HIGH COURT MALAYA SHAH ALAM
LA LEISURE PTY LTD – Appellant
Versus
SABRECRAFT MARINE SDN BHD & ORS – Respondent
[Suit No: BA-22NCC-123-10/2021]
Key Points: - (!) Time was set at large; reasonable completion period could not be determined. - (!) The 1st Defendant’s counterclaim for variation works or storage charges was not proven. - (!) There was a breach by the 1st Defendant in failing to deliver the Vessel; set-off defense rejected. - (!) The 3rd Defendant liable jointly and severally as guarantor under clause 16. - (!) Plaintiff failed to prove loss of profits and no total failure of consideration; but recoverable wasted expenditure of AUD 523,558.56 against 1st and 3rd Defendants. - (!) Sale of the Vessel and conversion were breaches by the 1st Defendant. - (!) Plaintiff entitled to the wasted expenditure damages; judgment in favor of Plaintiff against 1st and 3rd Defendants.
JUDGMENT
Introduction
[1] On 1 March 2017, after a period of pre-contractual negotiations, the Plaintiff and the 1st Defendant entered into an agreement for the construction of a new vessel ("Agreement"). The subject vessel was identified as "Build Number: 002, Hull Identification No AU-SBR 125120617" ("Vessel").
[2] The Agreement contained the terms governing the relationship between the parties. The parties included the 3rd Defendant who signed on behalf of the 1st Defendant and also in his personal capacity as a guarantor for the 1st Defendant's performance. The 3rd Defendant is a director of the 1st Defendant.
[3] The Plaintiff sued the Defendants in this action for various relief because the 1st Defendant failed to deliver the Vessel that the Plaintiff had contracted for and paid the 1st Defendant to build. The 1st Defendant had allegedly sold the partially built Vessel to the 2nd Defendant.
[4] The 1st Defendant counterclaimed for outstanding payments and storage charges. According to the 1st Defendant, the delays in construction were caused by the Plaintiff and that the partially built Vessel was sold to mitigate losses.
[5] The cause of action discernible from the pleaded case of both parties appear to be breach of contract. The Plaintiff additionally pleaded money had and received in relation to the proceeds of the sale of the Vessel and conversion of the Vessel.
[6] During post-trial submissions on 4 December 2024, counsel for the Plaintiff informed the Court that the Plaintiff would not be pursuing prayers (1) to (6) of the claim, essentially those prayers for specific relief relating to specific performance of the Agreement and the taking of possession of the Vessel.
Issues For Determination
[7] Based on the pleadings of the parties and the aforesaid abandonment of relief by the Plaintiff, the following are the issues for determination:
(1) What is the legal consequence of the pleaded delay events in the construction of the Vessel?
(2) Whether the 1st Defendant was entitled to stop construction and/or claim storage charges.
(3) Whether the Plaintiff had fully paid for the Vessel including variation works and whether there was total failure of consideration.
(4) Whether the 1st Defendant was entitled to sell the Vessel and/or whether the 1st Defendant committed conversion.
(5) Whether the 3rd Defendant is personally liable as a guarantor under the Agreement.
(6) Whether the Plaintiff is entitled to the liquidated quantum of damages sought from the 1st and 3rd Defendants.
Interpretation Of Foreign Law Contract
[8] Before I deal with the issues, it is noted that the parties made an express choice of law in the Agreement ie Australian law. Thus Australian law is the proper law applicable to interpret the Agreement and the performance of obligations arising from it.
[9] As neither party pleaded or proved the application of any Australian law in this case, there is a presumption that the applicable Australian law is identical to Malaysian law. See European Profiles Ltd v. Sentinel Steel (Malaysia) Sdn Bhd; [1993] 4 CLJ 577; [1993] 2 AMR 3144.
Analysis And Findings
Delays In Construction
What Is The Legal Consequence Of The Pleaded Delay Events In The Construction Of The Vessel?
[10] It is not disputed that according to cl 5.1 of the Agreement, it was contemplated that construction of the Vessel would be completed within 14 weeks from the date of receipt of the first instalment payment comprising 40% of the total consideration of AUD438,000.00. The sum AUD175,200.00 was paid on 2 March 2017 and thus the original delivery date was on 8 June 2017 ("Delivery Date").
[11] The pleaded delay events are:
(a) Copyright issues with the design provided by the Plaintiff
(b) Changes in specifications (windshield, deck layout and other changes raised in a 17 July 2017 email)
(c) Delay in confirming which drive to use on the Vessel
(d) Delay in lodging paperwork with Australian Maritime Safety Authority ("AMSA")
The burden of proving tha
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.