IN THE HIGH COURT OF JHARKHAND AT RANCHI
DEEPAK ROSHAN, J.
Jharkhand Ispat Private Limited – Appellant
Versus
Damodar Valley Corporation – Respondent
W.P.(C) No. 3578 of 2022
Decided on : 04-05-2026
| Table of Content |
|---|
| 1. factual overview of electricity dispute and assessment history. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13) |
| 2. parties' contentions on jurisdiction and procedural requirements. (Para 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39) |
| 3. writ maintainability despite alternative statutory remedies. (Para 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50) |
| 4. mandatory nature of inspection reports for valid assessments. (Para 51 , 52 , 53 , 54 , 55 , 56 , 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64 , 65 , 66 , 67 , 68 , 69 , 70 , 71 , 72 , 73 , 74 , 75 , 76 , 77) |
| 5. quashing illegal assessment and directing fresh assessment procedure. (Para 78 , 79 , 80 , 81 , 82 , 83 , 84) |
JUDGMENT :
DEEPAK ROSHAN, J.
1. Heard learned counsel for the parties.
2. The present writ petition has been filed challenging the order dated 16.07.2022 passed by the Superintendent Engineer (E), Damodar Valley Corporation (Annexure-8 to the Writ Petition), exercising powers under section 126 of the Electricity Act, 2003, in compliance to the order passed by this Court dated 07.04.2022, in W.P.(C) No.95 of 2008.
3. The instant writ petition involves a unique dispute and as such, very briefly the facts are narrated, as submitted before this Court.
4. The Petitioner-Company is a manufacturing unit of Iron and Steel having a contract demand of 8000 KVA and the electrical connection had been taken from the respondent herein.
On 10/16.10.2007, pursuant to a request made by the petitioner for replacement of defective meter, the energy meter was replaced, acceding to such request of the petitioner.
All of a sudden, on 01.01.2008, the electrical connection of the unit was discontinued in the evening hours, the reason thereof came to the knowledge of the petitioner only on 02.01.2008, that an F.I.R. had been registered and allegation of theft of electricity has been levelled against the petitioner.
5. The petitioner approached this Court by filing a writ petition vide W.P.(C) No. 95 of 2008 and also filed an Interlocutory Application for restoration of its electrical connection vide I.A. No.138/2008.
6. A Counter Affidavit was filed by the respondents in the writ petition inter-alia on the ground that an inspection was carried out in the factory premises and certain seals were found to be missing and small copper wire (six in numbers) was used for shorting the electrical connection and based upon which, the connection was discontinued.
It was also averred in the Counter Affidavit filed by the Respondents that there had been detection of huge power loss in terms of Check Meter installed at Ramgarh Sub-Station from where electricity is being supplied to the petitioner, as also, other consumers and on the basis of alleged tampering of meter, the difference of actual supply and consumption is found to be 20%
lesser and as such, the electrical connection was discontinued.
On 24.01.2008, the petitioner was served with a provisional estimated of penal amount to the tune of Rs.17.80 Crores approximately. The said provisional estimate was in two parts:
a) Unit Charges
b) Demand Charges
7. The provisional assessment was based upon the units recorded in the meter of Ramgarh Sub-station and difference in units recorded in the meter of petitioner installed in the factory premises.
8. The writ petition was heard by this Court and vide order dated 28.01.2008, the respondents were directed to restore the electrical connection within 48 hours, subject to petitioner depositing Rs.1.50 crores against the provisional bill, which were subject to future adjustment, if any. Since then, the writ petition was pending.
9. Finally, the writ petition came to be heard on 07.04.2022 by a co-ordinate bench of this Court and by a detailed order, the writ petition was disposed of inter-alia making following observations:
“So far relief sought by the petitioner, pursuant to their amendment application is concerned,
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.