2026 Supreme(Online)(Tel) 20893

HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
J. Sreenivas Rao, J
Prof.M.Haragopal Rao – Appellant
Versus
Sri Burra Venkatesham IAS. – Respondent
CONTEMPT CASE No.2527 of 2024



Advocates:
For the Appellants/Petitioners: M. Hara Gopal
For the Respondents: S. Satyanarayana Rao

Contempt jurisdiction is limited to determining deliberate disobedience of a court order; it cannot be used to adjudicate disputes regarding the quantum of monetary benefits or interpret entitlements not specifically detailed in the original order.

Headnote:The petitioner invoked Sections 10 to 12 of the Contempt of Courts Act, 1971, alleging willful disobedience of a court order dated 03.04.2024 which directed the respondents to treat the period from 30.07.2001 to 04.07.2002 as 'Compulsory Wait' and extend service benefits. While the respondents implemented the order and paid a portion of the arrears, the petitioner contended that the calculated amount was significantly lower than his entitlement. The court framed the issue around whether the discrepancy in the calculation of monetary benefits could be adjudicated within contempt proceedings. The court reasoned that the scope of contempt jurisdiction is limited to determining whether there has been deliberate disobedience of a court order and not to function as an original or appellate court to resolve disputes over the quantum of benefits, quoting that the court is "not entitled to enter into questions which have not been dealt with and decided in the judgment or order." For the foregoing reasons, this contempt case is closed.

Table of Content
1. allegation of contempt due to discrepancy in calculation of service benefits following a court order. (Para 1 , 2 , 3 , 4 , 5)
2. verification of implementation of court order through audit reports and pay fixation. (Para 6 , 7 , 8 , 9 , 10 , 11 , 12)
3. limited scope of contempt jurisdiction regarding the adjudication of monetary disputes. (Para 13 , 14 , 15)
4. closure of contempt proceedings with direction for final payment of determined amount. (Para 16)

ORDER:

This contempt case has been filed seeking to punish the respondents/contemnors for willfully disobeying the order dated 03.04.2024 passed by this Court in Review I.A.No.2 of 2023 in W.P. (TR) No.1450 of 2017, by invoking the provisions of Sections 10 to 12 of the Contempt of Courts Act, 1971.

2. Mr. M. Hara Gopal, who is the petitioner in the contempt case, appeared as a party-in-person. Though he has engaged counsel, he requested this Court to permit him to argue the case on his own.

3. Heard the petitioner/party-in-person, and Mr. S. Satyanarayana Rao, learned Government Pleader for Services-I appearing for the respondents/contemnors.

4. Submissions of learned petitioner/party-in-person:

4.1. Learned petitioner/party-in-person submitted that this Court while disposing of Review I.A.No.2 of 2023 on 03.04.2024 directed the respondents/contemnors to treat the period from 30.07.2001 to 04.07.2002 as compulsory wait and extend the service benefits in his favour by giving time limit. However, the respondents have wrongly calculated the amount at only Rs.65,262/-, whereas, he is entitled to an amount of Rs.7,27,372/-. The respondents are intentionally disobeying the orders passed by this Court in Review I.A.No.2 of 2023 and, therefore, they are liable to be punished under the provisions of the Contempt of Courts Act, 1971.

5. Submissions of learned Government Pleader:

5.1. Learned Government Pleader submitted that pursuant to the orders passed by this Court, the Government has issued Memo No.5657/IE/A1/2019, dated 19.06.2025, which was communicated vide the Director’s Proc.Rc.No.CIESER1/PCH1/1/ 2024-SER1, dated 25.06.2025. Thereafter, the necessary pay fixation was carried out vide the Director’s Proc.Rc.No.CIE- SER1/PCH1/1/2024-SER1, dated 30.06.2025.

5.2. Pursuant to the said proceedings, the Account Section of the Office of the Director of Intermediate Education, Telangana, Hyderabad, paid the arrears amounting to Rs.1,70,441/- on 05.08.2025. However, the petitioner submitted a statement claiming that the respondents were liable to pay the arrears of Rs.7,27,372/-. Basing on the said statement, respondent No.2, through proceedings dated 02.02.2026, deputed one B. Narsimha Rao, Senior Audit Officer (Retired), who is presently attending to the audit work in the office, to verify the petitioner’s claim for arrears, including eligibility, amounts already drawn and amounts claimed, and to submit a report.

5.3. Pursuant to the said proceedings, the Senior Audit Officer (Retired) submitted a report dated 17.03.2026 stating that the petitioner had claimed House Rent Allowance (HRA) at the rate of 20%, which is applicable to the Hyderabad District, and that his claim for payment of HRA at 20% applicable to Hyderabad for the period from 30.07.2001 to 04.07.2002, during which he was treated as being on ‘Compulsory Wait’, had been accepted. The report further states that the petitioner had earlier been sanctioned Half Pay Leave for the period from 30.07.2001 to 22.02.2002 and that payment for the said period had already been made by the Principal, Government Junior College, Bichkund, Nizamabad District. However, the petitioner claimed arrears for the said period without taking into account the fact that he had already drawn half salary for the very same period. Therefore, it was found appropriate to deduct the amounts already paid to him. The report of the Senior Audit Officer (Retired) further states that the petition

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top