SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2014 MarsdenLR 1617

COURT OF APPEAL PUTRAJAYA
OXBRIDGE HEIGHT SDN BHD – Appellant
Versus
ABDUL RAZAK MOHD YUSOF & ANOR – Respondent
[Civil Appeal No: J-02(NCVC)(W)-2725-12-2013]



Petitioner Advocates:B Thangaraj,Tan Vincent,R Archana ,Respondent Advocate: K Bharathi

Settlement agreements can be valid even with modifications to statutory obligations when negotiated under proper conditions and with appropriate oversight, particularly in housing development contexts.

Headnote:(A) Housing Development (Control and Licensing) Regulations 1989 - Section 11(1) - Contracts Act 1950 - Section 64 - Appeal regarding breach of settlement agreement and tort of deceit - High Court dismissed the claim; appeal partly allowed for breach of settlement agreement with damages of RM50,000 awarded, plus interest from date of order. (Paras 1-34)

(B) Fraudulent Misrepresentation - The court found insufficient evidence to establish fraudulent misrepresentation; mere suggestion of waiver of liquidated damages was not binding. (Paras 19-21)

(C) Settlement Agreement - Found valid in allowing extension of completion date and waiver of liquidated damages claims, upheld by evidence of negotiations and approvals involving JPN. (Paras 23-30)

Table of Content
1. appellant's claim and background facts (Para 1 , 2 , 4 , 5 , 6)
2. background facts of the housing project and parties involved (Para 7)
3. details of the settlement agreement (Para 8 , 9 , 10 , 12 , 13)
4. details of the settlement agreement and execution (Para 11)
5. claims and arguments presented by the appellant (Para 14 , 17)
6. pleading the claim in high court (Para 15 , 16 , 18)
7. high court findings on deceit and settlement agreement validity (Para 19 , 20 , 21 , 22)
8. appeal court's reasoning on validity and public policy (Para 23 , 24 , 25 , 26 , 30)
9. court's evaluation of appeal principles and legal standards (Para 27)
10. discussion on statutory limits of waiving lad (Para 28 , 29)
11. conclusion and awarded damages (Para 31 , 32 , 33)
Mohamad Ariff Md Yusof JCA:

A. The Parties

[1] The appellant in this appeal, Oxbridge Height Sdn Bhd, was a housing developer for a project described as Jaya Putra Perdana which comprised part of a larger project described as Bandar Jaya Putra. The respondents were purchasers of a double-storey terrace house in Phase B of Jaya Putra Perdana. The appellant was the vendor of the property.

[2] The appellant/plaintiff had sued the respondents/defendants in the High Court below for the tort of deceit, fraudulent misrepresentation and breach of a settlement agreement entered into between them. The High Court dismissed the appellant's claim with costs.

B. Our Decision In The Appeal

[3] We allowed the appellant's appeal before us in part with an order that parties were to bear their own costs. The claim for breach of the settlement agreement was allowed with damages of RM50,000.00 to be paid by the respondents to the appellant together with judgment interest from the date of our order until full payment.

C. Background Facts

[4] In the sale and purchase agreement ("SPA") executed between the parties dated 17 April 2006, which followed the standard agreement under Schedule G of reg 11(1) of the Housing Development (Control and Licensing) Regulations 1989 ("the regulations"), the usual provision on Liquidated and Ascertained Damages ("LAD") for late delivery was included. Clause 23 of the SPA required vacant possession of the building to be delivered to the purchaser within 24 calendar months from the date of the SPA, failing which the vendor (the developer) was liable to pay to the purchaser liquidated damages "calculated from day-to-day at the rate of 10% per annum of the purchase price from the expiry date of the delivery of vacant possession .... until the date the purchaser takes vacant possession of the same building."

[5] The project stalled. According to the plaintiff, as the developer, the project suffered financial difficulties as a result of flooding (force majeure) from around December 2006 until early 2007. The project was classified by Bahagian Pemantauan Perumahan Swasta, Jabatan Perumahan Negara, Kementerian Perumahan dan Kerajaan Tempatan ("JPN") as a "projek lewat" and "projek sakit". In the report produced by JPN, it was acknowledged that the project suffered delays because the developer faced a force majeure problem.

[6] The parties then entered into a settlement agreement formally dated as 10 October 2011. This important agreement was tendered in Court as exh P18 (appearing on pp 464 to 476 of the Appeal Record, Parts B & C). The immediate parties to the settlement agreement were the appellant as vendor and several parties described as "the purchaser" as set out in sch 2 of the said agreement. There were altogether 41 purchasers included in sch 2, with the present respondents listed as purchaser no 11. It was also clear from sch 2 that the properties concerned phase 3B of the project. According to the appellant, the 1st respondent acted as the representative of purchasers of phase 3B.

[7] It appeared on the evidence that the signing of the settlement agreement was the result of the involvement and assistance of JPN and a series of meetings held between the parties. Accord

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top