SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 MarsdenLR 709

COURT OF APPEAL PUTRAJAYA
VENTURE SKL SDN BHD – Appellant
Versus
GEONEX (M) SDN BHD – Respondent
[Civil Appeal No: C-02(NCVC)(W)-438-03-2021]



Petitioner Advocates:Kamalanathan Ratnam,Vinod R Kamalanathan ,Respondent Advocate: Lee Shu Min

The court determined that a contract remains valid unless mutually annulled or replaced, upheld by statutory obligations under the Evidence Act.

Headnote:[Statute Analysis] The governing statutes include provisions from the Evidence Act 1950 regarding the presumptions of validity of agreements and responsibilities of parties in contracts. [Facts of the Case] The case involves an appeal against a trial judgment related to the termination of an iron ore mining contract. The trial court found the Appellant's claim dismissed and allowed the Respondent's counterclaim. [Findings of Court] The appellate court reversed the decision, finding the Agreement still subsisted and the Respondent acted wrongly in terminating it. [Issues] The critical issue framed was whether the initial Agreement remained in force following discussions for a new Agreement. [Ratio Decidendi] The appellate court reasoned that the Agreement was never mutually terminated and emphasized the Respondent's duty to draft a new contract as previously discussed. [Result] The appeal was allowed, the Appellant's claims were recognized, and the Respondent's counterclaim was disallowed.

Table of Content
1. essential facts of the appeal regarding the mining contract and the initial judgment. (Para 1 , 2 , 4 , 19)
2. overview of the trial's findings and judgments impacting the appeal. (Para 18 , 20 , 22)
3. concluding judgment on the appeal and its implications for both parties. (Para 24 , 25)
4. determination of contract status and implications of actions taken by the respondent. (Para 26 , 31 , 38 , 42)
Lim Chong Fong JCA:

Introduction

[1] This is an appeal against the trial judgment of the High Court in respect of an iron ore mining contract whereby the Appellant's claim was dismissed with costs and the Respondent's counterclaim of RM20,000.00 was allowed with costs.

[2] We heard the appeal on 19 January 2023 and thereafter unanimously allowed the appeal. In this regard, we found that the contract was terminated on 29 September 2016. We set aside the High Court's judgment and we, in substitution, only allowed the Appellant's claim made in prayers (v), (vi) and (vii) of the statement of claim to be assessed by the High Court (but not exemplary and punitive damages) with costs of RM40,000.00 subject to allocatur. Additionally, the Respondent's counterclaim is disallowed.

[3] The Appellant and Respondent were the Plaintiff and Defendant in the High Court respectively.

Background

[4] By a quadripartite written agreement dated 26 February 2016 ("Agreement") made between the Respondent, Appellant, Siva Kumar Govindan (a director of the Respondent) and Hoe Hock Lai (a director of the Appellant), the Respondent appointed the Appellant as its exclusive mining sub-contractor to mine an area known as ML 16/2014 Lot P.a 26644 (PA 265864) Sungai Rawit, Mukim Semantan, Temerloh, Pahang consisting of 40.33 hectares (99.66 acres) ("Land") upon which the Director of Land & Mines of Pahang leased the Land to Bayu Mining Sdn Bhd ("Lessee"). The Lessee and the Respondent were also granted permission and rights as an operator to carry out development work and mining operation on the Land by the Director of Land & Mines of Pahang.

[5] The Agreement without its appendices is reproduced below:

[6] After the execution of the Agreement, the Appellant's and Respondent's representatives met on 19 May 2016 and 31 May 2016 and discussed on the Agreement ("Meetings"). The minutes of the Meetings are also reproduced Below:

[7] Since the conclusion of the aforementioned Meetings, there was no new agreement entered between the partis.

[8] AS a result, the Respondent via its solicitor Messrs. Bastion Vendargon wrote on 2 September 2016 and again on 7 September 2016 to the Appellant enquiring about the drafting of the new agreement.

[9] The Respondent thereafter on 29 September 2016 wrote to the Appellant to forthwith cease all operations until the new agreement is finalised and executed by the parties.

[10] The Respondent again via its solicitor Messrs. Bastion Vendargon wrote on 17 October 2016 to the Appellant giving the Appellant 2 weeks from the date of the notice to vacate the Land.

[11] The Appellant via its solicitor Messrs. R. Shan & Associates replied on 27 October 2016 to the Respondent's solicitor Messrs. Bastion Vendargon that the Agreement was still valid and on the Appellant's desire to continue to perform the Agreement. The Appellant also denied trespassing on the Land.

[12] Subsequently after the mining lease had been successfully renewed, the Respondent via its solicitor Messrs. Bastion Vendargon wrote on 29 November 2017 to the Appellant giving the Appellant 4 weeks from the date of the notice to vacate the Land.

[13] The Appellant via its new solicitor Messrs. Andrew-David Wong & Ong replied on 20 December 2017 to the Respondent' solicitor Messrs. Bastion Vendargon that the Agreement was still valid but the Appellant could not carry out mining activity since October 2016 because of the dispute between the Respondent and the Lessee on mining on the Land. The Appellant maintained that it was ready and willing to perform the Agreement and did

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top