2025 MarsdenLR 5643

Azimah Omar, J
Davanam Constructions Sdn Bhd – Plaintiff
Versus
THP Enstek Development Sdn Bhd (formerly known as TH-NSTC Sdn Bhd) – Defendant



Advocates:
For the Appellants/Petitioners: [Not specified]
For the Respondents: [Not specified]

A party to a joint venture agreement cannot unilaterally amend essential terms without mutual consent; breach of contract can justify the termination of the agreement.

Headnote:(A) Contract Law - Joint Venture Development Agreement - The court dealt with the terminability of the Joint Venture Development Agreement (JVDA) due to breach of contract claims, focusing on whether the Plaintiff had unlawfully sought to amend the Approved Master Plan without the Defendant's consent, reflecting on mutual agreements from antecedent agreements including the 2008 Memorandum of Understanding, Framework Agreement, and Assignment Agreement. The court found that the Defendant had the right to terminate the JVDA after issuing a remedy notice and cited the Plaintiffs refusal to comply as the reason. (Paras 1, 64, 114, 118, 121)

(B) Contractual Interpretation - The court emphasized that parties must perform contractually agreed obligations and cannot unilaterally alter key contract terms without other party consent. It highlighted claims that excessive market fluctuations do not excuse performance failures nor re-write contractual obligations. (Paras 84, 116)

Facts of the case:
The Plaintiff alleged wrongful termination of the JVDA by the Defendant while failing to execute a promised iconic development because of financial constraints. Defendant maintained the Plaintiff had breached the JVDA by not adhering to the core development plan.

Findings of Court:
The Plaintiffs failure to perform allowed the Defendant to rightfully terminate the JVDA. The court dismissed both the Plaintiff's claim and the Defendant's counterclaim due to mutual breaches of contract.

Issues: Whether the Plaintiff's rights to amend the Approved Master Plan were valid and if the Defendant’s termination of the JVDA was lawful.

Ratio Decidendi: The court supported its conclusion by highlighting that the JVDA and associated agreements mandated mutual consent for amendments to essential contract terms, which the Plaintiff breached.

Result: Claim dismissed with costs awarded against the Plaintiff.

Table of Content
1. plaintiffs seek remedies for unlawful termination. (Para 1 , 2 , 3)
2. court emphasizes clarity and efficiency in presentations. (Para 4 , 5 , 6)
3. nature of agreement requires collective reading of contracts. (Para 14 , 15)
4. case hinges on unilateral amendments to approved master plan. (Para 88)
5. defendant's termination of jvda deemed valid due to fundamental breach. (Para 89 , 90 , 92 , 94 , 114 , 120)

Azimah Omar J:

GROUNDS OF JUDGMENTA. INTRODUCTION

[1]Based on its Statement of Claim, the Plaintiffs cause of action against the Defendant is primarily for declaratory reliefs to declare that the Defendant had unlawfully terminated a Joint Venture Development Agreement dated 3.07.2009 while seeking specific performance of the same. In the event that the Court was not minded to grant the relief of the specific performance, the Plaintiff alternatively sought for special damages (as specified in the Statement of Claim) and general damages either in the minimum sum of RM1,400,000,000.00 (1.4 Billion Ringgit) on the basis of an entitlement of 70% of the gross development value, or 70% of the total estimated profit.

[2]The full breadth of the remedies claimed by the Plaintiff were set out in paragraph 60 of the Statement of Claim:

60. Wherefor, the Plaintiff claims against the Defendant and prays to the Court for the following relief and Orders: -

(a)A declaration that the notice of termination issued by the Defendant dated 27.10.2016 to the Plaintiff terminating the Joint Venture Development Agreement dated 03.07.2009 (“the JVDA”) and the forfeiture of the deposit sum RM2,000,000.00 without leaving delivered vacant possession of the said Land, are null and void, a material breach of the JVDA, wrong in law and tantamounts to wrongful repudiation of the JVDA and indicates the Defendant’s intention not to be bound by the JVDA;

(b)A declaration that the Defendant pays to the Plaintiff compensation and damages for the breach of the JVDA and for the wrongful and unlawful termination of the JVDA, to be assessed by the Registrar of the Court;

(c)An Order of Specific Performance of the JVDA by the Defendant or in lieu of Specific Performance compensation and damages to be paid by the Defendant to the Plaintiff, to be assessed by the Registrar of the Court;

(d)An Order for the Defendant to pay special damages to the Plaintiff as follows: -

(i)RM2,000,000.00 being the refund of the deposit sum paid to the Defendant;

(ii)RM3,671,706.00 paid by the Plaintiff for conversion of land use and sub division;

(iii)RM4,929,222.00 paid by Plaintiff for the construction of the Detention Ponds;

(iv)RM5,000,000.00 paid by Plaintiff to Ascenteus pursuant to the terms of Assignment Agreement dated 01.07.2010 in furtherance to the stipulations of the JVDA and the Addendum;

(v)RM100,268.00 wrongfully charged and claimed by the Defendant from the Plaintiff for quit rent;

(vi)RM250.00 wrongfully claimed by the Defendant from the Plaintiff for conversion of Lot 33;

(vii)RM1,088,997.00 paid by Plaintiff for architect fees;

(viii)RM376,532.00 paid by Plaintiff for consultancy fees;

(ix)RM144,421.00 incurred by Plaintiff for exchange losses;

(x)RM12,200.00 paid by Plaintiff for facilitation fees;

(xi)RM277,200.00 paid by Plaintiff for professional charges;

(xii)RM72,298.00 paid by Plaintiff for planning services;

(xiii)RM364,282.00 paid by Plaintiff for professional management fees;

(xiv)RM19,828.00 paid by Plaintiff for soil investigation works;

(xv)RM250,471.00 paid by Plaintiff for technical services fees;

(xvi)RM62,654.00 incurred by Plaintiff for travelling expenses;

(xvii)RM135,897.00 incurred by Plaintiff for term loan interest;

(xviii)RM518,737.00 paid by Plaintiff for administration, audit, secretarial and general expenses;

(xix)RM521,680.00 paid by Plaintiff for legal fees and charges; and

(xx)RM16,239,446.00 incurred by Plaintiff for interest charges for the cost of financing to date of the project, procured from the

(xxi)financial institutions namely Religare Indi

Click Here to Read the rest of this document