HIGH COURT MALAYA SHAH ALAM
KEMAS MAJU CONSTRUCTION SDN BHD – Appellant
Versus
MASTER CRAFT GROUP SDN BHD & OTHER CASE – Respondent
[Originating Summons No: BA-24C-54-12/2024 BA-24C-56-12/2024 & BA-24C-1-01/2025]



Petitioner Advocates:Phang Ting Hong,Tan Wei Sheng ,Respondent Advocate: Lim Zi-Han,Sean Ferdinand Ng

Adjudication decisions under CIPAA 2012 are subject to limited review; allegations of procedural unfairness must be substantiated, and courts cannot reassess the merits of the adjudicator's findings.

Headnote:(A) Construction Industry Payment and Adjudication Act 2012 - Sections 15, 16, and 28 - Adjudication decision favoring claimant for unpaid sum of RM1,389,572.92 - Respondent's applications to set aside and stay execution of the adjudication decision dismissed; enforcement application allowed. (Paras 11, 13, 75)

(B) Natural Justice - Denial of natural justice claims must be substantiated; procedural fairness must be accorded during adjudication proceedings. (Paras 34, 46)

(C) Jurisdiction - Adjudicator's decisions are subject to limited grounds for review; court cannot assess merits of the adjudicator's findings. (Paras 47, 62)

Facts of the case:
Master Craft Group Sdn Bhd initiated adjudication proceedings against Kemas Maju Sdn Bhd for unpaid construction work, resulting in an adjudication decision awarding RM1,389,572.92. Kemas Maju filed applications to set aside and stay the adjudication decision, claiming denial of natural justice and lack of jurisdiction.

Findings of Court:
The court dismissed Kemas Maju's applications, finding no evidence of procedural unfairness or lack of jurisdiction by the adjudicator. Enforcement of the adjudication decision was allowed as all conditions were met.

Issues: The court addressed whether Kemas Maju's claims of denial of natural justice and jurisdictional excess were valid.

Ratio Decidendi: The court held that allegations of procedural unfairness must be substantiated and that the adjudicator's findings cannot be reviewed on their merits. Kemas Maju failed to demonstrate any substantial grounds for setting aside the adjudication decision.

Result: Applications to set aside and stay execution dismissed; enforcement application allowed.

Table of Content
1. commencement of adjudication proceedings (Para 1 , 2 , 3)
2. details of subcontract and payment claims (Para 4 , 5 , 6)
3. adjudicator's decision and claims (Para 9 , 10 , 11)
4. parties' dissatisfaction and appeal (Para 12 , 13 , 14)
5. purpose of cipaa 2012 (Para 15)
6. preliminary objections raised by kemas maju (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25)
7. kemas maju's grounds for setting aside and stay (Para 29 , 30)
8. court's analysis on natural justice (Para 32 , 33 , 34)
9. independence and impartiality of the adjudicator (Para 50 , 51 , 52)
10. jurisdictional challenges against the adjudicator (Para 54 , 55 , 56)
11. application for stay of execution (Para 68 , 69 , 70)
12. conditions for enforcement of adjudication decision (Para 75 , 76)
13. conclusion and order of the court (Para 77)
Sumathi Murugiah JC:

A. Introduction

[1] On August 2024, Master Craft Group Sdn Bhd (Master Craft) had commenced an Adjudication Proceedings pursuant to the Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012) against Kemas Maju Sdn Bhd (Kemas Maju) to claim a sum of RM1,389,572.92 as the unpaid sum. The Adjudicator, Mr Wilfred Abraham, decided in favour of the Master Craft in his Adjudication Decision dated 7 November 2024 (AD).

[2] As a result of the AD, the followings were filed by the parties:

(i). OS No BA-24C-1-01/2025 (Suit 1) was filed by Master Craft to enforce the AD pursuant to s 28 of CIPAA 2012;

(ii). OS No BA-24C-54-12/2024 (Suit 54) was filed by Kemas Maju to set aside the AD pursuant to s 15 of CIPAA 2012;and

(iii). OS No BA-24C-56-12/2024 (Suit 56) was filed by Kemas Maju for Stay of Execution of the AD pursuant to s 16 of CIPAA 2012.

[3] Since there are 3 OS filed in relation to this AD, the parties agreed to having all the 3 OS heard together and for the decision to be delivered together. Since this is a cross suit between the parties, for ease of reference the parties will be referred to henceforth as Master Craft and Kemas Maju wherever applicable.

B. Brief Background

[4] By way of a Letter of Award dated 25 April 2023 (LOA), Master Craft was appointed by Kemas Maju as the sub-contractor for the building works (Project). The Project concerns the construction of houses in Kedah where Kemas Maju is the main contractor. Master Craft was subآ¬contracted by Kemas Maju to the works as follows:

i. The external works - constructing and installing the perimeter fencing;

ii. Clearing up works; and

iii. Related finishings works of the houses.

[5] Due to a non-payment for the works done by Master Craft, a Payment Claim dated 1 July 2024 was issued to Kemas Maju by Master Craft pursuant to the Construction Industry Payment and Adjudication Act 2012 (CIPAA 2012). Kemas Maju responded with its Payment Response dated 11 July 2024.

[6] Subsequently, Master Craft had commenced Adjudication Proceedings via a Notice of Adjudication dated 7 August 2024. served on Kemas Maju on 12 August 2024. BMG on the other hand had not responded to the payment claim by any Payment Response to Juang.

[7] As the parties failed to agree on an adjudicator, the AIAC Director appointed Wilfred Abraham on 2 September 2024 as the Adjudicator. Following Master Craft's solicitors' letter on 13 September 2024 confirming the terms, he formally accepted the appointment via Form 6 on the same date.

C. Adjudication Proceedings

[8] An Adjudication Claim together with supporting documents were emailed on 29 September 2024 to Kemas Maju. Kemas Maju in turn had emailed its Adjudication Response to Master Craft on 10 October 2024. Master Craft emailed its Adjudication Reply on 17 October 2024.

[9] Via both the Payment Claim and the Adjudication Claim, Master Craft's claim against Kemas Maju for the balance of payment owed for works done is for the sum of RM1,389,572.92.

[10] Kemas Maju on the other hand via its Payment Response and Adjudication Response admitted a sum of RM501.096.16 only as being owed to Master Craft upon setting off the Debit Note

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top