2012 MarsdenLR 1238

HIGH COURT OF MALAYA SHAH ALAM
TEKNIK SEGALA SDN BHD – Appellant
Versus
SALCON ENGINEERING BERHAD – Respondent
[Civil Suit No: 22-2167-2007]



Important Points

A plaintiff in a contract must prove entitlement to claims and any alleged variations; failure to meet contractual milestones justifies termination and denial of claims.

Subject

Contract Law - Breach of Contract

Act Referred

Evidence Act 1950: S.101, S.103, S.92
Contracts Act 1950: S.40

Headnote

(A) Contracts Act 1950 - Termination of Contract - Liquidated and Ascertained Damages (LAD) - Breach of Contract - Plaintiff entered into a contract for the supply of a SCADA system, but did not complete the works by the deadline. Defendant lawfully terminated the Contract due to default and claimed LAD, costs for rectification, and consulting engineer costs. Plaintiff's claims for unpaid sums and variation orders rejected due to failure to prove entitlement. (Paras 1-64)

(B) Burden of Proof - The plaintiff bears the burden to prove claims and variations on the contract terms. Given no pleadings supported the variations, claims were dismissed. (Paras 16, 20, 37)
Table of Content
1. contract for scada system and lcp. (Para 1 , 2 , 3)
2. defendant's arguments on claims. (Para 4 , 5 , 6)
3. counterclaims by the defendant. (Para 7 , 8)
4. issues to be tried. (Para 9 , 10)
5. payment terms under the contract. (Para 12 , 13)
6. pleading requirements and variations. (Para 14 , 15 , 16 , 17)
7. burden of proof in contract claims. (Para 18 , 19 , 20 , 21)
8. limitation on oral evidence. (Para 22 , 23)
9. completion of contract milestones. (Para 24 , 25 , 26 , 27)
10. entitlement to payments based on milestones. (Para 28 , 29)
11. plaintiff's pleas for cash flow assistance. (Para 30 , 31)
12. legal burden of proof on the plaintiff. (Para 32 , 33)
13. assessment of work completed and payments. (Para 34 , 35)
14. nature of variation in lump sum contracts. (Para 36 , 37 , 38)
15. evidence on contract variations. (Para 39 , 40 , 41)
16. entitlement to liquidated damages. (Para 42 , 43)
17. timeliness and delays in performance. (Para 44 , 45 , 46)
18. lawfulness of contract termination. (Para 47 , 48)

[1] This case involves a contract for the Supply, Delivery, Installation, Testing and Commissioning of Supervisory Control and Data Acquisition (SCADA) System and Local Control Panel (LCP) for the Sungai Kinta Water Treatment Project ("the Works"). The plaintiff entered into a contract with Salcon-Trans Consortium (STC), an unincorporated venture company to complete the works. The defendant was the managing partner of the joint venture. The contract entered by the parties was in the form of a works order dated 2 November 2004 which comprised of the documents and appendixes attached thereto, ("the Contract"). It is an agreed fact that the plaintiff had on 22 November 2006 removed the entire Programmable Logic Controller (PLC) programme from the relevant computers on the project site. It is also an agreed fact that the defendant had issued a notice dated 22 November 2006 for the termination of the Contract ("Termination Notice").

[2] It has been agreed by the parties that:

(1) The terms of the Contract included, inter alia:

(i) The contract sum was RM 1,790,000.00

(ii) Term of payment was 60 days from the date of completion of each milestone and submission of invoice

(iii) The delivery date was August 2005.

(2) The payment term as set out in clause 10 of the Contract as follows

"(i) Payment terms

60 days upon completion of each milestone and submission of an invoice.

(ii) Progress terms

10% upon design drawing submission and approval

75% upon Factory Acceptance Test (FAT) and site delivery

10% upon site testing and commissioning

5% retention for 12 months after commissioning".

[3] The plaintiff has pleaded that it had completed the Works on or before the completion date but the defendant had failed to pay RM809,068.95 comprising the balance of the Contract Sum and sums for variation works.

[4] It is the defendant's case that the plaintiff is not entitled to claim the said sum for the following reasons:

(1) The plaintiff is not entitled to claim the alleged unpaid billed sums amounting to RM273,034.50 because the sums relate to materials or works that had not been completed up to date of the Termination Notice.

(2) The plaintiff is not entitled to claim the alleged unbilled sums amounting to RM198,744.45 because the sums relate to materials or works that had not been completed up to the date of the Termination Notice.

(3) The plaintiff is not entitled to any part of the variation order claims amounting to RM334,945.00 because they relate to materials and work that were within the scope of the Contract, or materials and work that had not been instructed or authorized by the defendant.

[5] It is the defendant's case that the Contract was awarded on a lump sum basis and the Contract Sum was to be paid for the completion of total Contract obligations and works under the following payment milestones:

(i) 10% upon design drawing submission and approval

(ii) 75% upon FAT and site delivery

(iii) 10% upon site testing and commissioning

(iv)5% retention fo

1
2
3
4
5
6
7
8
9
10