SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 MarsdenLR 539

HIGH COURT MALAYA SHAH ALAM
OTIS ELEVATOR COMPANY (M) SDN BHD – Appellant
Versus
DESARU CONVENTION CENTRE SDN BHD & OTHER CASES – Respondent
[Originating Summons No: BA-24C-29-04/2022 BA-24C-30-04/2022 & BA-24C-31-04/2022]



Petitioner Advocates:Deepak Mahadevan,Moganasundari Mahalingam,Loon Ann Ni ,Respondent Advocate: Rajendra Navaratnam,Raja Kumar Raja Kandan,Koh Yi Ting,Ng Chu Yin

An Employer cannot rely on a Dispute Resolution Agreement to oppose a Sub-Contractor's Section 30 Application under CIPAA.

Headnote:This judgment revolves around three originating summonses regarding adjudication proceedings initiated by the plaintiff against three defendants for unpaid construction works, evaluated under the Construction Industry Payment and Adjudication Act 2012 (CIPAA). The court clarifies that an Employer cannot utilize a Dispute Resolution Agreement with a Main Contractor to contest a Sub-Contractor's right to enforce an adjudication decision. The court ultimately allows the originating summonses with costs, affirming the legal rights of the plaintiff to recover the adjudicated amounts.

Table of Content
1. employer cannot use dispute resolution agreement against sub-contractor. (Para 5)
Wong Kian Kheong J:

A. Introduction

[1] This judgment concerns the following three originating summonses (3 OS):

(1) OS No BA-24C-29-04/2022 (1st OS) has been filed by the plaintiff company (plaintiff) against Desaru Convention Centre Sdn Bhd [defendant (1st OS)];

(2) the plaintiff has instituted OS No BA-24C-30-04/2022 (2nd OS) against Desaru Estate Sdn Bhd [defendant (2nd OS)]; and

(3) OS No BA-24C-29-04/2022 (3rd OS) has been commenced by the plaintiff against Desaru Corniche Hotel Sdn Bhd [Defendant (3rd OS)].

B. Background

B(1). 1st OS

[2] The defendant (1st OS) had appointed Malaysian Resources Corporation Bhd (MRCB) as the main contractor for the construction of "Desaru Convention Centre" [Project (1st OS)].

[3] By way of a "Letter of Acceptance" (LA) dated 26 October 2015, MRCB appointed the plaintiff to perform certain construction work in the Project (1st OS) [Works (1st OS)].

[4] The plaintiff had performed the Works (1st OS) but had not been paid by MRCB for the Works (1st OS) [Unpaid Works (1st OS)]. Hence, the plaintiff claimed from MRCB for the Unpaid Works (1st OS) under the Construction Industry Payment and Adjudication Act 2012 (CIPAA). I shall refer to the adjudication proceedings commenced by the plaintiff against MRCB regarding the Unpaid Works (1st OS) as "Adjudication Proceedings (1st OS)".

[5] In The Adjudication Proceedings (1st OS):

(1) on 14 December 2021, the adjudicator, Mr Wong Kee Them [Adjudicator (1st OS)], had adjudicated [Adjudication Decision (1st OS)] that, among others, MRCB shall pay to the plaintiff a sum of RM334,998.21 [Adjudicated Amount (1st OS)] with interest and costs as stipulated in the Adjudication Decision (1st OS); and

(2) upon an application by the plaintiff's solicitors, due to a typographical error by the Adjudicator (1st OS), on 11 April 2022, the Adjudicated Amount (1st OS) was amended by the Adjudicator (1st OS) to RM334,988.21 [Amended Adjudicated Amount (1st OS)].

[6] The plaintiff's solicitors had sent a demand dated 21 December 2021 [Plaintiff's Demand-MRCB (1st OS, 21 December 2021)] to MRCB's representative in the Adjudication Proceedings (1st OS), Contract Solutions-I (CS), for MRCB to pay the Adjudicated Amount (1st OS) with interest and costs as stated in the Adjudication Decision (1st OS).

[7] MRCB's solicitors, Messrs Selva Mookiah Associates, replied to the Plaintiff's Demand-MRCB (1st OS, 21 December 2021) in a letter dated 19 January 2022 [MRCB's Letter (1st OS, 19 January 2022)]. According to MRCB's Letter (1st OS, 19 January 2022), among others:

(1) the Defendant (1st OS) owed money to MRCB under the main contract between the Defendant (1st OS) and MRCB with regard to the Project (1st OS) {Main Contract [Defendant (1st OS)-MRCB]}; and

(2) MRCB could not pay the Adjudicated Amount (1st OS) to the Plaintiff because MRCB had not received payment from the Defendant (1st OS) pursuant to the Main Contract [Defendant (1st OS)-MRCB].

Attached to MRCB's Letter (1st OS, 19 January 2022) was MRCB's letter dated 8 April 2021 to the Defendant (1st OS) which enclosed MRCB's "Final Account" for the Project (1st OS) [MRCB's Final Account (1st Project)]. MRCB's Final Account (1st Project) stated that there was an amount of RM33,799,638.10 due from the Defendant (1st OS) to MRCB for works performed by MRCB under the Main Contract [Defendant (1st OS)-MRCB].

[8] By way of a letter dated 24 January 2022, the Plaintiff's solicitors demanded for the Defendant (1st OS) [as MRCB's "principal" for the Project (1st OS) as understood in s 4 CIPAA] to pay to the Plaintiff the Adjudicated Amount (1st OS) with interest and costs as stipulated in the Adjudication Decision (1st OS) {Plaintiff's Demand [Defendant (1st OS), 24 January 2022]}. The Plaintiff's Demand [Defendant (1st OS), 24 January 2022] was made pursuant to s 30 CIPAA.

[9] The solicitors for the Defendant (1st OS) replied to the Plaintiff's De

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top