COURT OF APPEAL, PUTRAJAYA
FIRST COUNT SDN BHD – Appellant
Versus
WANG YEW LOGGING & PLANTATION SDN BHD – Respondent
[Civil Appeal No: Q-02-2932-2010]



The acceptance of a reduced contract fee by continuing operations leads to estoppel, barring claims of loss due to the reduction, necessitating sufficient proof for claims in contract disputes.

Headnote:(A) Contracts Act, 1950 - Reduction of contract fees - Breach of contract - Plaintiff claimed for loss due to reduction in contract fees imposed by defendant - The court found that continuation of contract despite reduced fees constituted acceptance of the new terms, thus applying estoppel - On examination of evidence, the trial judge was found to have erred in principles of contract law in her judgments on proofs of damages and misrepresentation. (Paras 12, 13, 19, 37, 60)

(B) Estoppel - Applicability - The court ruled that accepting reduced fees and continuing operations indicated agreement to those terms, thereby applying the doctrine of estoppel against the plaintiff regarding any claims of loss post-acceptance. (Paras 12, 26, 29, 40)

(C) Evidence Assessment - The court found that the trial judge failed to appreciate the principles set out in the Contracts Act, resulting in wrongful awards to the plaintiff due to insufficient proof of damages. (Paras 41, 52, 59)

Facts of the case:
The plaintiff entered into a Timber Extraction Agreement with the defendant, who later unilaterally reduced contract fees, which led to the present dispute regarding alleged loss and damages from misrepresentation and contract breach. The defendant counterclaimed over plaintiff's failure to meet production limits.

Findings of Court:
The defendant's appeal was allowed, the trial judge's decisions were set aside regarding the plaintiff's claims, while the counterclaim findings were affirmed.

Issues: The main issues of whether the Collateral Agreement existed and if the defendant breached the contract by reducing fees were addressed, along with the evidentiary burden of proof for damages.

Ratio Decidendi: The court established that the plaintiff's acceptance of reduced contract fees amounted to estoppel against making claims of loss. The failure to prove damages adequately led to the dismissal of the plaintiff's claims.

Result: Defendant's appeal allowed, cross-appeal dismissed.

Table of Content
1. introduction of the appeal and parties involved. (Para 1 , 2 , 3)
2. background facts of the agreements and disputes. (Para 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11)
3. issues agreed upon for trial. (Para 12 , 13)
4. court decision on plaintiff's claims (Para 14)
5. arguments from both parties regarding contract breaches and misrepresentation. (Para 16 , 18)
6. contentions and appeals by parties (Para 17)
7. standards for appellate intervention on fact-finding. (Para 19 , 20)
8. standards for appellate intervention (Para 21 , 22)
9. estoppel principles in contract law (Para 24 , 25)
10. application of estoppel and elections under the contracts act. (Para 29 , 34 , 39 , 41)
11. application of contracts act 1950 (Para 33)
Raus Sharif PCA:

Introduction

[1] This is an appeal by the appellant against the decision of the learned High Court Judge dated 20 August 2010 allowing the respondent's claim in part and dismissing the appellant's counterclaim against the respondent. Aggrieved by the High Court decision the respondent in turn had also filed a cross-appeal.

[2] The appellant is the defendant and the respondent is the plaintiff. For convenience parties will be referred to as plaintiff and defendant, as in the trial Court.

[3] The plaintiff 's claim against the defendant in the High Court was for loss and damages caused by breach of a purported Collateral Agreement and/ or a Timber Extraction Agreement dated 13 October 2000 entered between the plaintiff and the defendant. The defendant's counterclaim was for special damages by reason of the plaintiff 's failure to achieve the Monthly Production Limit (MPL) as stated in the Timber Extraction Agreement.

Background Facts

[4] The facts may be briefly set out as follows. The defendant is the licensee under the Timber License No T/3148 at Ulu Baleh, Kapit Division, Sarawak. ("concession area"). Initially, the defendant had engaged the services of a company known as Unique Evergreen Sdn Bhd ("Unique Evergreen") as their main contractor to fell, extract and harvest timber logs from the concession area and thereafter to transport the timber logs to a transit camp and then to Putai Logpond in the vicinity of Ulu Baleh, Kapit Division.

[5] On or about 27 September 2000, the defendant informed the plaintiff that Unique Evergreen would be terminating their contract with the defendant and the defendant was desirous to appoint the plaintiff as their main contractor in place of Unique Evergreen . Pursuant thereto, it was the plaintiff 's pleaded case that it had entered into a Collateral Agreement, partly orally, partly in writing and partly by conduct with the defendant on the following terms:

5.1 the defendant will enter into a Timber Extraction Agreement appointing the plaintiff as their main contractor to replace Unique Evergreen for the timber operations;

5.2 the defendant will sell a total of fourteen machineries to the plaintiff to be used for the timber operations; and the defendant will ensure the plaintiff would make a net profit after making payments of various overheads;

5.3 the defendant will ensure that the income from the timber operation to be generated through sufficient volume to be allowed in the MPL, would be sufficient for the plaintiff to make a net profit after making payment of various overheads, in particular, the repayment of the machineries.

[6] The plaintiff maintained at all material times that it was as a result ofthe abovementioned Collateral Agreement that the plaintiff entered into the Timber Extraction Agreement dated 13 October 2001 with the defendant. The salient terms of the Timber Extraction Agreement are these:

The main contractor warrants and represents that they are experienced logger to fell and extract and harvest hill timber logs in Sarawak and has inspected the said concession area and thereby satisfied that it is in a position capable and interested to operate and fulfill the needs of the licensee"

The main contractor is also an experienced log transportation opera