SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 1378

HIGH COURT MALAYA KUALA LUMPUR
BESJAYA MAJU SDN BHD – Appellant
Versus
HIM DEVELOPMENT SDN BHD & ORS – Respondent
[Civil Suit No: WA-22NCvC-324-06-2023]



Petitioner Advocates:Karen Isabel Wilfred ,Respondent Advocate: Ooi Tuan Leng,Tang Hui Jun,Chiam Jia Yann

The enforceability of a Joint Venture Agreement is upheld despite delays, and implied consent to extensions does not absolve parties of their contractual obligations.

Headnote:(A) Civil Law Act 1956 - Joint Venture Agreement - Clause 5.1(i)(a) - The Plaintiff claimed damages for breach of contract due to the Defendants' failure to fulfill obligations under the Joint Venture Agreement dated 10 November 2014. The court found that the Defendants did not fulfill conditions precedent, and the JVA remained enforceable. (Paras 12, 16, 41)

(B) Implied Consent - The Plaintiff's conduct indicated implied consent to extensions of time, but this did not negate the Defendants' obligations to fulfill the contract. (Paras 25, 27)

(C) COVID-19 Act - The Defendants failed to prove that COVID-19 caused delays in performance, thus could not rely on the Act for relief. (Paras 20, 22)

(D) Damages - The court awarded RM2,425,000.00 in contractual damages, RM1,282,533.63 in interest, and RM120,000.00 in costs, reinforcing that parties cannot evade responsibilities due to external disruptions. (Paras 42, 43)

JUDGMENT

Roz Mawar Rozain J:

[1] This case presents a classic intersection of contractual obligations, commercial reliance, and the consequences of non-performance in a high-stakes joint venture development. As emerged at trial, this dispute is not merely about delayed approvals and missed deadlines but about the expectations and responsibilities of parties engaged in a sophisticated land development agreement.

[2] The Plaintiff asserts its right to claim contractual entitlements under their Joint Venture Agreement for land development dated 10 November 2014 (JVA). The 1st defendant and its guarantors (the 2nd defendant and one Lai Hoong Sung (the Deceased) with now the 3rd and 4th defendants cited in this suit as they are the co-administrators of the Deceased's estate) argue that the contract should be deemed terminated due to unfulfilled conditions precedent, raising critical questions about waiver, extensions by conduct, and liability.

Agreed Facts

[3] The following facts were agreed upon by all the parties and remain undisputed:

(a) The JVA between the Plaintiff and the 1st defendant that they had executed on 10 November 2014 is for a residential development project on land held by the Plaintiff under HS(M) 26010, Lot PT 40200 and HS(M) 26533, Lot PT 40593.

(b) The 1st defendant had made a deposit payment of RM200,000.00 as per cl 3 of the JVA to the Plaintiff. The payment by the 1st defendant was made in two tranches (RM30,000.00 and RM170,000.00).

(c) The 1st defendant had successfully amalgamated the two pieces of land for development and subdivided the development land into 16 individual lots.

(d) The 2nd defendant and the Deceased executed a Guarantee and Indemnity Agreement on the same date as the JVA — 10 November 2014 (the Guarantee) whereby they had jointly and severally undertook and guaranteed the 1st defendant's obligations under the JVA including the payment of RM2,425,000.00 (the total after deducting the deposit payment of RM200,000.00) with interest at 8% per annum from the agreed completion date of 10 May 2018 until full settlement.

(e) The 2nd defendant and the Deceased were directors of the 1st defendant at the material times and through cl 2(f) of the Guarantee, it was agreed that their obligations will continue to exist until released through the implementation of the Guarantee, regardless of any resignation as director, unless the Plaintiff agrees in writing to substitute the director who resigned.

(f) The Plaintiff had not, at any time, given consent to replace any of the guarantors under the Guarantee.

(g) The 2nd defendant and the Deceased agreed that their liability under the Guarantee shall not in any way be relieved, diminished or affected by death, their insanity or any incapacity (cl 2(1) of the Guarantee).

(h) The Plaintiff's cause of action under the Guarantee continues to exist against the estate of the Deceased based on the provisions of the Guarantee and in accordance with s 8(1) of the Civil Law Act 1956 .

(i) This action by the Plaintiff is commenced against the 3rd and 4th defendants as personal representatives for the estate of the Deceased according to O 15 r 6A of the Rules of Court 2012 (RoC).

Evidence Adduced At Trial

[4] At trial, the Plaintiff called upon its representative (PW1), who gave evidence on the Plaintiff's entitlement under the JVA and the 1st defendant's failure to perform its contractual obligations. PW1 testified that the Plaintiff had contributed the lands for the joint venture project. In return, it was entitled to 3.5 units of double-storey linked houses or their monetary equivalent of RM2,625,000.00 as stipulated under the JVA.

[5] PW1 claimed that the joint venture project was delayed beyond the agreed 4 years (ending on 10 November 2018). Despite approvals such as the layout plan being secured on 18 July 2018, the 1st defendant had failed to complete the joint venture project as agreed under the JVA. The Plaintiff's evidence highlighted that critical milestones like the layo

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top