2023 MarsdenLR 1988

COURT OF APPEAL PUTRAJAYA
JAKS RESOURCES BERHAD – Appellant
Versus
STAR MEDIA GROUP BERHAD & OTHER APPEALS – Respondent
[Civil Appeal Nos: W-02(IM)(NCVC)-1122-08-2020 W-02(IM)(NCVC)-1188- 09-2020 & W-02(IM)(NCVC)-1435-10-2020]



Important Points

The finding of a judge in an interlocutory application regarding a construction contract's completion date is not binding on subsequent litigation, allowing for full trial on contested material facts.

Subject

Civil Law - Contract Law

Act Referred

Rules of Court 2012: S.O 14A, S.O 18 r 19, S.O 81

Headnote

(A) Arbitration Act 2005 - Section 8 and 11 - Rules of Court 2012 - Order 14A - Construction contract - Dispute regarding completion date and validity of call on Banker's Guarantee - High Court's finding on completion date not binding in subsequent suit due to lack of finality - Res judicata and issue estoppel not applicable - Remitted for trial. (Paras 130-132)

(B) Legal principles - Res judicata - Requires final determination of issues - Tentative findings in interlocutory applications do not preclude later litigation - Unconscionability standard for injunctions to restrain calls on Bank Guarantees. (Paras 36, 62, 70)

(C) Issues of fact and law - Multiple disputes necessitate full trial - Summary disposal inappropriate where material facts are contested. (Paras 82-89)

(D) Findings of Court - High Court’s decision to strike out Defence and Counterclaim not justified; appeals allowed, remitted for trial. (Paras 131-132)
Judgement Key Points

Key Points: - The Court of Appeal held that findings on Extended Completion Date in Originating Summons are not binding final determinations for res judicata/issue estoppel in underlying suits; such findings are interim and not final (!) (!) (!) . - Interlocutory determinations (O 14A applications) are inappropriate where there are material disputes of fact requiring viva voce evidence; full trial is necessary to resolve underlying disputes (!) (!) (!) . - The orders remitted the suits for trial, rejecting summary disposal under O 14A where multiple disputes of fact remain and the underlying contract merits are not finally decided (!) (!) (!) . - Unconscionability and related tests for restraining calls on Bank Guarantees are recognized but not determinative where final merits are contested; such rulings do not preclude later trials on the merits (!) (!) (!) . - The deemed completion provision (cl 16.4) and its interpretation require full consideration of the SPA's overall structure at trial, not just interim findings (!) (!) (!) . - The Court references that res judicata requires final determination; interim findings in OS 11/OS 12 cannot foreclose later litigation of underlying disputes (!) (!) (!) .

How to determine whether a finding of a judge in an interlocutory application restraining a Bank Guarantee is binding on subsequent disputes in separate suits?

How to determine whether an interlocutory ruling on completion date can support res judicata or issue estoppel in later full trials?

What is the appropriate scope of O 14A ROC where material facts are in dispute and a full trial is necessary to resolve underlying construction contract disputes?


Petitioner Advocates:Gopal Sri Ram,Wong Rhen Yen,Emily Wong Li Yan,Marcus Lee Min Lun ,Respondent Advocate: Wong Guo Bin,Sophia Hoo Tsin Ai,Tharminder Singh,Daryl Kirk

Table of Content
1. determination of binding nature of findings in construction disputes. (Para 1 , 2 , 3)
2. background of sale and purchase agreement and obligations. (Para 4 , 5 , 6 , 8 , 9 , 10)
3. disputes over completion date and vendor's entitlement. (Para 11 , 12 , 14 , 15 , 18 , 20)
4. high court's findings and implications on ongoing disputes. (Para 22 , 23 , 24 , 25)
5. arguments presented in appeals regarding procedural appropriateness. (Para 26 , 27 , 28 , 29)
6. res judicata and its applicability in construction disputes. (Para 30 , 31 , 32 , 33)
7. importance of factual disputes in determining legal outcomes. (Para 34 , 35 , 36 , 37)
8. court's role in assessing claims and counterclaims in construction contracts. (Para 38 , 39 , 40 , 41)
9. interim measures and their limitations in arbitration contexts. (Para 42 , 43 , 44 , 45)
10. finding of fact in interlocutory applications and its binding nature. (Para 46 , 47 , 48 , 49)
11. interpretation of 'deemed' provisions in contracts. (Para 50 , 51 , 52 , 53)
12. finality of decisions in interlocutory proceedings. (Para 54 , 55 , 56 , 57)
13. res judicata's limitations in interim findings. (Para 58 , 59 , 60 , 61)
14. need for full trial in complex construction disputes. (Para 62 , 63 , 64 , 65)
15. final decision on appeals and remittance for trial. (Para 66 , 67 , 68 , 69)
Lee Swee Seng JCA:

[1] The key issue in these 3 related appeals hovers around whether a finding of the learned High Court Judge with respect to the extended completion date in a construction contract in an Originating Summons taken out to restrain the call on a Banker's Guarantee ("BG") is binding on the parties and its privies in the underlying construction disputes between them. The underlying disputes before the High Court are in 2 separate suits where the parties have claims and a counterclaim in one of them.

[2] Related to the above issue is whether the parties' disputes are amenable to a disposal by way of an application under O 14A Rules of Court 2012 (" ROC "). One learned Judge in a suit before her thought so as substantially all issues arising from the construction dispute would be resolved by reference to the extended completion date as decided by a previous High Court Judge when hearing the Originating Summons and dismissing it and thus dismissing the injunction to restrain the call on the BGs.

[3] Another learned High Court Judge before whom another related suit was filed apparently did not think so as there are multiple issues of fact and law that would require a trial to unravel.

[4] The genesis of the disputes between the parties can be traced to a Sale and Purchase Agreement ("SPA") entered into on 19 August 2011 by JAKS Island Circle Sdn Bhd ("JIC") with Star Media Group Berhad ("Star Media") as part of a joint development between the parties for JIC to build a mixed residential and commercial development on Star Media's land. Based on the agreed terms, Star Media agreed to sell a piece of land located in Petaling Jaya, Selangor ("the said Land") to JIC for RM135 million. JIC paid RM500,000.00 to Star Media as deposit and part payment for the said Land. The balance purchase price of RM134.5 million was agreed to be paid by way of JIC delivering the "Vendor's Entitlement" to Star Media in lieu of monies. See: SPA cl 4.1 at p 15 Appellant's Core Bundle of Documents ("ACB(D)").

[5] The Vendor's Entitlement is defined in the SPA as the delivery of vacant possession, Issued Document of Title and Certificate of Completion and Compliance of Tower A and the right of Star Media to rent certain number of car park bays from JIC. See: SPA cl 1.1 at p 12 ACB(D).

[6] It was a term of the SPA that JIC was also to procure a BG for RM50 million which JIC did from Ambank (M) Berhad ("Ambank") and United Overseas Bank (Malaysia) Berhad ("UOB") in the sum of RM25 million each, both in favour of Star Media which JIC did on 8 November 2013. See: BGs dated 8 November 2013 at pp 118-130 ACB(D).

[7] The ultimate holding compa

1
2
3
4
5
6
7
8
9
10
11