SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2010 Supreme(SC) 614

Supreme Court of India
THE HONOURABLE MR. JUSTICE R.V. RAVEENDRAN & THE HONOURABLE MR. JUSTICE J.M. PANCHAL
Afcons Infrastructure Ltd. & Another
Versus
Cherian Varkey Construction Co. (P) Ltd. & Others
CIVIL APPEAL NO.6000 OF 2010 (Arising out of SLP (C) No.760 of 2007)
Decided on : 26-07-2010

Advocates appeared:
For the Appellants:Krishnanan Venugopal, Senior Advocate, Anil K. Bhatnagar, Amit Dhingra, Manu Seshadri (for Dua Associates), Advocate. For the Respondents:T.L.V. Iyer, Senior Advocate, V.J. Francis, Anupam Mishra, C.N. Sree Kumar, P.R. Nayak, Dushyant Parashar, Advocates.

Headnote:Code of Civil Procedure, 1908 - Section 89 read with Order X, Rule 1-A - Reference to arbitration without consent of parties - Court has to formulate terms of possible settlement - Court has to give option to parties to choose any of ADR processes - There can be reference to arbitration only if there is an arbitration agreement between parties - If there is no agreement between parties for reference to arbitration, Court cannot refer matter to arbitration under Section 89 - When a matter is referred to conciliation, matter does not go out of stream of Court process permanently - If there is no settlement matter is returned to Court for framing issues and proceeding with trial. (Paras 15, 16, 23, 24, 24.4 and 25)

       (2003) 1 SCC 49; (2005) 6 SCC 344 - Relied upon.

       Arbitration and Conciliation Act, 1996 - Sections 30, 62 and 64 - Code of Civil Procedure, 1908 - Section 89 read with Order X, Rule 1-A - Award of Arbitrator is binding on parties and is executable as decree of Court - Arbitration is an adjudicatory process and it always ends in a decision. (Para 27)

       Interpretation of Statute - Where words of statute are clear, it should be given its plain and normal meaning, without adding or rejecting any words - Departure from literal rule of plain and straight reading can be only in exceptional cases. (Paras 13 to 13.5)

       AIR 1952 SC 324; 1971 (1) All ER 179; (1975) 4 SCC 298; 1978 (1) All ER 948-Relied upon.

Judgement Key Points

No specific provision or direction is made in the judgment regarding imposition of costs for non-participation in ADR processes under Section 89 or Order X Rules 1A to 1C. Parties referred to a conciliatory forum are required to appear before it, failing which the matter may be returned to the court upon failure of conciliation efforts. (!) (!) (!)


Judgment :-

R.V. RAVEENDRAN, J.

Leave granted. The general scope of Section 89 of the Code of Civil Procedure (`Code' for short) and the question whether the said section empowers the court to refer the parties to a suit to arbitration without the consent of both parties, arise for consideration in this appeal.

2. The second respondent (Cochin Port Trust) entrusted the work of construction ofcertain bridges and roads to the appellants under an agreement dated 20.4.2001. The appellants sub-contracted a part of the said work to the first respondent under an agreement dated 1.8.2001. It is not in dispute that the agreement between the appellants and the first respondent did not contain any provision for reference of the disputes to arbitration.

3. The first respondent filed a suit against the appellants for recovery of Rs.210,70,881 from the appellants and their assets and/or the amounts due to the appellants from the employer, with interest at 18% per annum. In the said suit an order of attachment was made on 15.9.2004 in regard to a sum of Rs.2.25 crores. Thereafter in March 2005, the first respondent filed an application under section 89 of the Code before the trial court praying that the court may formulate the terms of settlement and refer the matter to arbitration. The appellants filed a counter dated 24.10.2005 to the application submitting that they were not agreeable for referring the matter to arbitration or any of the other ADR processes under section 89 of the Code. In the meanwhile, the High Court of Kerala by order dated 8.9.2005, allowed the appeal filed by the appellants against the order of attachment and raised the attachment granted by the trial court subject to certain conditions. While doing so, the High Court also directed the trial court to consider and dispose of the application filed by the first respondent under section 89 of the Code.

4. The trial court heard the said application under section 89. It recorded the fact that first respondent (plaintiff) was agreeable for arbitration and appellants (defendants 1 and 2) were not agreeable for arbitration. The trial court allowed the said application under section 89 by a reasoned order dated 26.10.2005 and held that as the claim of the plaintiff in the suit related to a work contract, it was appropriate that the dispute should be settled by arbitration. It formulated sixteen issues and referred the matter to arbitration. The appellants filed a revision against the order of the trial court. The High Court by the impugned order dated 11.10.2006 dismissed the revision petition holding that the apparent tenor of section 89 of the Code permitted the court, in appropriate cases, to refer even unwilling parties to arbitration. The High Court also held that the concept of pre existing arbitration agreement which was necessary for reference to arbitration under the provisions of the Arbitration & Conciliation Act, 1996 (`AC Act' for short) was inapplicable to references under section 89 of the Code, having regard to the decision in Sukanya Holdings (P) Ltd. v. Jayesh H. Pandya & Anr. [2003 (5) SCC 531]. The said order is challenged in this appeal.

5. On the contentions urged, two questions arise for consideration :

(i) What is the procedure to be followed by a court in implementing section 89 and Order 10 Rule 1A of the Code?

(ii) Whether consent of all parties to the suit is necessary for reference to arbitration under section 89 of the Code?

6. To find answers to the said questions, we have to analyse the object, purpose, scope and tenor of the said provisions. The said provisions are extracted below :

"89. Settlement of disputes outside the court. - (1) Where it appears to the Court that there exist elements of a settlement which may be acceptable to the parties, the Court shall formulate the terms of settlement and give them to the parties for their observations and after receiving the observations of the parties, the Court may reformulate the terms of a possible




































































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top