SUPREME COURT OF INDIA
DHANANJAYA Y. CHANDRACHUD, M.R. SHAH, JJ.
Gujarat Urja Vikas Nigam Limited – Appellant
Versus
Mr. Amit Gupta and Others – Respondents
Civil Appeal No. 9241 of 2019
Decided On : 08-03-2021
Insolvency and Bankruptcy Code, 2016 - Section 60(5) - Electricity Act, 2003 - Sections 61(h), 62 and 86 - Purchase Agreement - Termination of PPA - Compensation - Narrative of this case begins with Government of Gujarat notifying Solar Power Policy, 20099 [“Policy”] , for development of Solar Power projects in state - Appellant, a Government of Gujarat undertaking, is a successor to Gujarat Electricity Board and is also holding company of all State Power Utilities in Gujarat - Government of Gujarat allocated a 25-megawatt capacity to the Corporate Debtor for developing and setting up a solar photovoltaic based power project in State of Gujarat - Corporate Debtor expressed its desire to setup a Solar Photovoltaic Grid Interactive Power Plant10 [“Plant”] of 10-megawatt capacity and exercised its option for sale of entire electrical energy produced from plant to the appellant for commercial purposes - Whether termination of PPA was valid, or dwelt on the interpretation of the PPA, it has still erroneously set aside the termination of PPA by the appellant without any basis under IBC – Held, appellant had served a notice of termination to Corporate Debtor with effect though termination could not be carried out due to the operation of interim protection which had been granted to the respondents by NCLT. It was contended on behalf of appellant that it cannot be made to suffer on the ground of erroneous injunctions granted by NCLT and NCLAT, due to which it had to pay a higher tariff because it could not terminate PPA with the Corporate Debtor and procure electricity at a cheaper tariff from another power producer - Since Court have set aside termination of PPA based on reasons discussed above, appellant is liable to pay for the electricity procured - Consequently, appellant’s claim in respect of compensation for termination of PPA in terms of Article 9.3.1 of PPA does not arise because it is restrained from terminating PPA - Appeal dismissed.
JUDGMENT :
DHANANJAYA Y. CHANDRACHUD, J.
(A) The appeal
1. By its judgment dated 29.8.2019, the National Company Law Tribunal1 [“NCLT” or “Adjudicating Authority”] stayed the termination by the appellant of its Power Purchase Agreement2 [“PPA”] with Astonfield Solar (Gujarat) Private Limited3 [“third respondent” or “Corporate Debtor”]. The order of the NCLT was passed in applications4 [C.A. No. 701/2019 (first respondent) and C.A. No. 700/2019 (second respondent)] moved by the Resolution Professional of the Corporate Debtor5 [“first respondent” or R.P.”] and Exim Bank 6 [“second respondent”] under Section 60(5) of the Insolvency and Bankruptcy Code, 20167 [“IBC”]. On 15 October 2019, the NCLAT dismissed the appeal by the appellant8 [“appellant” or “GUVNL”] under Section 61 of the IBC. The decision by the NCLAT is called into question.
2. The appellant assails the order dated 15 October 2019 of the NCLAT on, inter-alia, two broad grounds: first, that the NCLT and NCLAT do not possess jurisdiction under the IBC to adjudicate on a contractual dispute between the appellant and the Corporate Debtor and second, in any event, the termination of the PPA was validly made under Article 9.2.1(e) and Article 9.3.1 of the PPA.
(B) The genesis of the PPA
3. The narrative of this case begins with the Government of Gujarat notifying the Solar Power Policy, 20099 [“Policy”] on 6 January 2009, for development of Solar Power projects in the state. The appellant, a Government of Gujarat undertaking, is a successor to the Gujarat Electricity Board and is also the holding company of all the State Power Utilities in Gujarat.
4. On 1 August 2009, the Government of Gujarat allocated a 25-megawatt capacity to the Corporate Debtor for developing and setting up a solar photovoltaic based power project in the State of Gujarat. The Corporate Debtor expressed its desire to setup a Solar Photovoltaic Grid Interactive Power Plant10 [“Plant”] of 10-megawatt capacity and exercised its option for sale of the entire electrical energy produced from the plant to the appellant for commercial purposes.
5. In exercise of its powers under Sections 61(h), 62 and 86 of the Electricity Act, 200311 [“Electricity Act”] the Gujarat Electricity Regulatory Commission12 [“State Commission” or “GERC”] published a draft tariff order for purchase of solar energy, inviting comments and suggestions from members of the public and stakeholders. Public hearings were held by the State Commission on the price at which power could be procured.
6. After the process of public hearings and consultations, a Tariff Order dated 29 January 201013 [“First Tariff Order”] was issued by the State Commission for procurement of power by the appellant from power producers, under Section 86(1)(a) of Electricity Act. The tariff was determined on the basis of the then prevailing capital and financing costs, and debt equity ratio. It was envisaged that the PPA will be for 25 years, with higher tariffs in the first 12-15 years, and a scaled-down tariff for the remaining years. The tariff was to be applicable to solar projects commissioned within the control period of the First Tariff Order, i.e. from 29 January 2010 to 28 January 2012.
7. The appellant filed a petition before the State Commission on 28 May 2013, seeking initiation of proceedings for re-determination of the capital cost and tariff fixed under the First Tariff Order. This petition was filed on the basis that subsequent incentives given to power producers on 27 February 2010 had brought down their cost of capital and, as a consequence, the tariff fixed under the First Tariff Order should be revised. This petition was dismissed by the State Commission on 8 August 2013. An appeal against the order was dismissed by the Appellate Tribunal for Electricity14 [“APTEL”] on 22 August 2014. An appeal15 [Civil Appeal No. 10301 of 2014] against APTEL’s decision is pending before this Court, with notice having been issued on 28 November 2014.
8. The appellant and the
The lease agreement, license agreement, and the allotment letter should be read as coterminous contracts. The termination of the license agreement and lease deed was found to be in accordance with th....
Termination of contract by BIDA justified despite insolvency proceedings due to prior breaches by Corporate Debtor, hence moratorium protections under IBC inapplicable.
The NCLT lacks jurisdiction to adjudicate contractual disputes such as rights under Joint Venture Agreements when they do not arise from the insolvency proceedings of the corporate debtor.
The court ruled that the NCLAT erred in approving a settlement without adhering to the procedural requirements of the Insolvency and Bankruptcy Code, emphasizing the collective nature of insolvency p....
NCLT lacks jurisdiction to adjudicate disputes solely arising from contractual matters unrelated to the insolvency process.
Section 60 of Code deals with Adjudicating Authority for Corporate persons.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.