected on this ground alone.

5.1 Reliance is placed upon the decision in Madanlal v. Shyamlal (2002) 1 SCC 535 to buttress the argument that „sufficient cause‟ requires a higher degree of proof than „reasonable cause‟. Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd. 2024 SCC OnLine SC 2494 is relied to contend that extension is not to be granted mechanically but only in cases where sufficient cause is shown. The decisions in Balwant Singh v. Jagdish Singh & Ors. (2010) 8 SCC 685, Skylark Cagers India Pvt. Ltd. v. Institute of Liver and Biliary Sciences 2023 SCC OnLine Del 1276, and H. P. Singh v. G. M. Northern Railways & Ors. 2023 SCC OnLine J&K 1255 are also relied upon to oppose the extension.

6. Heard the learned counsel for the parties. No contentions other than those noted above have been pressed.

7. On a reading of Sections 29A(4) and 29A(5) of the Act it emerges that the period can be extended by this court upon sufficient cause being shown and extension can be either prior to or after the expiry of the period.

8. One and a half years in arbitration was consumed in completing service and in filing of the statement o

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top