SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 534

IN THE HIGH COURT OF DELHI AT NEW DELHI
MINI PUSHKARNA, J.
Kalpataru Projects International Limited - Petitioner
Versus
JSW Infrastructure Limited - Respondent
O.M.P.(I) (COMM.) 218 of 2026 & I.A. Nos. 14254 of 2026 & 14255 of 2026
Decided On : 25-05-2026

Advocates Appeared:
For the Petitioner:Mr. Dayan Krishnan, Sr. Advocate with Dr. Sunil Mittal, Mr. Malak Bhatt, Mr. Anu Tiwari, Mr. Prithviraj Dey and Mr. Sukrit Seth.
For the Respondent:Mr. Darpan Wadhwa, Sr. Advocate with Mr. Nakul Mohta, Ms. Misha Rohatgi Mohta, Mr. Amer Vaid and Ms. Sneha Menon.

Injunctions against invoking unconditional bank guarantees are only granted in cases of egregious fraud or irretrievable injury. Disputes regarding liquidated damages and performance failures are evidentiary matters reserved for the arbitral tribunal and do not justify summary judicial interference in the interim stage.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 9 - Interim measures - Injunction against invocation of an unconditional and irrevocable bank guarantee - Principles for grant - Requires proof of egregious fraud or irretrievable injustice - Mere commercial or financial hardship fails to meet the threshold - Such guarantees are independent contracts distinct from underlying disputes. (Paras 30, 31, 32, 33)

(B) Contractual interpretation - Extension of time - Levy of liquidated damages - Effect of provision in contract stating extension of time does not preclude right to levy damages - Whether delay is attributable to the contractor or the entity granting extension is an evidentiary matter to be decided by an arbitrator. (Paras 17, 21, 23)

(C) Scope of Section 9 petition - Court’s role in summary proceedings - Limited to assessing prima facie case for interim relief - Not intended for detailed adjudication of substantive contractual disputes or determination of liability for performance failure - Such issues are reserved for the arbitral tribunal. (Paras 9, 17, 24)

Facts of the case:
A contractor filed a petition seeking an interim injunction to restrain the principal from invoking an unconditional performance bank guarantee and levying liquidated damages following the termination of a contract. The contractor contended that the principal had granted time extensions without initially claiming damages, thereby creating an estoppel. The principal maintained that the contract permitted the levy of damages for deficient work and that the bank guarantee remained an independent and unconditional instrument.

Findings of Court:
The court observed that the bank guarantee was an autonomous, unconditional instrument and that the contractor failed to plead or establish any case of egregious fraud or irretrievable harm. Financial or commercial hardship does not constitute irretrievable injury. Furthermore, contractual clauses explicitly allowed for the recovery of liquidated damages despite extensions of time, with conflicting claims regarding the cause of delay requiring evidentiary proof before the arbitrator.

Issues: The main issues were whether the court could restrain the invocation of an unconditional bank guarantee in the absence of fraud or irretrievable injury, and whether a prima facie case was established to stay the recovery of liquidated damages pending arbitration.

Ratio Decidendi: Courts should be slow to interfere with the invocation of unconditional bank guarantees, as they act as independent contracts. Enforcing such guarantees is distinct from the underlying performance disputes between parties. As the contract allowed for damages even during extension periods, and considering disputes regarding performance and the cause of termination involved complex evidence, the court declined to exercise its discretionary power to grant an injunction.

Result: Petition dismissed.

Table of Content
1. factual background of the arbitration dispute and contract termination. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. parties argument regarding liquidated damages and bank guarantee invocation. (Para 7 , 8)
3. scope of section 9; prima facie assessment of liquidated damages applicability. (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24)
4. unconditional bank guarantees remain enforceable regardless of underlying contractual disputes. (Para 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34)
5. distinguishing prior precedents and final rejection of injunctive relief. (Para 35 , 36 , 37 , 38 , 39)

JUDGMENT :

MINI PUSHKARNA, J.

1. The present petition has been filed under Section 9 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”), seeking inter alia relief for staying, restraining and injuncting the respondent from acting upon, giving effect to or enforcing the Letter dated 07th May, 2026, issued by the respondent, in so far as the said Letter seeks to levy liquidated damages against the petitioner for the period which was validly extended by the respondent earlier, without levy of liquidated damages. There is a further prayer to restrain the respondent from initiating any coercive steps against the petitioner, including, invoking the Bank Guarantee dated 18th July, 2025.

2. As per the case put forth by the petitioner, the present dispute arises out of a Contract Agreement dated 14th September, 2023 entered between the parties pursuant to the Letter of Intent dated 19th January, 2022 and Purchase Order dated 05th February, 2022, for execution of 131 Km Iron Ore Slurry Pipeline Project in the State of Odisha, wherein, the petitioner was required to complete the works within a stipulated period of 24 months, i.e., by 18th January, 2024. However, the work could not be completed within the original timeline on account of various circumstances. Thus, respondent issued Amendment no. 1 dated 27th December, 2023, whereby, the completion date was extended till 31st May, 2026, without levy of any liquidated damages.

3. Subsequently, three other Amendment Letters were issued by the respondent, and on 07th May, 2026, the respondent issued the Amendment No. 5 to the Purchase Order, whereby, substantial work was descoped from the petitioner’s scope and the contract price was reduced from Rs. 240 crores to 123.20 crores, amounting to a reduction of nearly 50%. The said unilateral amendment was accompanied by a covering letter directing the petitioner to complete the balance work by 31st May, 2026, and simultaneously threatening risk purchase. In the same communication, the respondent also reserved rights to levy damages for alleged delay upto 31st May, 2026.

4. Thereafter, the respondent issued a Formal Notice of Risk Purchase dated 15th May, 2026 invoking Clause 21 of the Contract Agreement, by way of which the respondent alleged that the petitioner has completed only 47% of the agreed contractual scope and further called upon the petitioner to forthwith remedy and/or rectify the default.

5. As per the petitioner, since the respondent failed to fulfil its obligations, the petitioner terminated the Contract Agreement vide its Letter dated 18th May, 2026.

6. Since the respondent is now seeking to invoke risk purchase, threaten levy of liquidated damages against the petitioner, and invoke the Bank Guarantee, the present petition has come to be filed.

7. On behalf of the petitioner, following submissions have been made:

7.1 The Amendment No. 1 dated 27th December, 2023 made by the respondent to the Purchase Order dated 05th February, 2022, explicitly states that liquidated damages charges would not be applicable for validity extension of the Purchase Order.

7.2 The said Amendment No. 1 dated 27th December, 2023 clearly evinces that the respondent itself understood and accepted that the delay in completion of the project was not attributable to the petitioner. Thus, the respondent categorically excluded liqui

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top