SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Mad) 65201

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N.ANAND VENKATESH, J
NJR Constructions Pvt. Ltd. – Appellant
Versus
Union of India – Respondent
Arbitration O.P.(Com.Div.) No.291 of 2023



Advocates:
For the Appellants/Petitioners: Mr.P.J.Rishikesh
For the Respondents: Ms.V.Sudha, SCGPC

The court established that an arbitral award can be set aside if it lacks intelligible reasoning and fails to assess critical issues, such as the responsibility for delay in contract performance.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral award - Petitioner contended delay in work completion and claims denied by Arbitrator - Arbitrator failed to ascertain responsibility for delay and misapplied legal principles - Court found award unintelligible regarding claims for extension and interest - Award partially set aside. (Paras 11, 20, 32)

(B) Arbitration - Requirement of adequate reasoning - An award must provide intelligible reasoning and not merely confirm prior reports without substantive analysis - Failure to do so warrants judicial intervention. (Paras 12, 20)

Facts of the case:
The petitioner was awarded a construction contract subject to a stipulated completion date. Disputes regarding delays and claims led to arbitration, wherein the sole Arbitrator denied most claims based on perceived delays attributable to the petitioner.

Findings of Court:
Court determined the Arbitrator’s reasoning was inadequate concerning delay attributions, and awarded modified interest and costs due to unsustainable conclusions by the Arbitrator.

Issues: Key issues included the attribution of delay and the adequacy of reasoning in the Arbitrator’s award regarding liquidated damages and interest.

Ratio Decidendi: The court concluded that the Arbitrator’s failure to properly evaluate delay causes was a critical flaw, which rendered the award unintelligible and necessitated its modification.

Result: Petition partly allowed; certain claims of the Arbitrator set aside with modifications to interest and costs awarded.

Table of Content
1. arbitration dispute background and claims. (Para 3 , 4)
2. assessment of claims and interests. (Para 5 , 9 , 27)
3. responsibility for contract delays. (Para 8 , 10 , 11)
4. prevention principle in construction contracts. (Para 14 , 19 , 20)
5. final decision on arbitration award. (Para 32)

ORDER

This is a petition filed by the petitioner under Section 34 of the Arbitration and Conciliation Act, 1996 (for brevity, the Act) against the award dated 30.9.2021 passed by the sole Arbitrator.

2. Heard both.

3. The case of the petitioner is as follows :

(i) The petitioner participated in the tender called for by the respondent for construction of an administrative building including development works, etc., for constructing a compound wall and for various other works at Composite Regional Centre/National Institute for Mentally Handicapped at Venkatachalam (M), Nellore District, Andhra Pradesh. The work was awarded in favour of the petitioner through letter dated 24.11.2016. The agreement was entered into between the parties and the agreement stipulated that the work must be completed by 24.11.2017. However, the actual date of completion of work was only on 11.2.2019.

(ii) Later, the petitioner raised a final bill for a sum of Rs.11,48,16,841/-. Pursuant to that, some disputes had arisen between the parties during execution and ultimately, the matter landed up before the sole Arbitrator.

(iii) Before the sole Arbitrator, the petitioner made the following claims :

(1) to pay a sum of Rs.8,31,675/- towards difference between ornamental grill and agreement item of MS grills provided for windows;

(2) to grant extension of time upto 11.2.2019 without imposing any levy and to release a sum of Rs.1,00,10,979/-;

(3) to pay a sum of Rs.1,99,46,911/- towards escalated price under Clauses 10C and 10CA of the agreement;

(4) to pay a sum of Rs.33,17,740/- towards GST to be paid to the Government;

(5) to pay a sum of Rs.95,24,688/- towards cost of overhead charges incurred for prolongation period of 444 days;

(6) to pay a sum of Rs.82,50,000/- towards compensation for loss of business;

(7) to pay interest at the rate of 7.5% from the due date of payment of final bill till the actual date of payment and to pay interest at the rate of 18% from the date of payment of final bill till the date of payment of award amount; and (8) to pay a sum of Rs.5 lakhs towards costs of arbitration.

(iv) Before the sole Arbitrator, the respondent raised a defence that the petitioner was expected to start the work on 09.12.2016 and complete the same on 24.11.2017, that a total of 350 days was fixed for the completion of the work, that however, right from the beginning, the petitioner was slow in executing the work, that there was a delay of 444 days in completing the work against the stipulated period of 350 days, that the delay was attributable to the petitioner and that various claims made by the petitioner were not sustainable. Ultimately, the respondent sought for dismissal of the claim petition.

(v) On considering the materials that were relied upon by the learned counsel on either side, the sole Arbitrator passed an award dated 30.9.2021 in the following terms :

Claim No.Details of claimAmount of claim in Rs.Amount of award in Rs.
1Ornamental grill8,31,675NIL
2Recovery of levy imposed1,00,10,979NIL
3Escalation under Clauses 10C & 10CA1,99,46,91137,17,916
4GST RecoveryDetails to be submittedAs per actual
5Overhead charges95,24,6883,48,408
6Business Loss82,50,00032,925
7InterestAs stated in the claim
8Cost of arbitration5,00,000 NIL

(vi) Aggrieved by that, the petitioner is before this Court.

4. The respondent filed a counter to this petition by way of reply wherein they refuted the claims made by the petitioner. Ultimately, the respondent sought for dismissal of this petition.

5. This Court has carefully considered the submissions of the learned counsel on either side and perused the materials available on record and more particularly the impugned award.

6. Even though the lea

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top