SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2020 MarsdenLR 1887

HIGH COURT MALAYA SHAH ALAM
CABNET SYSTEMS [M] SDN BHD – Appellant
Versus
DEKAD KALIBER SDN BHD & ANOR – Respondent
[Originating Summons No: BA-24C-5-01-2019]



Petitioner Advocates:Maximilian Tai Kim Sen,Krishanthini Dewi Jeeva Kumar ,Respondent Advocate: Nadzarin Wok Nordin,Azhar Arman Ali,Rachel Loi Guong-Li

Statutory obligations under CIPAA supersede contract liabilities regarding payments, asserting that payments made by a principal do not constitute undue preference in liquidation contexts.

Headnote:(A) Construction Industry Payment and Adjudication Act 2012 – Section 30; Companies Act 2016 – Sections 528(1) and 471(1) – Dispute over unpaid adjudicated sums following the subcontracting in a construction project – The court ruled the 2nd defendant liable to pay the adjudicated amounts, affirming the definition of 'principal' and clarifying that payment does not constitute an 'undue preference' due to the statutory obligation imposed by Section 30 CIPAA. (Paras 19, 20, 41)

(B) Adjudication costs – The court concluded that the term 'adjudicated amount' does not include adjudication costs, which must be paid separately as confirmed by statutory interpretation. (Paras 34, 41)

Facts of the case: The plaintiff entered into a Sale and Purchase Agreement with a subcontractor who failed to pay for supplied equipment, leading to adjudication under CIPAA. The 1st defendant, the main contractor, went into liquidation affecting payment obligations. (Paras 5-11)

Findings of Court: The 2nd defendant is deemed a principal under the statutory definition and is liable to pay without it being an undue preference under insolvency law, following previous case law standards. (Paras 19-25, 41)

Issues: The issues included the definition of 'principal', whether payment constitutes undue preference, the need for leave under winding-up procedures, and the interpretation of 'adjudicated amount'. (Paras 13, 20, 24)

Ratio Decidendi: The ruling concluded that payment obligations were statutory and did not infringe upon preferential payment laws, thereby affirming the hold of statutory obligations over contract rights in certain scenarios. (Paras 19-25, 41)

Result: Originating Summons allowed with costs payable by the defendants.

JUDGMENT

Wong Kian Kheong J:

A. Background

1

[1] The first defendant company (1st defendant) was the main contractor of a construction project called "ICQS" at Bukit Kayu Hitam, Kedah Darul Aman (Project).

[2] For the Project, the 1st defendant had appointed Synergycentric Sdn Bhd (SSB) as a subcontractor for "ICT and Security Works Package" (Subcontract).

[3] On 18 July 2017, the plaintiff company (plaintiff) entered into a "Sale and Purchase Agreement" (SPA) with SSB whereby for the purpose of the Project, the plaintiff had agreed to sell to SSB, deliver, install, test and commission "CCTV" (Closed-Circuit Television), "ACS" (Access Control System) and "PA" (Public-Address System) (collectively referred to as the "Equipment").

[4] Pursuant to the SPA, the plaintiff had supplied, delivered, tested and commissioned the Equipment for the Project.

[5] According to the plaintiff, SSB had only paid RM3,449,302.48 to the plaintiff for the Equipment and there was an outstanding sum of RM1,120,718.96 (plaintiff's Claim).

[6] The plaintiff's Claim was referred to adjudication under the Construction Industry Payment and Adjudication Act 2012 (CIPAA) and the adjudicator, Mr Loo Chun Kok, made an adjudication decision on 10 November 2018 (AD). The AD provided as follows, among others:

(1) SSB shall pay RM1,077,326.36 (Adjudicated Sum) to the plaintiff;

(2) a sum of RM34,546.84 as late payment interest on the Adjudicated Sum (up to 11 July 2018) shall be paid by SSB to the plaintiff (Pre-AD Interest);

(3) interest at the rate of 5% per annum on the Adjudicated Sum shall be paid by SSB to the plaintiff from 12 July 2018 until full payment of the Adjudicated Sum (Post-AD Interest); and

(4) SSB shall pay a total sum of RM44,000.90 to the plaintiff for the fees and expenses of the Adjudicator and Asian International Arbitration Centre (Adjudication Costs).

[7] On 21 August 2019, the Kuala Lumpur High Court (Winding-Up Court) wound up SSB (Winding-Up Order). The Winding-Up Order has appointed the Official Receiver (OR) as an interim liquidator for SSB.

[8] Pursuant to s 30 CIPAA, the plaintiff's solicitors had served a demand dated 27 November 2018 on the 1st defendant [plaintiff's Demand (1st defendant)] to pay the total sum awarded in the AD (Total Adjudicated Sum) within 14 days from the date of the plaintiff's Demand (1st defendant).

[9] The 1st defendant replied to the plaintiff's Demand (1st defendant) by a letter dated 10 December 2018 [1st defendant's Letter (10 December 2018)]. According to the 1st defendant's Letter (10 December 2018), among others:

(1) the 1st defendant, SSB and the 2nd defendant had entered into a novation regarding the Subcontract (Novation); and

(2) the plaintiff was "advised" to write directly to the 2nd defendant regarding the plaintiff's claim for the Total Adjudicated Sum.

[10] The plaintiff's solicitors had requested for a copy of the Novation from the 1st defendant by way of two letters dated 18 December 2018 and 10 January 2019 (plaintiff's two requests) but to no avail.

[11] The plaintiff's solicitors sent a demand dated 18 December 2018 to the 2nd defendant [plaintiff's Demand (2nd defendant)] for the 2nd defendant to pay the Total Adjudicated Sum within 14 days from the date of the plaintiff's Demand (2nd defendant). The 2nd defendant did not accede to the plaintiff's Demand (2nd defendant).

B. This Originating Summons (OS)

[12] The plaintiff filed this OS for the following orders against the 1st and 2nd defendants (collectively referred to as the "defendants"), among others:

(1) a declaration that the 1st defendant and/or the 2nd defendant is liable as the "principal of SSB to pay to the plaintiff the Total Adjudicated Sum under the AD; and

(2) an order that the 1st defendant and/or the 2nd defendant as SSB's "principal" shall pay to the plaintiff the Total Adjudicated Sum under the AD.

C. Issues

[13] This OS raises the following questions:

(1) based on the Novation and s 63 of the Contracts Act 1950 [ CA (1950)], is the 2

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top