2009 MarsdenLR 1459

COURT OF APPEAL PUTRAJAYA
ASIAPOOLS (M) SDN BHD – Appellant
Versus
IJM CONSTRUCTION SDN BHD – Respondent
[Civil Appeal No: W-04-167-2006]



Payment obligations under a subcontract are contingent on the main contractor receiving payment from the employer, as dictated by 'pay when paid' provisions.

Headnote:(A) Contract Law - Sub-Contracts - The provisions of cl 13.01 of the sub-contract allow for payment only upon receipt by the main contractor from the employer, affirming the 'pay when paid' principle. The court affirmed the High Court's ruling disallowing immediate payment to the plaintiff due to non-receipt from the employer. (Paras 13, 26, 50)

(B) Legal Principles - The contractual interpretation must reflect the parties' mutual intention as expressed in the written terms, without reliance on pre-contractual negotiations. The nature of a 'pay when paid' clause necessitates actual payment for liability to arise. (Paras 40, 51)

Facts of the case:
The plaintiff successfully executed sub-contract works for a condominium, but the defendant failed to pay fully due to the employer's non-payment. A claim of RM212,989.25 was filed by the plaintiff. The Sessions Court initially ruled in favor of the plaintiff, but the High Court allowed the defendant's appeal, requiring repayment to the defendant. (Paras 5-6, 26)

Findings of Court:
The High Court's decision was upheld, confirming that payment obligations under the sub-contract occurred only after payment was received from the employer. (Para 26)

Issues: Whether the defendant is obligated to pay the plaintiff without first receiving payment from the employer and the proper interpretation of 'progress payments' as referenced in the contract. (Paras 14, 26)

Ratio Decidendi: The court determined that 'progress payment' encompasses final payments within the scope of the sub-contract, valid only upon receipt from the employer, thereby emphasizing that contractual obligations are strictly determined by the contract's language. (Paras 14, 40)

Result: Appeal dismissed with costs.

Table of Content
1. facts of the case and parties involved. (Para 1 , 5 , 31)
2. arguments regarding payment obligations. (Para 6 , 7 , 11 , 12)
3. court's analysis of case law on contract clauses. (Para 8 , 9 , 10 , 13)
4. precedents from other jurisdictions on payment clauses. (Para 19 , 20 , 21)
5. final decision regarding payment liability. (Para 25 , 27 , 28)
6. interpretation of contractual clauses. (Para 50 , 52)
Low Hop Bing JCA:

Appeal

[1] Parties are referred to in their capacities in the Sessions Court.

[2] The Kuala Lumpur Sessions Court had allowed the plaintiffs claim with costs against the defendant.

[3] The defendants appeal to the High Court was allowed with costs. The High Court made a further order that the judgment sum of RM271,458.29, paid by the defendant to the plaintiff, be returned to the defendant, together with interest at 8% p.a.

[4] The plaintiff has now appealed to this Court.

Finding Of Facts

[5] The facts at the trial are not in dispute. The plaintiff was the nominated sub-contractor to build, inter alia, a swimming pool for a 161-unit condominium in Seremban. The defendant had earlier entered into a main contract with the developer ("the employer"), Ng Chee Yew Sdn Bhd, to build the condominium as the main contractor The plaintiff had completed the swimming pool, but has not been paid fully by the defendant, as the employer had not paid the defendant. Pursuant to the main contract, the defendant has commenced an action against the employer to recover the sum of RM1,749,762.08. Under the sub-contract, the plaintiff had filed the claim in the Sessions Court for the unpaid sum of RM212,989.25.

Reliance On Main Contract

[6] In the instant appeal, the plaintiffs learned counsel Mr Oh Teik Keng cited Ryoden (M) Sdn Bhd v. Syarikat Pembenaan Yeoh Tiong Lay Sdn Bhd, 1991 MarsdenLR 1488 HC, and argued that the defendant is not entitled to rely on the main contract in order to defer the defendants liability to pay the plaintiff.

[7] Learned counsel Mr T Shanmugaraj contended that the defendant did not attempt to rely on the main contract.

[8] In our view, the defendants stand has rendered Royden, supra, irrelevant.

[9] Be that as it may, we observe that in Ryoden (M) Sdn Bhd, supra, the defendant was employed by the employer as the main contractor for the construction of a project, Raintree Terrace. The defendant and the plaintiff entered into two sub-contracts to supply, inter alia, air-conditioning and ventilation systems Clause 2 thereof required the plaintiff to observe all the provisions of the main contract only so far as they are related and applicable to the sub-contract works and were not repugnant to or inconsistent with the express provisions of the sub-contract. The plaintiff alleged that the defendant had failed or refused to pay the plaintiff certain progress payments notwithstanding that such payments were duly certified by the authorized architect of the project. The plaintiff instituted the action against the defendant. The learned registrar entered summary judgment against the defendant under O 14 of the Rules of the High 1980. On appeal to judge in chambers, the defendant argued that the defendant was not indebted to the plaintiff on the grounds, inter alia, that cl 27(a)(vii) of the main contract specially provided that payment would be made only within 14 days after the receipt by the defendant from the employer of the amounts stated in the architects certificate. Clause 27(a)(vii), which is a "pay when paid" clause, was not expressly stated in the two sub-contracts. Lim Beng Choon J (as he then was) distinguished Brightside Mechanical & Electrical Services Group Ltd v. Hyundai Engineering & Construction Co Ltd; 1988 MarsdenLR 1027, 1988 MarsdenLR 568, supra, as the wordings used in cl 11 in the sub-contract therein were different from cl 11 and cl 2 in Ryoden, supra .

[10] We must stress here that the reliance by the main contractor on the main contract, in particular cl 27(a)(vii), in Ryoden, supra, d

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance