2019 MarsdenLR 2355

HIGH COURT MALAYA KUALA LUMPUR
RANJAN PARAMALINGAM & ANOR – Appellant
Versus
BANGSAR PARK RESIDENTS ASSOCIATION – Respondent
[Civil Suit No: WA-22NCVC-152-03/2017]



Important Points

Claims involving both public and private law elements require careful procedural consideration, focusing on the predominant nature of the claims.

Subject

Civil Law - Nuisance

Act Referred

Headnote

In a case regarding the establishment of a gated and guarded scheme in Bangsar Park, the Defendant sought to strike out the Plaintiffs' claim based on the premise that it predominantly involved public law elements and that judicial review should have been the appropriate recourse. The Court, after reviewing the pleadings and submissions, found that there were significant private law elements and material facts in dispute, leading to the dismissal of the Defendant's application. The Court determined that full trial was necessary. Key legal principles were invoked under Order 14A and Order 33, Rule 2 of the Rules of Court 2012 regarding the appropriate procedural recourse for such claims.

Petitioner Advocates:Dato Bastian Pius Vendargon,Anne Vendargon ,Respondent Advocate: Fahri Azzat,Ameerul Aizat

Table of Content
1. the dispute centers on the legality of a gated community imposed by the defendant. (Para 1 , 3)
2. essence of dispute over gated community legality. (Para 2)
3. defendant argues for judicial review citing public law elemental claims by plaintiffs. (Para 4 , 5)
4. court discusses procedural appropriateness for the claims and addresses disputed facts. (Para 6)
Aliza Sulaiman JC:

Introduction

[1] The 1st Plaintiff is an advocate and solicitor who is currently a partner of Messrs. P S Ranjan & Co On 13 March 2015, the 1st Plaintiff became the registered proprietor of the house at No 79, Jalan Limau Manis, Bangsar Park, 59000 Kuala Lumpur (said Property). The 2nd Plaintiff has been a tenant of the said Property even before the 1st Plaintiff became the registered proprietor of the same.

[2] The Defendant is a society registered under the Societies Act 1966 [Act 335] where some residents of Bangsar Park are its members.

[3] The essence of the dispute between the parties is over the establishment of a gated and guarded scheme (GGS) in an area within a part of Bangsar Park which the Plaintiffs claim is in breach of the law.

[4] By a Notice of Application (NoA) pursuant to O 14A and O 33, r 2 of the Rules of 2012 (ROC 2012) filed on 27 September 2018 (Enclosure 74), the Defendant moves this Court to determine the following issues of law before the trial:

(a) Whether the Plaintiffs claim against the Defendant is based solely on substantive principles of public law or has a predominant and substantial public law element?

(b) Whether the Plaintiffs should have commenced an action by way of judicial review against the Kuala Lumpur City Council (DBKL) about its complaint instead of filing an action against the Defendant?

If both the above questions are answered in the affirmative, the Defendant seeks an Order that the Plaintiffs claim be struck out with costs for being an abuse of Court process.

[5] The grounds for the application as stated in the NoA are that-

(a) the questions of law raised deal with threshold issues regarding the Plaintiffs claim that ought to be decided before preparations are made for the full trial of claim so that time, costs and effort is saved if the threshold issues do not favour the Plaintiffs;

(b) the facts upon which the questions of law are based are substantially agreed upon;

(c) the question in subparagraph 4(a) above will clarify the nature of the Plaintiffs claim against the Defendant and enable this Court to determine whether the Plaintiffs have used the appropriate originating process based on the case of Ahmad Jefri Mohd Jahri v. Pengarah Kebudayaan & Keseniaan Johor & Ors, ;

(d) the question in subparagraph 4(b) above intends to determine whether the Plaintiffs have used the correct procedure in making their claim; and

(e) if these preliminary issues are decided in favour of the Defendant, it would conclude the entire proceedings and it would be unnecessary to try other issues.

[6] Having considered oral submissions by learned counsels representing the parties, the NoA, Affidavits, written submissions and four letters submitted after the hearing date (ie three letters dated 9 January 2019, 10 January 2019 and 11 January 2019 from the Plaintiffs counsel and one letter dated 11 January 2019 from the Defendants counsel regarding the additional document titled 11 Timeline Proving That There Was No Approval From DBKL For A Period Of Twelve (12) Months"), I dismissed the Defendants application with costs of RM5,000.00 to the Plaintiffs subject to allocatur.