SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 4800

SESSION COURT SHAH ALAM
TERAJU PRECAST SERVICES SDN BHD – Appellant
Versus
SWETTENHAM HERITAGE SDN BHD – Respondent
[Civil Suit No: BA-A52NCvC-308-08/2021]



Petitioner Advocates:Nasrul Hadi Mat Saad ,Respondent Advocate: Christopher,Lee Eu Kong

The court ruled that the Plaintiff failed to prove the existence of the retention sum owed, and the Defendant's counterclaim for negligence was dismissed due to lack of evidence and failure to establish a duty of care.

Headnote:(A) Evidence Act 1950 - Section 101 - Goods and Services Tax Act 2014 - Sections 31(1) and 33(1) - Claim for outstanding debts arising from a subcontracted construction project - Plaintiff sought payment for retention sum of RM62,287.73, while Defendant counterclaimed for RM146,993.96 due to rejected GST claim - Court dismissed both claims, finding Plaintiff failed to prove the retention sum was owed, and Defendant's counterclaim lacked merit. (Paras 83, 84)

(B) Burden of Proof - The burden rests on the Plaintiff to establish the existence of the retention sum owed, which was not substantiated during the trial. (Paras 55, 83)

(C) Duty of Care - The Defendant failed to prove that the Plaintiff owed a duty of care beyond contractual obligations, as the Defendant was not in a vulnerable position and had control over its accounting processes. (Paras 57, 84)

Facts of the case:
The Plaintiff and Defendant were engaged in a construction project under a main contractor, with the Plaintiff alleging that a retention sum remained unpaid. The Defendant counterclaimed for losses related to a rejected GST claim. (Paras 2, 3, 4, 5)

Findings of Court:
The court found that the Plaintiff did not provide sufficient evidence to support its claim, and the Defendant's counterclaim was speculative and unproven. Both claims were dismissed. (Paras 83, 84)

Issues: The main issues included whether the Defendant owed the Plaintiff the retention sum and whether the Plaintiff was liable for the Defendant's counterclaim. (Paras 16, 17)

Ratio Decidendi: The court ruled that the Plaintiff failed to discharge its burden of proof regarding the retention sum, while the Defendant's counterclaim was dismissed due to lack of evidence and failure to establish a duty of care. (Paras 83, 84)

Result: Both parties' claims are dismissed, and each party is ordered to bear its own costs.

JUDGMENT

(Full Trial)

Yong Leou Shin SCJ:

A. Introduction

[1] This is a claim for outstanding debts arising from a business relationship involving subcontracted construction works under a public construction project.

[2] The Plaintiff sought judgment against the Defendant for the sum of RM62,287.73, alleging it remained unpaid as the retention sum, along with costs. The Defendant denied liability and counterclaimed RM146,993.96, citing losses from a rejected GST claim.

[3] After a full trial, this court dismissed both parties' claims and ordered each party to bear their own costs.

B. Salient Facts

[4] The Plaintiff and the Defendant were engaged in work under the main contractor, Hakikat Engineering Sdn Bhd ("Hakikat Engineering"), for a construction project undertaken by the Jabatan Kerja Raya (JKR). The project, titled "Cadangan Pembinaan Ibu Pejabat Pertahanan Awam (IPPA), Sungai Merab, Mukim Dengkii, Sepang, Selangoris referred to as the IPPA Project.

[5] The Defendant was awarded subcontract work under the IPPA Project by the main contractor, Hakikat Engineering. When a portion of the IPPA Project required work involving 'Precast Components IBS', the Defendant subcontracted this specific work to the Plaintiff.

[6] On 28 September 2015, the Plaintiff and Defendant signed an "Agreement of Strategic Alliance - Proposed Construction of the Civil Defence Headquarters (IPPA), Sungai Merab, Mukim Dengkii, Sepang, Selangor" based on a Letter of Award.

[7] The Agreement stipulated a total contract value of RM2,814,802.50. Despite the Agreement, the Plaintiff reported to the main contractor, Hakikat Engineering, regarding any "Stop Work Orders" issued during the project.

[8] After 1 year and 6 months of working under the Letter of Award, the Plaintiff, with the consent of Hakikat Engineering and JKR, signed a Deed of Assignment on 14 April 2017.

[9] The Deed of Assignment transferred the obligation for payments owed by JKR for work completed by the Plaintiff under the Letter of Award directly to the Plaintiff. The contractual value under the Deed of Assignment at the time of signing was RM1,526,382.00.

[10] Following the Deed of Assignment, JKR commenced direct payments to the Plaintiff for the 'Precast Components IBS' work performed.

[11] The Plaintiff completed its contractual obligations and received progress payments but alleged that an outstanding amount of RM62,287.73 i.e the retention sum remained unpaid by the Defendant.

[12] In 2018, the Plaintiff filed a claim against the Defendant in the Magistrate's court in Shah Alam for the outstanding amount of RM62,287.73 through Civil Suit No: BA-A72NCVC-2169-10/2018 ("Civil Suit No: 2169").

[13] The Civil Suit No:2169 was later withdrawn by mutual agreement that the claimed amount of RM62,287.73 would be paid after the Defendant received the retention sum from the Jabatan Kerja Raya (JKR).

[14] However, the Plaintiff claimed that no payment was made even after the Project's completion in March 2019. Accordingly, the Plaintiff, through its solicitors, issued a demand letter dated 11 November 2020 requesting the Defendant to pay RM62,287.73 to the Plaintiff.

[15] The Defendant filed a defence denying any indebtedness to the Plaintiff and submitted a counterclaim amounting to RM146,993.96, alleging losses incurred after the Royal Malaysian Customs Department rejected the Defendant's GST claim.

C. Agreed Issues To Be Tried

[16] Agreed issues to be tried (filed vide encl 29) are as follows:

i. Whether the Defendant still owes the Plaintiff the sum of RM62,287.73 under the Contract.

ii. Whether the sum of RM62,287.73 constitutes the retention sum withheld by the Jabatan Kerja Raya under the Contract.

Whether the Jabatan Kerja Raya has released the retention sum, and if so, which party received the retention sum.

iv. Whether the Plaintiff is liable to pay the Defendant's counterclaim for losses and expenses amounting to RM146,993.96.

v. Whether the sum of RM146,993.96 represents the refund of GST input tax to the


Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top