SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(Mad) 69900

IN THE HIGH COURT OF JUDICATURE AT MADRAS
MR. V. LAKSHMINARAYANAN, J
Sree Infratech India Private Limited – Appellant
Versus
The Chairman (MSEFC) & Director (Ind. & Com), Micro and Small Enterprises Facilitation Council (MSEFC) – Respondent
W.P.No.33528 of 2025 & WMP.Nos.37673 & 37676 of 2025



Advocates:
For the Appellants/Petitioners: Mr.V.Rani, Senior Counsel, for Mr.Pramodh Kumar
For the Respondents: Mr.A.Tamilvannan, Additional Government Pleader (P), Mr.M.Nandakumar

The jurisdiction of the MSEF Council to adjudicate disputes under the MSME Act is determined at the arbitration stage and not prematurely during mediation.

Headnote:(A) Micro, Small and Medium Enterprises Development Act, 2006 - Section 18 - Jurisdiction of MSEF Council to adjudicate on disputes regarding works contracts and alternative dispute resolution through mediation and arbitration - The issue of jurisdiction was deemed premature at the mediation stage without an adjudication of merits. (Paras 1, 10, 16, 27)

(B) Arbitration and Conciliation Act, 1996 - Sections 65 to 81—Provisions for mediation and the principle that disputes, including jurisdiction issues, should be addressed within arbitration proceedings if mediation fails. (Paras 15, 20, 26)

Facts of the case:
The petitioner engaged a subcontractor for a project but contested the jurisdiction of the MSEF Council to handle a claim filed by the subcontractor under the MSME Act regarding payment for the work done. The subcontractor alleged abandonment of the contract and raised a claim for payment along with interest under the MSME Act.

Findings of Court:
The court found the issue of jurisdiction to be premature and ruled that such issues should be resolved only after arbitration processes were exhausted. The petitioner was directed to follow up with a petition for jurisdiction under the Arbitration Act if needed.

Issues: Whether the MSEF Council has jurisdiction to handle disputes regarding works contracts under the MSME Act and the appropriateness of initiating arbitration processes.

Ratio Decidendi: The court reasoned that mediation under the MSME Act does not determine jurisdiction and that issues can only be raised in subsequent arbitration proceedings. Therefore, the petitioner’s plea was premature.

Result: Writ petition dismissed.

Table of Content
1. claims of abandonment and contractual obligations (Para 1 , 2 , 4)
2. arguments regarding jurisdiction under the msme act (Para 11 , 12)
3. role of mediation and arbitration in dispute resolution (Para 15 , 20)
4. court's dismissal of the petition as premature (Para 24 , 27)

ORDER

The petitioner claims to be a reputed infrastructure company. It engages in road construction and infrastructure development. It was awarded a contract by M/s.DRAI Private Limited. A sub-contract for electrical utility shifting under NH-844 project was awarded to the petitioner. The petitioner, in turn, appointed the second respondent for execution of the electrical utility shifting works. The sub contract was preceded by a Letter of Intent (hereinafter referred to as 'LOI') dated 01.10.2021. A Memorandum of Understanding (hereinafter referred to as 'MOU') dated 23.02.2022 was entered into by both the parties. The petitioner alleges that the sub contract had to be executed on a back-to-back basis. In terms of the LOI and MOU, the second respondent was responsible for execution, coordination, certification and obtaining approvals.

2. The petitioner states that the payment to be made was subject to certification by TANGEDCO and NHAI and consequential release of funds by the Principal Contractor/NHAI, to the petitioner. The petitioner alleges that midway through the work, the second respondent abandoned the same, which resulted in cost escalation, contractual breaches and safety incidents. Though the second respondent is the defaulter, it filed a claim petition invoking Section 18 of the Micro, Small, and Medium Industries Development Act, 2006 (hereinafter referred to as MSME Act). The claim petition was initially for a sum of Rs.3.34 crores and later, escalated to Rs.12,46,53,375.69/-. Along with the claim, interest under Section 16 of the MSME Act was also sought for. The claim of the second respondent was not supported by any tax invoices, completion certificate or other tangible evidences to justify the claim.

3. Summons was served on the petitioner by the first respondent. Between 28.12.2023 and 13.05.2025, the petitioner participated in the same. On coming to know about a clarification issued by the Union of India through its MSME Ministry, that ‘works contract’ is not covered under the National Industrial Classification (hereinafter referred to as 'NIC') codes for Udyam Registration, the petitioner raised an objection before the first respondent on 23.05.2025. It called upon the Council to examine and determine its jurisdiction before proceeding further in the matter.

4. The MSEF Council, by its impugned order dated 30.06.2025, held that there is no explicit exclusion of ‘work contract’ under the ambit of MSEF Council, and the clarification also does not assist the petitioner. The Council overruled the preliminary objection and adjourned the matter to 09.07.2025. Challenging the same, the present writ petition.

5. The contesting second respondent entered appearance and filed a counter. According to it, it is engaged in electrical contracts and other related works for over three decades. It is registered with the Government of Puducherry from 28.03.1999 onwards. It obtained ‘Udyam Registration’ on 21.09.2020 as required under MSME Act. It is a ‘small enterprise’ as defined under Section 2(m) of the said Act. 6. The second respondent accepted that it was appointed as a sub contractor as part of the project of four-laning of Jitttandahalli - Dharmapuri Section of NH-844. It pleads the writ petitioner had orally informed the second respondent about the scope of work and the nature of execution. In good faith, the second respondent had commenced the work even before the execution of the LOI. It accepted that the LOI was issued on 01.10.2021 and the MOU was signed on 23.02.2022. The second respondent denied the averment that it had abandoned the work. On the contrary, it submitted that it successfully completed the work and raised bills on v

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top