COURT OF APPEAL PUTRAJAYA
ENCORP ISKANDAR DEVELOPMENT SDN BHD – Appellant
Versus
KONSORTIUM IPMINES MERZ SDN BHD – Respondent
[Civil Appeal Nos: B-02(C)(A)-981-08-2020 & B-02(C)(A)-984-08-2020]
| Table of Content |
|---|
| 1. overview of appeals and court decisions. (Para 1 , 2 , 3 , 4) |
| 2. court's decision to allow the appeals. (Para 5 , 6) |
| 3. chronology of events leading to adjudication. (Para 7 , 8 , 9 , 10) |
| 4. issues identified for high court determination. (Para 11 , 12 , 16 , 17) |
| 5. jurisdictional challenges and statutory interpretation. (Para 18 , 19 , 20 , 21) |
| 6. application of cipaa and its implications. (Para 22 , 23 , 24 , 25) |
| 7. interpretation of agreements and jurisdiction. (Para 26 , 27 , 28 , 29) |
| 8. arguments regarding applicability of cipaa. (Para 30 , 31 , 32) |
| 9. court's interpretation of the novation agreement. (Para 33 , 34 , 35) |
| 10. adjudicator's jurisdiction and decision-making. (Para 38 , 39 , 40 , 41) |
| 11. arguments regarding quantum meruit application. (Para 60 , 61 , 62 , 63) |
| 12. corrections made by the adjudicator and natural justice. (Para 69 , 70 , 71) |
| 13. reviewability of adjudication decisions. (Para 72 , 73) |
| 14. stay of enforcement and its implications. (Para 74 , 75) |
Introduction
[1] There are 2 Appeals filed herein, both by the Appellant, Encorp Iskandar Development Sdn Bhd The Respondent in both the appeals is Konsortium Ipmines Merz Sdn Bhd Both the appeals are against the decision of the Shah Alam High Court dated 29 July 2020. The High Court decision emanated from the Adjudication Decision (AD) of Mr Foo Joon Liang (the Adjudicator) dated 26 September 2019. The AD was issued under the Construction Industry Payment and Adjudication Act, 2012 (CIPAA) pursuant to an adjudication commenced by the Respondent against the Appellant for payment for work done. As to the outcome of the adjudication, in a nutshell, the Adjudicator allowed the Respondent's claim against the Appellant.
[2] Flowing from the abovesaid AD, the Appellant applied to the Shah Alam High Court vide Saman Pemula No: BA-24C-103-10/2019 (OS: 103), to set aside the AD and to stay the enforcement of the same, pending arbitration between the parties, pursuant to ss 15 and 16 of CIPAA. This was followed by the Respondent applying to enforce the same AD under s 28 of the same Act vide Saman Pemula No: BA-24C-121-12/2019 (OS: 121). The learned High Court Judge (HCJ) heard both the OS at one go.
[3] On 29 July 2020 the learned HCJ dismissed the Appellant's application (OS: 103) and at the same instance, allowed the Respondent's application (OS: 121).
[4] Aggrieved, the Appellant appealed to the Court of Appeal against both the decisions abovementioned. Hence, the Appeals before us herein. For both the appeals, the learned HCJ had prepared one common grounds of judgment.
Our Decision
[5] We heard both the Appeals together and after having appraised the Records of Appeal for both the Appeals including the grounds of judgment (GOJ) of the learned HCJ and having considered the submissions by both learned counsels, we unanimously found that there are merits in the Appellant's appeals. Thus, we allowed the appeals and consequently set aside the decisions and the orders of the learned HCJ dated 29 July 2020. Effectively, the AD dated 26 September 2019 is also accordingly set aside.
[6] We allowed the Appeals abovesaid on the following grounds.
Factual Background And Chronology Of Events
[7] The relevant undisputed facts and chronology of events are:
The Adjudication:
(i) The Appellant is the owner of a mixed development project in Johor Bahru, Johor Darul Takzim known as "Cadangan Pembangunan Pangsapuri Servis (571 unit) Dan Ruang Niaga..." (the project).
(ii) 6 August 2013 - Vide a Letter of Award dated 6 August 2013 (the Main Agreement) the Appellant appointed its associate company Encorp Construct Sdn Bhd (ECSB) as its main constructor for the project. (see: "Appeal Record, Vol 2B" pp 289 - 294).
(iii) 24 October 2014 - ECSB then engaged the Respondent as its subcontractor for the project vide a Sub-Contract Agreement dated 24 October 2014 (Sub-Contract).
(iv) 30 June 2015 - Thereafter, the Respondent, ECSB and the Defendant entered into a Novation
Inai Kiara Sdn Bhd v. Puteri Nusantara Sdn Bhd
Jack-In Pile (M) Sdn Bhd v. Bauer (Malaysia) Sdn Bhd & Another Appeal
Pasukhas Sdn Bhd v. Empire Multiple Sdn Bhd & Another Case
View Esteem Sdn Bhd v. Bina Puri Holdings Berhad
ACFM Engineering & Construction Sdn Bhd v. Esstar Vision Sdn Bhd & Another Appeal
ASM Development (KL) Sdn Bhd v. Econpile (M) Sdn Bhd & Other Appeals
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.