SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Online)(HP) 1904

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
G.S. Sandhawalia, CJ, Bipin Chander Negi, J
Tarun Mahindroo – Appellant
Versus
H.P. Power Corporation Limited – Respondent
Arbitration Appeal No. 11 of 2020



Advocates:
For the Appellants/Petitioners: Suneet Goel, Vishwas Kaushal
For the Respondents: Shashi Shirshoo

In the absence of contemporaneous evidence, claims for loss of profit due to contract prolongation are unsustainable, particularly when the agreement contains a specific clause precluding compensation for lost profits or advantages resulting from the foreclosure of the contract.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Foreclosure of contract - Claim for loss of profit and overheads due to prolongation of work - Arbitrator rejected claim for lack of evidence and presence of specific restrictive clause (Clause 36) in contract agreement - High Court upheld the rejection, confirming that Appellate Court cannot interfere when award is based on specific contract terms and absence of evidence - Parties are bound by the express agreement terms regarding foreclosure compensation. (Paras 6(ii), 6(iii), 7)

Facts of the case:
The appellant was awarded a work contract for bachelor accommodation, which was eventually foreclosed due to a land dispute. The Arbitrator awarded certain damages and costs but rejected the appellant's claim for loss of profit and overheads totaling Rs. 29,40,495/-, citing the lack of evidence and the restrictive nature of Clause 36 of the contract, which bars compensation for lost profits arising from foreclosure. The High Court dismissed the subsequent objection petition under Section 34.

Findings of Court:
The court held that the appellant failed to lead any oral or documentary evidence to substantiate the claim for loss of profit. Furthermore, the court observed that Clause 36 clearly stipulates that the contractor is not entitled to compensation for potential profits or advantages had the work been completed full-term upon any foreclosure of the contract.

Issues: Whether the rejection of the claim for loss of profit and overheads by the Arbitrator, affirmed by the Section 34 court, was legally permissible in the absence of evidence and in light of the specific contractual clause prohibiting such compensation upon foreclosure.

Ratio Decidendi: An award cannot be sustained if it lacks evidence; where a specific contract clause explicitly excludes compensation for loss of profit during foreclosure, the contractor cannot recover such amounts, especially when no contemporaneous evidence was produced to demonstrate actual losses.

Result: Appeal dismissed.

Bipin Chander Negi, Judge

The present appeal has been preferred against the impugned judgment dated 23.08.2019, whereby objections filed under Section 34 of the Arbitration and Conciliation Act, preferred by the present appellant, have been rejected. Admittedly, in the case at hand, an award with respect to construction of work for bachelor accommodation at Sundarnagar, District Mandi, H.P, for a sum of Rs. 1,96,03,299/- was granted in favour of the present appellant. The work was required to be completed within 18 months. The land whereupon the building was to be constructed was owned by the State Government and possessed by the respondent-Corporation. However, the appurtenant land through which the passage existed to reach the site was owned by the BBMS. Post-award, site development to the tune of Rs. 1,02,654/- before August 2011 had been done by the present appellant. The appellant, right from 31.08.2011 to 23.06.2016, attempted to get delivery of the site, as is evident from letters written by the appellant in this regard (Annexure C-3 with the claim petition filed before the Arbitrator). Similarly, the respondent, in terms of Annexure-III appended with the reply filed to the claim petition, had extended the date of completion of the work till 15.08.2014. The closure of work had taken place on 16.12.2016, vide Annexure C-4 appended with the claim petition filed before the Arbitrator.

In the aforesaid backdrop, taking into account the dilatory conduct of the respondent and the optimistic hope of the present appellant to complete the work, damages to the tune of Rs. 1 lakh were awarded by the Arbitrator on account of the inordinate and delayed closure of the contract on 16.12.2016. Other than the aforesaid, costs of the arbitration proceedings had also been awarded in favour of the appellant. Since the claim for refund of security and earnest money was admitted by the respondent, the same had been granted by the Arbitrator in favour of the present appellant. The aforesaid amount awarded was to carry interest at the rate of 9%. If the same was not paid within one month of the passing of the award, then it was to carry an enhanced rate of interest at the rate of 12%.

The sole contention raised in the objection petition under Section 34 pertained to the non-grant of the claim to the extent of Rs. 29,40,495/- claimed as loss of profit and overhead on account of prolongation of the contract by the appellant. The aforesaid claim had been rejected by the Arbitrator on account of absence of proof and in terms of Clause 36 of the contract entered into inter se the parties. The learned Single Judge, while dismissing the claim, found no fault in the reasoning of the Arbitrator and concurred with the same, while reproducing the said clause and holding as under:-

6(ii) The above Clause empowers the respondent to abandon or reduce the scope of the work for any reason whatsoever. The contractor will have no claim, in terms of this Clause, to any compensation on account of any payment of compensation, on account of any profit or advantage which he might have derived from the execution of the works in full, but which he could not derive on account of fore-closure either of part or whole works.

Clause 36.1, when read in its entirety, though provides that in case of fore-closure of the contract, the contractor has to be paid at the contract rates for full amount of the works executed at the site and in addition, reasonable amount certified by the Engineer-in-Charge for the items, which could not be utilized on the works to full extent because of the fore-closure. The items mentioned in this Clause are in respect of preliminary works, i.e. temporary access roads, temporary labour huts, staff quarters, site office, storage accommodation workshop, installation and dismantling of construction equipment and water storage tanks etc. Clause also provides for materials in similar way.

6(iii) Thus, in terms of Clause 36.1 of the agreement du

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top