SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2011 MarsdenLR 2174

FEDERAL COURT PUTRAJAYA
DAMANSARA REALTY BHD – Appellant
Versus
BUNGSAR HILL HOLDINGS SDN BHD & ANOR – Respondent
[Civil Appeal No: 02( )-5-2011 (W)]



In commercial contracts, time is deemed of the essence unless explicitly stated otherwise; failure to develop property as stipulated constitutes a breach justifying contract termination.

Headnote:(A) Contracts Act 1950 - Sections 47 and 56(1) - Property Development Agreement - Termination of contract - The court affirmed the decision that the plaintiff's prolonged delay in commencing development constituted a breach entitling defendants to terminate the agreement, ruling time was of the essence. (Paras 9, 32, 70)

(B) Commercial Contracts - Time is of the essence - The court determined that the Property Development Agreement required completion of works within the stipulated timeframe and rejected the plaintiff's interpretation of leisurely development. (Paras 9, 31, 32)

(C) Interlocking Agreements - The argument that multiple agreements executed simultaneously were interlocked and should be treated as a single transaction was dismissed, as each agreement was held to be separate. (Paras 15, 20)

Facts of the case:
The plaintiff entered into a Property Development Agreement with the first defendant, granting development rights over land for fifteen years. The plaintiff failed to develop the land leading to termination by defendants. (Paras 6-8)

Findings of Court:
The court found that time was of the essence in the Property Development Agreement, and the plaintiff's failure to act justified the termination. (Paras 31, 70)

Issues: Whether the plaintiff was required to continuously develop land, whether time was of the essence, and the validity of the termination notice. (Paras 8, 12, 43)

Ratio Decidendi: The court ruled that conducting no development for thirteen years constituted a material breach, justifying the defendants' actions to terminate the contract under the guidance that time was deemed of the essence in commercial agreements, regardless of explicit clauses. (Paras 9, 12, 32)

Result: Appeal dismissed with costs.

Table of Content
1. leave granted for appeal and key facts highlighted. (Para 1 , 2 , 3 , 5 , 6)
2. dispute pertains to the requirement for continuous development. (Para 7 , 8 , 9 , 10)
3. the interpretation of the pda as a stand-alone contract. (Para 12 , 19 , 30)
4. arguments regarding interlocking agreements. (Para 15 , 16 , 25)
5. obligations under s 47 of the contracts act. (Para 33 , 41)
6. validity of the termination notice. (Para 42 , 46)

[1] On 26 January 2011, leave was granted to appeal against the decision of the Court of Appeal given on 29 October 2009. Six questions were posed for our consideration. We heard the appeal on 14 June 2011. We reserved our decision to consider the points raised by the parties. We now give our judgment.

[2] For convenience, in this judgment the appellant is referred to as the plaintiff and the respondents collectively as the defendants. Where necessary, the defendants will respectively be referred to as either the first defendant or the second defendant.

[3] In coming to its decision, the Court of Appeal by majority upheld the judgment of the High Court given on 22 June 2009 dismissing the action of the plaintiff.

[4] For the reasons given below, we dismiss this appeal with costs. We uphold the decision of the learned High Court Judge as affirmed by the majority in the Court of Appeal that the defendants were justified in terminating the contract.

Brief Background Facts

[5] The courts below have thoroughly dealt with the facts in this case. (See: [2009] 9 CLJ 317 HC and [2011] 4 CLJ 16 CA). Hence, we need only to highlight the relevant and pertinent facts for the purposes of this appeal.

[6] An agreement termed as the Property Development Agreement ("PDA") was entered into by the parties concerning 15. 5 acres of land ("the Development Property") located in Damansara Heights. It is not in doubt that the Development Property belongs to the first defendant. Under the said PDA, the plaintiff was given development rights over the Development Property for fifteen (15) years, commencing from 4 July 1994. It is common ground that the plaintiff does not have any interest in the land, be it legal or equitable. All the plaintiff had over the property was development rights.

[7] Upon the execution of the PDA, the plaintiff did not make any effort to commence development on the Development Property. It is not in doubt that the plaintiff failed to take any proactive measure to develop the said land. In consequence, by letter dated 25 October 2007, the defendants issued a termination notice to the plaintiff, citing the latter's failure to develop the Development Property as a material breach under the PDA and/or a repudiation of the same. As such, it was declared that the PDA would effectively terminate on 25 November 2007. It is not in doubt that the termination notice was issued some thirteen and a half (13 ½) years into the subsistence of the PDA.

[8] The gist of the dispute between the parties is this - whether the plaintiff was required to continuously develop the Development Property over the span of fifteen years or whether the plaintiff was at liberty to commence development as and when it felt the time was right so long as it had commenced work within the 15 years period. It is to be noted that only upon service of the termination notice did the plaintiff take some steps towards initiating the development works. However, these efforts did not eventually materialise.

[9] The plaintiff commenced an action against the defendants for wrongful repudiation. The High Court dismissed the action. The learned High Court Judge, having carefully scrutinised the PDA, found, inter alia, that as the PDA was a commercial contract, it ought to be construed in a commercially sensible manner which the parties all along intended for time to be of the essence. As such, in his view, it was reasonable to assume that the parties intended to have the whole Development Property land developed within the time period of fiftee

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top