2020 MarsdenLR 2605

COURT OF APPEAL PUTRAJAYA
LIANBANG VENTURES SDN BHD – Appellant
Versus
JURUKUR PERUNDING SERVICES SDN BHD & ANOR – Respondent
[Civil Appeal No: M-04(NCVC)(W)-507-10-2018]



Important Points

Termination of a surveyor's contract without lawful reason entitles the surveyor to damages despite non-compliance with deposit regulations, as the contract remains valid.

Subject

Contract Law - Breach of Contract

Act Referred

Contracts Act: S.24
Licensed Land Surveyors Regulations: S.26(1)

Headnote

(A) Contracts Act, 1950 – Section 24 – Licensed Land Surveyors Regulations 2011 – Reg 26(1) – Dispute over contract for strata title survey – Appellant unlawfully terminated surveyor's contract – Plaintiffs entitled to damages for works done – Contract not rendered illegal by non-payment of deposit fee. (Paras 1-56)

(B) Appeal – Standard of review – Findings of fact by trial judge are entitled to deference; appellate courts should be slow to interfere unless the findings are perverse. (Paras 56)

Facts of the case: The plaintiffs, a surveying firm, were engaged by the defendant to conduct survey works for a development project. Disputes arose regarding payment and the defendant terminated the contract without justification after several service requests. (Paras 1-10)

Findings of Court: The Court upheld the decision that the plaintiffs were entitled to claim damages as the contract was valid and their services had been unlawfully terminated. (Paras 56)

Issues: The main issues were whether the termination of the contract was lawful, the validity of the survey works, and the application of regulatory deposit requirements. (Paras 8-19)

Ratio Decidendi: The plaintiffs’ claim is valid as the termination was unlawful; non-payment of survey fees before work commenced did not render the contract illegal or void. (Paras 32-34)

Result: Appeal dismissed with costs. (Paras 56)

Petitioner Advocates:V Sithambaram,Wong Fook Meng,Ruebankumar Asokan ,Respondent Advocate: Yusri Farid Mat Sood,Mohd Omar Nathan Abdullah

JUDGMENT

Kamaludin Md Said JCA:

Introduction

[1] This is the appellant's appeal against the decision of the High Court of Melaka in dismissing the appellant's appeal against the respondents.

[2] This appeal emanates from the decision of the Sessions Court of Melaka in partially allowing the respondents' claim against the appellant, amongst others, a declaration that the appellant had unlawfully terminated the respondents' service for strata title application and dismissing its counterclaim.

[3] For ease of reference, we will refer to the appellant as the defendant and the respondents as the plaintiffs in this appeal, as they were in their original capacities in the trial Court below.

The Salient Facts

[4] The 1st plaintiff is a licensed land surveying private company providing, amongst others services in land surveying. The 2nd plaintiff is a licensed land surveyor and a director of the 1st plaintiff company.

[5] The defendant is a housing and property developer and was responsible for the development of Dataran Pahlawan Melaka ("the Development").

[6] The plaintiffs alleged that by agreement between both parties, the defendant appointed the plaintiffs to do the survey works and application for strata title in respect of the defendant's Development project. The 1st plaintiff started carrying out the survey works in 2007.

[7] By a letter of appointment dated 21 March 2008, the defendant had officially engaged the plaintiffs' service for the purposes of carrying out land survey works and the application for strata title for the defendant and the defendant agreed to pay any costs incurred for the said service.

[8] The plaintiffs alleged that they had carried out the survey works. However, the application for strata title could not be completed because the boundary of the land title has not been finalised. The defendant was required to deposit surveyor's fee for purpose of submitting the proposed strata title. The deposit fee to the Land Surveyors Board is pre-condition before the survey works can commence. Despite numerous requests, the defendant failed to pay the deposit fee to the Land Surveyors Board.

[9] The defendant terminated the plaintiffs' service on 3 April 2014 without giving any reason for the termination. The 1st plaintiff had requested the defendant to provide the reason for the termination. The plaintiffs claimed fee for 80% of the survey works which were carried out on the instructions of the defendant.

[10] The plaintiffs commenced this action in the Sessions Court of Melaka inter alia, for:

(i) A declaration that the defendant had unlawfully terminated the plaintiffs' service;

(ii) Special damages in the sum of RM592,454.01 that approximately 80% of the Survey Works/works have been completed; and

(iii) Special damages in the sum of RM25,000.00 being the estimated claim in providing service for air space permit application.

[11] The defendant filed a counterclaim against the plaintiffs for general damages as a result of the plaintiffs' breach of contract by failing to carry out the application for strata title in respect of the Development.

[12] The learned Sessions Court Judge allowed the plaintiffs' claim and as to damages, half of the plaintiffs' claim for deposit fee on the assumption that the plaintiffs had carried out 50% of the Survey Works was awarded. The learned Sessions Court Judge allowed the sum of RM370,233.76 with interest and Costs to the plaintiffs. The defendant's counterclaim was dismissed by the learned Sessions Court Judge.

[13] The defendant appealed to the High Court and the appeal was dismissed with Costs and the judgment of the Sessions Court was upheld.

Decision Of The Sessions Court

[14] The learned Sessions Court Judge having evaluated the evidence before him came to a finding of fact that the plaintiffs were appointed by the defendant to carry out survey works for the purposes of strata title application. The Court accepted the evidence of SP3 and SP4 as opposed to the evidence of SD2 who is an interested