SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 3218

HIGH COURT MALAYA KUALA LUMPUR
MAJLIS AMANAH RAKYAT – Appellant
Versus
PERNEC INTEGRATED NETWORK SYSTEMS SDN BHD – Respondent
[Civil Appeal No: WA-12BNvC-66-06/2024]



Petitioner Advocates:Adam Luqman ,Respondent Advocate: Roger Leong

The legal standard for unconscionability requires the demonstration of oppressive conduct or bad faith; merely citing delays is insufficient to warrant an injunction against a performance bond call.

Headnote:(A) Performance Bond - Unconscionability - Balance of Convenience - An injunction against the appellant from claiming the Performance Bond was granted by the Sessions Court, which the appellate court found to have misapplied the law regarding unconscionability and the balance of convenience. The court emphasized that delays caused by the respondent did not justify the injunction, and the performance bond could be called without establishing a breach. (Paras 7, 24, 25)

(B) Legal Standard for Unconscionability - The court clarified that mere delays in performance do not establish unconscionability unless there is clear evidence of bad faith or oppressive conduct. The burden of proof rests on the party seeking to restrain the bond call. (Paras 10-13)

(C) Balance of Convenience - The appellate court highlighted that damages could serve as an adequate remedy for the respondent, while the injunction unjustly restricted the appellant’s rights. (Paras 18-19)

Table of Content
1. issues before the court in the appeal (Para 1 , 2)
2. factual background of the performance bond dispute (Para 3 , 4 , 5 , 6)
3. outcome of the sessions court's decision (Para 7)
4. arguments presented by mara and pernec (Para 8 , 9)
5. court's analysis of the unconscionability criterion (Para 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17)
6. balance of convenience assessment (Para 18 , 19)
7. issues related to delays and acceptance of eots (Para 20 , 21)
8. appellate intervention standards (Para 22 , 23)
9. conclusion of the appeal and ruling (Para 24 , 25)
Roz Mawar Rozain J:

[1] This is an appeal by the Appellant (MARA) against the decision of the Sessions Court dated 31 May 2024, which granted an injunction in favour of the Respondent (PERNEC) restraining MARA from claiming the Performance Bond (Jaminan Bank-i No 56752202740001) of RM778,630.00 issued by Affin Islamic Bank Berhad (the Bank), pending full disposal of the dispute in Court.

[2] The primary issues before this Court are:

(a) whether the Sessions Court erred in holding that MARA's call on the Performance Bond was unconscionable;

(b) whether the balance of convenience favours the grant of an injunction;

(c) whether there was sufficient evidence of delay attributable to MARA, justifying the injunction.

Factual Background

[3] The dispute arises from the MARA Total Campus Management System contract, awarded to PERNEC under a Service Agreement dated 15 August 2021. The project development period was fixed for 24 months which began on 5 November 2020 and was to end on 4 November 2022. There were timelines of when Go Live Phase 1 was to be completed on 10 December 2021 and Go Live Phase 2 on 4 October 2022. The Bank had issued the Performance Bond of RM779,630.00 in favour of the Appellants.

[4] According to correspondences and the PERNEC's request for an extension of time (EOT), MARA agreed on 17 December 2021 to grant PERNEC an extension to 4 September 2023. The timeline for Go Live Phase 1 was extended to 30 November 2022 and Go Live Phase 2 on 17 July 2023. The supplementary agreement was executed on 27 July 2022.

[5] Due to yet another delay, MARA issued several reminders. An ICT Development Committee Meeting was convened on 2 March 2023 when MARA had again agreed to give another extension of time to PERNEC where the Go Live Phase 1 then stretched to 29 August 2023 and Go Live Phase 2 on 4 September 2023 which was the deadline as agreed earlier in the 1st EOT. This second agreement (2nd EOT) was executed on 28 August 2023.

[6] Even after the 2nd EOT, MARA issued multiple Notices of Delay and Non-Performance to PERNEC that culminated in a Notice to Remedy under Clause 15.1(a) of their contract, until eventually, the project completion deadline of 4 September 2023 had lapsed. MARA followed by a Notice of Termination on 26 October 2023. On 31 January 2024, MARA sought to claim the Performance Bond, prompting PERNEC to file an injunction application, which the Sessions Court granted, preventing MARA from enforcing the bond.

Decision Of The Sessions Court

[7] The Sessions Court granted the injunction in favour of PERNEC which injuncts MARA from making any claim on and receiving any payment under the Performance Bond from the Bank until the resolution of the dispute. It was found that the delays in project completion were partly caused by MARA. The Sessions Court concluded that the balance of convenience favoured PERNEC, as the bond call would irreparably harm its financial standing. It wanted to maintain the status quo as it opined that the disputes on liability should be fully adjudicated in a trial before MARA could enforce the bond.

This Appeal

[8] In imploring this Court to allow its appeal, MARA argued that the Performance Bond is an on-demand bond, and MARA is entitled to call on it. MARA submitted that the Sessions Court misapplied the law on unconscionability and balance of convenience, and the injunction was wrongly granted as PERNEC's delays were solely its fault. MARA m

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top