2020 MarsdenLR 230
HIGH COURT SABAH & SARAWAK KOTA KINABALU
SABANILAM ENTERPRISE SDN BHD – Appellant
Versus
MASENANG SDN BHD – Respondent
[Originating Summons No: BKI-24NCC(ARB)-1-11-2017]
Important Points
Subject
Arbitration - Contractual Disputes
Act Referred
Headnote
(B) Bill of quantities – Standards for issuing interim certificates – The Arbitrator erred in holding the Architect was obligated to issue interim certificates absent a proper valuation. The contract stipulates that certain conditions must be met prior to issuing certificates, which were not fulfilled. (Paragraphs 47, 51)
(C) Common law rights – Interplay between contract rights and common law – The court clarified that where contractual rights exist, they can restrict the independent application of common law termination rights; hence, an immediate common law termination without following contractual procedures is invalid. (Paragraphs 36, 65)
Facts of the case: The Plaintiff engaged the Defendant as a contractor for a mixed-use development. Disputes arose over payment claims leading to arbitration, which favored the Defendant. The Plaintiff's OS sought to set aside this decision. (Paragraphs 1, 2)
Findings of Court: The court found no basis to set aside the arbitrator's award but mandated a reassessment of parts nullified with the proper application of the Arbitration Act procedures concerning questions of law and interim certification duties. (Paragraphs 73)
Issues: The main questions included the interpretation of the contract regarding interim certificate issuance and the legitimacy of the Defendant's termination rights based on common law versus contract stipulations. (Paragraphs 19, 57)
Ratio Decidendi: The court affirmed that the Architect's certification role is not agent-like, and the requirements specified under the PAM Contract must be strictly adhered to for terminating (or issuing certificates), reinforcing the primacy of contractual obligations over common law rights. (Paragraphs 49, 56)
Result: The court allowed the Plaintiff's application in parts; certain paragraphs of the arbitration award were set aside, and the matter was remitted to the Arbitrator for reconsideration. (Paragraph 73)
JUDGMENT
Introduction
[1] The Plaintiff is the owner of a mixed-used development project consisting of 4-storey technology and commercial center, 16-storey office, 19-storey hotel, 16-storey hotel suites and basement carpark (the Project) to be constructed on NT. 213125127, NT. 213008505, NT.213008747, NT.213008694, NT.213206378 & NT.868, Partial NT.213008498 (Lot 2) and Partial NT.213178931 (Lot 2) along Penampang By-pass, Kg. Hungab, District of Penampang ("the Site"). Pursuant to a tender made by the Defendant on 22 June 2012, the Plaintiff, through Arkitek Billings Leong & Tan Sdn Bhd (the Architect), had by a Letter of Award dated 21 September 2012 (LOA) appointed the Defendant as the main contractor for the said Project. Problems arose on the payment claims submitted by the Defendant to the Plaintiff. The parties went for arbitration which was decided in favour of the Defendant. Not satisfied with the Award of the Arbitrator, the Plaintiff had commenced this Originating Summons (OS). For clarity, the contractual relationship between the Plaintiff and the Defendant was recognized and described in the Award as the 'PAM Contract' (also described as the 'Contract'). Under the PAM Contract the Plaintiff was the Employer whilst the Defendant was the Contractor. In the Arbitration Proceedings the Plaintiff was referred to as the Claimant and the Defendant was the Respondent. Throughout this Judgment the parties are referred to as they are in this OS.
The Arbitration Proceedings
[2] On the 12 October 2017, the Arbitrator published a Final Award in favour of the Defendant with the following findings:
(i) that the Defendant's termination of the contract by acceptance of the Plaintiff's repudiation of the Contract was lawful.
(ii) that the Plaintiff's claim that the termination by the Defendant was wrongful is without merit.
(iii) that the Defendant's termination of the Contract had not complied with cl 26 of the Contract on all its stipulations as such the Defendant cannot be considered to have determined the Defendant's own employment pursuant to cl 26 of the PAM Contract.
[3] Consequently the Arbitrator dismissed the Plaintiff's claim and awarded the Defendant the sum of RM26,765,198.29 together with interest and cost being the total sum for the following items:
(a) value of work done as at the date of termination.
(b) loss and expense suffered by the Defendant by reason of the termination of the Contract.
(c) loss and expense arising from extension of time.
The Originating Summons (OS) (Enclosure 1)
[4] In the OS the plaintiff applied for the following:
(1) Pursuant to s 37(1)(a)(v) and/or 37(2)(b) of the Arbitration Act 2005 , the Arbitration Award issued on 12 October 2017 by the Arbitrator, Mr Boon Che Wee ("Arbitration Award") in an arbitration proceedings between Sabanilam Enterprise Sdn Bhd and Masenang Sdn Bhd be set aside in whole or in such parts that fall within and satisfy ss 37(1)(a)(iv) and (v) and/or 37(2)(b) of the ;
(2) Further and/or in the alternative, pursuant to s 42 of the Arbitration Act 2005 :
(a) the questions of law arising out the Arbitration Award set out in Annexure 1 hereto be dealt with by this Honourable Court;
(b) upon determination of the questions of law set out in Annexure 1 hereto, the Arbitration Award either be set aside in whole or in part, be varied in whole or in part in accordance with the determination in prayers 2(a), and/or be remitted to the Arbitrator together with the determination of the High Court of Sabah and Sarawak at Kota Kinabalu on the applicable questions of law for reconsideration;
(c) The costs of this application shall be paid by the Defendant to the Plaintiff; and
(d) Any other relief or orders that this Honourable Court deems fit and proper in the circumstances of this case.
[5] The grounds of the OS are as follows:
(i) The Arbitrator had failed to observe the rules of natural justice and/or had exceeded his jurisdiction in arriving at the Arbitration Award;
(ii) T