SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 MarsdenLR 1216

SESSION COURT SHAH ALAM
LIAN THNG KAIH – Appellant
Versus
GOFLEX DESIGN & RENO SDN BHD – Respondent
[Civil Suit No: BA-A52-31-02/2020]



Petitioner Advocates:RV Lingam ,Respondent Advocate: April Tay,Pey Shau Xuan

The plaintiff waived the right to claim liquidated damages due to prior agreement and failed to provide sufficient evidence for claims of breach and defects.

Headnote:(A) Contracts Act 1950 - Sections 56(1) and 75 - Evidence Act 1950 - Section 18(1) - Breach of contract - Plaintiff claimed liquidated damages and costs for incomplete renovation works by Defendant - Court found that Plaintiff waived penalty charges and contributed to delays - Defendant's counter-claim dismissed for lack of evidence. (Paras 17, 51, 81)

(B) Liquidated Damages - Waiver - The court ruled that the Plaintiff's actions indicated a waiver of the right to claim liquidated damages due to prior agreement between the parties. (Paras 52, 56)

(C) Time is of the Essence - The court determined that time was not of the essence after the Plaintiff allowed further delays and variations, thus affecting claims for damages. (Paras 65, 66)

(D) Burden of Proof - The court emphasized that the Plaintiff failed to provide sufficient evidence to substantiate claims for damages or defects, leading to the dismissal of the claims. (Paras 78, 79)

Table of Content
1. contractual obligations and payments (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12)
2. defendant's counter-claims and defenses (Para 13 , 14 , 15 , 16)
3. plaintiff's claims and arguments (Para 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28)
4. defendant's arguments and counterclaims (Para 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50)
5. court's analysis and findings (Para 51 , 52 , 53 , 54 , 55 , 56 , 57 , 78 , 79 , 80)
Yong Leou Shin SCJ:

A. Background Facts

[1] The Plaintiff engaged the Defendant M/S Goflex Design & Reno Sdn Bhd (Contractor) to do renovation works in the Plaintiff's house having an address as No 46A, Jalan Merah Mawar U9/6, Kayangan Height, 40150 Shah Alam, Selangor.

[2] The Defendant issued a quotation dated 17 October 2018 together with the scope of work that has to be completed by the Defendant where the whole sum for the contract for the renovation of the said house was RM299,050.50.

[3] The Defendant further issued a "Variation Order" dated 7 November 2019 for the sum of RM55,843.60 for the additional work to be done which was disputed by the Plaintiff.

[4] The Plaintiff have accordingly paid the sum of RM258,000.00 to the Defendant as payment for the works done by the Defendant.

[5] Plaintiff claimed that the Defendant have failed, refused and/or neglected to complete the renovation works as promised according to the specifications and part of the works done were defective.

[6] Due to the delay in the completion of the work by the Defendant, the Plaintiff on 16th of September 2019 had a meeting with the Defendant and issued a letter dated 17 September 2019 (the said letter) to provide a further extension of time to complete the said renovation works until 1st of October 2019 with the condition that the Defendant has to pay a sum of RM1000.00 per day as penalty/liquidated damage if the Defendant failed to complete the said renovation work on or before the 1st of October 2019.

[7] The Plaintiff's wife and one of the Directors of the Defendant Mr Bryant Wan Kah Jun ("SD-3") then executed the said letter as shown at p 61 of Bundle-B.

[8] Plaintiff claimed that the Defendant till to-date has failed, refused and/or neglected to complete the said renovation works as agreed and failed to deliver possession of the house to the Plaintiff at the promised time which is on or before the 1sf of October 2019.

[9] On the 17th of January 2020 the Plaintiff then instructed his solicitors Messrs R.V. Lingam & Co to send a Notice of Termination to the Defendant to stop all renovation works being done by the Defendant with immediate effect, [reference is made to pp 73 to 76 of Bundle-B]

[10] The Plaintiff in the Notice of Termination claimed the penalty/liquidated damage (RM 1,000.00 per day) as agreed by both parties calculated as follows:

[11] Further, the Plaintiff alleged that they had engaged other Independent Contractors to rectify the defective works done by the Defendant and to complete the unfinished work of the Defendant and have paid the total sum of RM74,562.50 to those contractors.

[12] As a consequence of the alleged breach of the contract by the Defendant, the Plaintiff claimed that they have suffered loss, damage and inconvenience and therefore the Plaintiff filed this action against the Defendant and claimed the following:

(i) The sum of RM107,000.00 being the agreed penalty and/or liquidated damage;

(ii) The sum of RM74,562.50 being the payments made to the Independent Contractors to complete the unfinished work and to rectify the defects caused by the Defendant;

(iii) Interest of 5% per annum from the date of Judgment until the date of realisation and

(iv) Costs.

[13] The Defendant denied the above claim and filed in their Defence stating briefly the follows:

(i) During the renovation work, the Defendant had also issued several variation orders to the Plaintiff which were dated 12 September 2019, 16 September 2019, 23 September 201

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top