[1] This is a suit principally to determine the contracting parties of the construction contract and the resultant consequences thereto for unpaid work done.
[2] The Plaintiff is a private limited company involved in the hydraulic pile injection system business.
[3] The First Defendant is likewise a private limited company involved in the property development business.
[4] The Second Defendant is also a private limited company involved in the property management services business.
Preliminary
[5] In this suit, the Plaintiff claimed against the Defendants for the following:
(1) A declaration that the 1st Defendant and/or the 2nd Defendant is a party/are parties to the Contract with the Plaintiff;
(2) The following sums to be paid by the 1st Defendant and/or the 2nd Defendant to the Plaintiff:
(a) The Outstanding Sum of RM2,463,418.95;
(b) In the alternative, damages to be assessed;
(c) Interest at 7.9% per annum being the Maybank Base Lending Rate of 6.9% per annum plus 1 % as provided in cl 30.17 of the Conditions of Contract on the Outstanding Sum of RM2,463,418.95 to run from the following periods until full payment is made:
(i) for the sum of RM1,641138
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.