HIGH COURT MALAYA SHAH ALAM
OTIS ELEVATOR COMPANY (M) SDN BHD – Appellant
Versus
DESARU CONVENTION CENTRE SDN BHD & OTHER CASES – Respondent
[Originating Summons No: BA-24C-29-04/2022 BA-24C-30-04/2022 & BA-24C-31-04/2022]
| Table of Content |
|---|
| 1. employer cannot use dispute resolution agreement against sub-contractor. (Para 5) |
A. Introduction
[1] This judgment concerns the following three originating summonses (3 OS):
(1) OS No BA-24C-29-04/2022 (1st OS) has been filed by the plaintiff company (plaintiff) against Desaru Convention Centre Sdn Bhd [defendant (1st OS)];
(2) the plaintiff has instituted OS No BA-24C-30-04/2022 (2nd OS) against Desaru Estate Sdn Bhd [defendant (2nd OS)]; and
(3) OS No BA-24C-29-04/2022 (3rd OS) has been commenced by the plaintiff against Desaru Corniche Hotel Sdn Bhd [Defendant (3rd OS)].
B. Background
B(1). 1st OS
[2] The defendant (1st OS) had appointed Malaysian Resources Corporation Bhd (MRCB) as the main contractor for the construction of "Desaru Convention Centre" [Project (1st OS)].
[3] By way of a "Letter of Acceptance" (LA) dated 26 October 2015, MRCB appointed the plaintiff to perform certain construction work in the Project (1st OS) [Works (1st OS)].
[4] The plaintiff had performed the Works (1st OS) but had not been paid by MRCB for the Works (1st OS) [Unpaid Works (1st OS)]. Hence, the plaintiff claimed from MRCB for the Unpaid Works (1st OS) under the Construction Industry Payment and Adjudication Act 2012 (CIPAA). I shall refer to the adjudication proceedings commenced by the plaintiff against MRCB regarding the Unpaid Works (1st OS) as "Adjudication Proceedings (1st OS)".
[5] In The Adjudication Proceedings (1st OS):
(1) on 14 December 2021, the adjudicator, Mr Wong Kee Them [Adjudicator (1st OS)], had adjudicated [Adjudication Decision (1st OS)] that, among others, MRCB shall pay to the plaintiff a sum of RM334,998.21 [Adjudicated Amount (1st OS)] with interest and costs as stipulated in the Adjudication Decision (1st OS); and
(2) upon an application by the plaintiff's solicitors, due to a typographical error by the Adjudicator (1st OS), on 11 April 2022, the Adjudicated Amount (1st OS) was amended by the Adjudicator (1st OS) to RM334,988.21 [Amended Adjudicated Amount (1st OS)].
[6] The plaintiff's solicitors had sent a demand dated 21 December 2021 [Plaintiff's Demand-MRCB (1st OS, 21 December 2021)] to MRCB's representative in the Adjudication Proceedings (1st OS), Contract Solutions-I (CS), for MRCB to pay the Adjudicated Amount (1st OS) with interest and costs as stated in the Adjudication Decision (1st OS).
[7] MRCB's solicitors, Messrs Selva Mookiah Associates, replied to the Plaintiff's Demand-MRCB (1st OS, 21 December 2021) in a letter dated 19 January 2022 [MRCB's Letter (1st OS, 19 January 2022)]. According to MRCB's Letter (1st OS, 19 January 2022), among others:
(1) the Defendant (1st OS) owed money to MRCB under the main contract between the Defendant (1st OS) and MRCB with regard to the Project (1st OS) {Main Contract [Defendant (1st OS)-MRCB]}; and
(2) MRCB could not pay the Adjudicated Amount (1st OS) to the Plaintiff because MRCB had not received payment from the Defendant (1st OS) pursuant to the Main Contract [Defendant (1st OS)-MRCB].
Attached to MRCB's Letter (1st OS, 19 January 2022) was MRCB's letter dated 8 April 2021 to the Defendant (1st OS) which enclosed MRCB's "Final Account" for the Project (1st OS) [MRCB's Final Account (1st Project)]. MRCB's Final Account (1st Project) stated that there was an amount of RM33,799,638.10 due from the Defendant (1st OS) to MRCB for works performed by MRCB under the Main Contract [Defendant (1st OS)-MRCB].
[8] By way of a letter dated 24 January 2022, the Plaintiff's solicitors demanded for the Defendant (1st OS) [as MRCB's "principal" for the Project (1st OS) as understood in s 4 CIPAA] to pay to the Plaintiff the Adjudicated Amount (1st OS) with interest and costs as stipulated in the Adjudication Decision (1st OS) {Plaintiff's Demand [Defendant (1st OS), 24 January 2022]}. The Plaintiff's Demand [Defendant (1st OS), 24 January 2022] was made pursuant to s 30 CIPAA.
[9] The solicitors for the Defendant (1st OS) replied to the Plaintiff's De
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.