2026 Supreme(Online)(NCLAT) 632
NATIONAL COMPANY LAW APPELLATE TRIBUNAL
Indevar Pandey, MT
M/S DHARAMPAL PREMCHAND LTD. – Appellant
Versus
Trimurti Foodtech Private Limited – Respondent
Company Appeal (AT) (Insolvency) No. 1872 of 2025
Advocates:
For the Appellants/Petitioners: Mr. Brajesh Kumar, Mr. Saurav Kumar
For the Respondents: Mr. Amir Arsiwala, Ms. Neha Arya
A disputed and contingent claim does not entitle an operational creditor to notice of Committee of Creditors meetings under Section 24(3)(c) of the IBC; an unchallenged classification of a claim as contingent during CIRP will bar its subsequent recall.
Headnote:(A) Insolvency and Bankruptcy Code, 2016 - Sections 24(3)(c), 31, and 61 - Corporate Insolvency Resolution Process - Mandatory notice of Committee of Creditors meetings to operational creditors - Scope of recall jurisdiction of Adjudicating Authority - Approval and finality of Resolution Plan.
(B) Constitutional Law of India - Article 300A - Deprivation of property - Leased assets in insolvency estate.
Facts of the case:
The Appellant, claiming to be an Operational Creditor, entered into a Contract Manufacturing and Packaging Agreement with the Corporate Debtor, and also provided equipment under a separate Equipment Lease Agreement. The Appellant terminated the agreement in 2017, but disputes regarding the validity of termination and substantial reciprocal claims existed. The Corporate Debtor was admitted into CIRP in 2021. The Appellant submitted a claim for approximately Rs. 6.81 Crores. The Resolution Professional (RP) informed the Appellant that the claim was under verification and not tallying with the books of account. The RP later issued a legal notice stating that the Appellant’s claim was admitted but would be treated as contingent due to a counterclaim of approximately Rs. 55.68 Crores from the Corporate Debtor. The Resolution Plan subsequently treated the Appellant’s claim as contingent with a 'NIL' admitted amount, which was approved by the Adjudicating Authority. The Appellant’s application to recall the approval was dismissed, leading to this appeal.
Findings of Court:
The court found that the Appellant’s claim was never finally admitted as an undisputed operational debt; it was always treated as contingent due to existing disputes and counterclaims. The court held that Section 24(3)(c) notice requirements presuppose that the claimant is recognized as an admitted Operational Creditor, which the Appellant was not. The court also found that the RP’s classification of the claim as contingent was justified given the reciprocal claims. The court noted the Appellant’s acquiescence by not challenging the classification during the CIRP. Allegations of fraud, collusion, and suppression of material facts were not substantiated. The court emphasized the importance of finality in the insolvency process, especially after a Resolution Plan has been implemented. The court distinguished the judgments cited by the Appellant as being factually different.
Issues: - Whether the Adjudicating Authority was justified in rejecting the recall application of the order approving the Resolution Plan. - Whether non-service of notice under Section 24(3)(c) of the Code vitiated the CIRP. - Whether the classification of the Appellant’s claim as “contingent” due to an unadjudicated counterclaim was illegal. - Whether the RP’s assumption of a continuing contract after its alleged termination was valid. - Whether there was any fraud, suppression, or material irregularity in the approval of the Resolution Plan.
Ratio Decidendi: An operational creditor whose claim is disputed, contingent, and not finally admitted is not entitled to notice of CoC meetings under Section 24(3)(c). The Resolution Professional’s role in classifying claims during CIRP does not require final adjudication of contractual disputes; the existence of serious reciprocal disputes justifies treating a claim as contingent. A successfully implemented Resolution Plan cannot be lightly reopened, especially when the claimant failed to challenge the treatment of its claim during the CIRP process. (Paras 53, 59, 62, 63, 72, 73) Result : Appeal dismissed. (Para 76)
(C) Arbitration and Conciliation Act, 1996 - Section 11 - Invocation of arbitration clause during CIRP does not invalidate the resolution process. (Paras 38, 41)
(D) Contract law - Termination and renewal of contract - In absence of a fresh document, a contract does not automatically renew; however, an RP can consider the contractual clauses and conduct of parties for claim verification without finally adjudicating the contract's status. (Paras 53, 61, 68) (E) Analysis of Judgments - Judgments regarding crystallization of damages claims (e.g., CSA Corporation, Associate Builders) and automatic renewal of leases (e.g., Hardesh Ores) were distinguished as not directly applicable to the claim verification process under the IBC. (Paras 67-71) (F) Practice and Procedure - The jurisdiction of the appellate tribunal under Section 61 of the IBC is limited; interference with an approved Resolution Plan requires a showing of patent illegality, material irregularity, or violation of mandatory provisions. (Para 50) (G) Evidence - Acquiescence and delay - A party who is aware of the classification of its claim during the CIRP and does not challenge it until after plan approval is deemed to have acquiesced. (Paras 33, 42, 43, 58)
| Table of Content |
|---|
| 1. what is the primary legal principle discussed in these paragraphs? (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55 , 56 , 57 , 58 , 59 , 60 , 61 , 62 , 63 , 64 , 65 , 66 , 67 , 68 , 69 , 70 , 72 , 73 , 74 , 75) |
J U D G M E N T
(25th May, 2026)
INDEVAR PANDEY, MEMBER (T)
1.The present Appeal has arisen from the order dated 16.09.2025 passed by the National Company Law Tribunal, Mumbai Bench-V (Adjudicating Authority) in I.A. No. 4588 of 2024 in CP (IB) No. 1139 of 2020, whereby the application filed by the Appellant, M/s Dharampal Premchand Ltd. (Claiming to be an Operational Creditor), seeking recall of an earlier order passed by Adjudicating Authority in IA No. 1916 of 2022 dated 31.03.2023, whereby it approved the Resolution Plan of Corporate Debtor-Trimurti Foodtech Ltd., who is Respondent No.3 herein, was dismissed.
2. The Appeal has been preferred against the said impugned order primarily on the ground that despite the operational debt claim of the Appellant being admittedly above the statutory threshold prescribed under Section 24(3)(c) of the Insolvency and Bankruptcy Code, 2016,(hereinafter referred to as ‘Code’), the Resolution Professional of the Corporate Debtor Mr. Manoj Kumar Mishra/ Respondent No.2, allegedly failed to issue notice of the Committee of Creditors meetings to the Appellant during the Corporate Insolvency Resolution Process. The Appellant has further alleged that although it had filed their claim in Form B during the CIRP, the same was subsequently treated as a “contingent claim” on the basis of an alleged counterclaim raised by Respondent No.2/RP, resulting in complete denial of any payment to the Appellant under the Resolution Plan submitted by the Successful Resolution Applicant-Mr. Jitendra Bhandari/ Respondent No.1. The Appellant has also challenged the CIRP process on the ground that machinery and equipment belonging to the Appellant and merely leased to Respondent No.3/Corporate Debtor were unlawfully treated as assets of the Corporate Debtor during the insolvency proceedings, apart from alleging various procedural irregularities and arbitrary exercise of jurisdiction during the resolution process. FACTS OF THE CASE
3. The facts relevant for deciding this matter are as given below:
(i) The Appellant, namely M/s Dharampal Premchand Ltd. (Claiming to be an Operational Creditor), is stated to be a well-established company operating in the FMCG sector for several decades and having diversified into manufacturing and marketing of fruit pulp-based jelly products and fruit bars. In connection with its business operations, the Appellant entered into commercial arrangements with Respondent No.3/Corporate Debtor namely Trimurti Foodtech Ltd. for manufacturing and packaging of fruit bars.
(ii) A fresh “Contract Manufacturing and Packaging Agreement” was executed between the Appellant and the Corporate Debtor on 20.08.2014, superseding an earlier agreement dated 28.11.2013. Under the said arrangement, the Corporate Debtor undertook manufacturing and packaging activities for the Appellant’s products. In furtherance of the arrangement, the Appellant extended substantial financial support to the Corporate Debtor in the form of mobilisation advance, security deposit, and advance towards procurement of raw material and packaging material. The total financial assistance extended under the arrangement was stated to be approximately Rs.6.25 Crores.
(iii) Simultaneously, assurances were allegedly extended by the Corporate Debtor regarding enhancement of manufacturing capacity and procurement of additional machinery for its Waluj Plant. Acting upon such assurances, the Appellant purchased necessary equipment and machinery worth approximately Rs.3.60 Crores and provided the same to the Co
Click Here to Read the rest of this document