SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 2344

HIGH COURT MALAYA KUALA LUMPUR
KONSESI KOTA PERMATAMAS SDN BHD – Appellant
Versus
TEGAS BROADCAST & MULTIMEDIA SDN BHD & ANOR – Respondent
[Civil Appeal No: WA-12BNCC-18-07/2024]



Petitioner Advocates:Jasvinjit Singh Gurcharan Singh ,Respondent Advocate: Roeshan Celestine Gomez,Jenny Ng Juen Yee

A developer is not liable to pay unpaid suppliers directly under Section 71 of the Contracts Act 1950 without a privity of contract, as it would result in unjust enrichment.

Headnote:(A) Contracts Act 1950 - Section 71 - Unjust enrichment - Developer's obligation to pay unpaid suppliers - The court examined whether a developer is liable to pay suppliers directly when the main contractor fails to do so. The Appellant contended no privity of contract existed, and thus Section 71 and unjust enrichment principles did not apply. The court found that the 1st Respondent had performed its obligations under the contract, but the Appellant was not liable due to the absence of a direct contractual relationship. (Paras 1, 9, 19, 20, 45)

(B) Privity of Contract - The court reiterated that a subcontractor cannot claim against the employer in the absence of a direct contract. The 1st Respondent's claim against the Appellant was denied as it would result in unjust enrichment and double payment. (Paras 18, 19, 20, 43)

(C) Retention of Title Clause - The court ruled that the absence of a valid retention of title clause in the contract between the 1st Respondent and the 2nd Respondent precluded the 1st Respondent from claiming payment from the Appellant. (Paras 34, 36)

(D) Acknowledgment of Debt - The court found that discussions regarding future contracts did not constitute an acknowledgment of the Outstanding Sum owed to the 1st Respondent. (Paras 41, 42)

Facts of the case:
The 1st Respondent supplied equipment for a project contracted by the Appellant, who failed to pay the Outstanding Sum of RM 814,014.31 after the main contractor defaulted. The 1st Respondent sought recovery under Section 71 and unjust enrichment principles.

Findings of Court:
The court ruled that the Appellant was not liable to pay the 1st Respondent due to the lack of privity of contract and the risk of double payment.

Issues: The main issues included whether the Appellant was liable to pay the 1st Respondent despite the absence of a direct contract and the applicability of Section 71 of the Contracts Act 1950.

Ratio Decidendi: The court held that Section 71 does not apply without a direct contractual relationship, and allowing the claim would result in unjust enrichment for the 1st Respondent.

Result: Appeal allowed with costs.

JUDGMENT

Ong Chee Kwan J:

Introduction

[1] This judgment deals yet again with the question whether a developer who is the ultimate beneficiary of all goods supplied by various suppliers for its property development, is obliged to pay the unpaid suppliers down the chain in the event that the developer's main contractor and or sub-contractors with whom the suppliers had contracted failed to make payments for the goods so supplied. Can the suppliers rely on s 71 of the Contract Act 1950 and or the cause of action for unjust enrichment to recover the outstanding sums due directly from the developer?

[2] In this case, the 1st Respondent had successfully claimed after a full trial against the Appellant the sum of RM 814,014.31 being the remaining outstanding sums with interest for special equipment and the related works done under a contract between the 1st Respondent and the 2nd Respondent (who was unrepresented at the trial) which had remained unpaid.

[3] The Appellant contended that it was not obliged to pay the 1st Respondent as there was no privity of contract between them. It was also contended that s 71 of the Contracts Act 1950 and or the principles of unjust enrichment simply did not apply to the facts of this case.

Background Facts

[4] The 1st Respondent was a company specialising in the supply and installation of professional audio-visual equipment and technical services.

[5] The Appellant was the concessionaire under a Concession Agreement dated 21 February 2013 with the Government of Malaysia and Universiti Teknologi MARA ("UiTM") to design, construct, and maintain the new UiTM campus in Rembau, Negeri Sembilan ("the Project").

[6] The Appellant had appointed Tech Art Sdn Bhd ("Tech Art") as the main contractor for the supply of special equipment for the Project. Tech Art subcontracted part of the works to the 2nd Respondent who then engaged the 1st Respondent via a Letter of Award dated 4 November 2015 and a Contract for Supply, Installation and Commissioning Special Equipment at Faculty of Communication and Media Studies New Campus UITM Rembau, Negeri Sembilan Darul Khusus. ("Agreement").

[7] For the purpose of this appeal, this Court had proceeded on the assumption that the 1st Respondent had duly performed its contractual obligations by supplying and installing the equipment and providing the requisite services, including Testing & Commissioning ("T&C"), training for UiTM staff, and submission of necessary documentation such as manuals, warranty cards, and as- built drawings under its Agreement with the 2nd Respondent.

[8] Partial payments amounting to RM7,937,297.91 had been made leaving an outstanding sum of RM814,014.31 remaining unpaid ("the Outstanding Sum") as detailed in the Invoices ("the Invoices") issued to the 2nd Respondent. Despite made numerous requests for payment from the 1st Respondent which were acknowledged, the 2nd Respondent failed to make the payment of the Outstanding Sum.

[9] At the Session Court , the 2nd Respondent claimed against the Appellant and the 2nd Respondent for the Outstanding Sum. Judgment was granted against the Appellant based on the cause of action for unjust enrichment and under s 71 of the Contracts Act 1950 . Unsurprisingly, the Appellant appealed against the decision. The 2nd Respondent did not appeal.

[10] The learned Session Court Judge had relied on the judgment of the Court of Appeal in Kraas Solutions Sdn Bhd v. Konsesi Kota Permatamas Sdn Bhd; [2018] 6 MLJ 202; [2018] 9 CLJ 26; [2018] 3 AMR 790 ("Kraas Solutions') in coming to her decision. The facts in Kraas Solutions are materially identical to the present appeal. The Appellant's counsel admitted the same during the hearing. Both cases involved the Project and same parties (ie, the Government of Malaysia/University Technology Mara (UiTM) being the developer, the concessionaire being the Appellant and the main contractor, Tech Art).

[11] The Court of Appeal in Kraas Solutions (supra) held that all conditions under s 7


Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top