2025 MarsdenLR 2184

HIGH COURT MALAYA KUALA LUMPUR
PUREGEN TECHNOLOGY SDN BHD – Appellant
Versus
MILLENNIUM ECO TECHNO SDN BHD – Respondent


Petitioner Advocates:Tan Wei Wei,Aaron Lee,Ngo Chi Ern ,Respondent Advocate: Pee Kui Yee,Lee Xue Er

Ahmad Shahrir Mohd Salleh J:

Introduction

[1] This appeal was filed by the defendant against the decision of the Sessions Court which allowed the plaintiff's claim for unpaid invoices in the sum of RM394,232.38 with costs.

[2] The plaintiff had also filed a cross-appeal challenging the decision of the Sessions Court. The cross-appeal was directed against the Sessions Court's decision to award statutory interest instead of the contractual interest of 1.5% per month as expressly stipulated in the invoices.

[3] After carefully perusing the record of appeal and considering the submissions of both parties, I found no cogent reasons to interfere with the findings of the learned Sessions Court Judge. The defendant's appeal and the plaintiff's cross-appeal were accordingly dismissed. Costs of RM10,000.00 were awarded in respect of dismissal of the appeal while costs of RM5,000.00 were awarded in respect of dismissal of the cross-appeal.

Brief Background Facts

[4] The defendant had engaged the plaintiff as its subcontractor through a Letter of Award dated 19 May 2017 ("Letter of Award"). The scope of work under the subcontract required the plaintiff to design, supply, install, test and commission

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top