IN THE HIGH COURT OF KERALA AT ERNAKULAM
MURALI PURUSHOTHAMAN, J
PARAMESWARA WARRIER – Appellant
Versus
POWER GRID CORPORATION OF INDIA – Respondent
O R D E R
The Civil Revision Petition is filed against the order dated 21.11.2016 in O.P.(Ele) No. 136 of 2011 passed by the Court of the Additional District Judge, North Paravur.
2. The Power Grid Corporation of India Ltd. (hereinafter referred to as the Corporation) drew 400 kV Cochin-Thrissur electric line through the property of the petitioner comprised in Sy. No.386/1- 3 of Vengola Village and for the said purpose, certain trees were cut and removed. As the lines were drawn, a large extent of the land underneath and adjacent to the lines was injuriously affected. However, in spite of the huge loss suffered, only a meagre amount was paid to the petitioner as compensation. Aggrieved thereby, the original petition was filed under Sections 10 and 16 (3) of the Indian Telegraph Act, 1885 r/w Section 51 of the Indian Electricity Act, 1910.
3. The original petition was tried along with two other original petitions filed by the petitioner as the properties involved in all the petitions are lying in a stretch and similarly situated and the nature of evidence in support of the claims was the same. A common order was passed in the three original petitions.
4. The learned District Judge f
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.