SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Online)(KER) 4716

HIGH COURT OF KERALA
P. B. Suresh Kumar, C.S. Sudha, JJ
M/S.ORIENTAL STRUCTURAL ENGINEER PVT. LTD. – Appellant
Versus
THE SECRETARY, PUBLIC WORKS DEPT. – Respondent
Arb.A 50 2015



A mutual agreement is essential for amending contract terms regarding currency proportions; without it, claims for additional costs due to currency changes are not enforceable.

Headnote:

Arbitration - Dispute Resolution - Arbitration and Conciliation Act, 1996 - Sections 34, 37 - The court examined the applicability of clauses concerning currency adjustments in contracts, emphasizing the necessity of mutual agreement for amendments to be valid.

Fact of the Case:

The appellant, a contractor, claimed additional costs due to the respondent's refusal to amend the currency proportion for payments, despite a recommendation from the Engineer. Disputes arose, leading to arbitration, where the claim was rejected by a majority of the Arbitrators.

Finding of the Court:

The court upheld the Arbitration Tribunal's decision, stating that without a mutual agreement to amend the contract terms regarding currency proportions, the claim for additional costs was not maintainable, thus affirming the Award.

Issues: Whether the respondent's refusal to change the currency proportion constituted a breach of contract, allowing the contractor to recover additional costs.

Ratio Decidendi: The necessity for mutual agreement before any amendments to contract terms is crucial, and failure to establish such agreement renders claims for additional payments invalid.

Final Decision: The appeal is allowed, setting aside the impugned order and the Arbitration Tribunal's Award.

J U D G M E N T

C.S.Sudha, J.

This appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 ('the Act', for short) is against the order dated 05/02/2015 in O.P.(Arbitration) No.418/2011 of the Additional District Judge–II, District Court, Ernakulam.

2. The appellant is the petitioner in the aforesaid O.P.

(Arbitration) and the claimant/contractor in the arbitral proceedings. The respondent herein is the respondent in the said proceedings. The parties in this appeal will be referred to as described in the arbitral proceedings.

3. The claimant/contractor was awarded the contract for the work of "KSTP–Phase I – Upgradation of State Highway from Muvattupuzha – Thodupuzha and Muvattupuzha – Angamali”, relating to which the parties entered into a contract agreement dated 07/11/2002. The letter of acceptance was issued on 01/10/2002. The work was agreed to be completed within a period of 24 months, which period was thereafter extended. The work was completed on 31/01/2007. Clause 67 of the Conditions of Particular Application (CoPA) of the contract agreement sets out the procedure to be followed in case, disputes arose between the parties during the course of execution of the works. Several disputes arose between the parties. Disputes no.11 and 12 pertain to refund of deduction of 1% of the value of work effected towards Workers’ Labour Welfare Fund Dispute and compensation for not effecting the change in foreign currency proportion respectively. The disputes were referred to the Dispute Review Board (DRB) as per Clause 67.1 of CoPA. However, the DRB could not make its recommendation within the period of 56 days provided for in CoPA and hence arbitration was initiated by the claimant. Pursuant to Clause 67.3 of CoPA, the claimant and the respondent appointed one Arbitrator each. The said two Arbitrators appointed a third Arbitrator as the Presiding Arbitrator.

4. In the present appeal we are concerned with dispute no.12 alone. Dispute No.12 is pertaining to payment of additional costs stated to have been incurred by the claimant on account of continued delay on the part of the respondent/Employer in changing the currency proportion for payment in accordance with the provisions of Sub-Clause 72.4 of the General Conditions of Contract (GCC). The claimant put up a claim for reimbursement of additional cost of ₹ 83,98,228/- towards loss stated to have been sustained due to the failure of the respondent/Employer to change the proportion of foreign currency from 24% to 2% as recommended by the Engineer for the period from 01/04/2004 to 31/02/2005 and also pay further amount in the changed proportion for all payments effected after 01/01/2006.

4.1. According to the claimant, the currency requirement was estimated based on the situation at the time of Tender on 14/06/2002. Thereafter the foreign currency requirement got reduced and it was assessed as 2% as against the 24% quoted in the Tender. Clause 36.1 of CoPA encourages the claimant to use as far as possible materials produced in India so that foreign currency requirement is reduced to the minimum.

Therefore, while organizing the procurement during the course of execution of works, the claimant was guided by the encouragement contained in Clause 36.1 in minimizing imports. As a result, the requirement of foreign currency came down drastically to 2% in the place of 24%. The Engineer recommended to the respondent/Employer to accept this change as per the agreement reached on 02/11/2004. In order to effect this change, it was necessary to execute a Supplementary Agreement and so as directed, the claimant submitted a draft of the same. The respondent did not agree to the change as the same would cause financial loss to them and hence change in foreign currency proportion was not effected.

4.2. As per Clause 72.4 of CoPA, it was obligatory on the part of the respondent/Employer to agree to the change in proportion of the currency. Due to refusal by the respondent to change the c

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top